CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Spelthorne Borough Council
Corporate Policy and Resources Committee, Monday 20 April 2026 at 7.00pm

Solar Canopy Project Closure Report

Agreed Committee 3 papers

AI summarySpelthorne's Corporate Policy and Resources Committee formally ended the Eclipse Leisure Centre solar canopy project on 20 April 2026, removing a £1.32m provision and accepting a lost potential £4.9m revenue.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSolar canopy for Eclipse Leisure Centre car park
Money£1.32m removed from Capital ProgrammePlus £12,000 + VAT supplier cost paid
What happens nextPass documentation to successor unitaryBy 1 April 2027 vesting day
Who it affectsAll wardsEclipse Leisure Centre car park site

What was decided

The Committee agreed to formally end the solar canopy project for the Eclipse Leisure Centre car park, removing the £1.32m provision from the Capital Programme. Report P17, P18

Risks from ground conditions, particularly attenuation tanks not accounted for in early design work, were deemed severe enough to prevent installation. Report P10, P16

The project had already been removed from the Capital Programme following a CPRC resolution on 8 September 2025, and the formal decision confirms closure. Report P18, P21

Why

Attenuation tanks under the car park were not identified in early design, requiring a 10-week redesign by supplier 3ti and causing key integration deadlines with Phase 2 works to be missed. Report P16

Community Infrastructure Levy funding was not feasible and the project would have required additional debt financing, conflicting with the May 2025 Best Value Inspection Directives to reduce Spelthorne's debt. Report P13, P16

Local Government Reorganisation under the December 2024 Devolution White Paper means Spelthorne will cease to exist as a sovereign council from 1 April 2027, with benefits accruing to a successor authority. Report P16

What happens next

Formally close the project and avoid ongoing project management costs, including outsourcing costs following the loss of internal support. Report P15, P18

Integrate lessons learned, particularly use of a clear RACI model, knowledge sharing on underground infrastructure, and identification of critical skills early. Report P15, P16

Pass all project documentation to the successor unitary for its future consideration, including the option of future retro-fitting. Report P20, P21

The money

  • £1.32M Capital Programme provision removed for the solar canopy project Report P18
  • £4.9m Estimated potential revenue generation over 24 years that will not be realised Report P18
  • circa £16,000 + VAT Supplier 3ti's initial design costs, reduced by negotiation Report P18
  • £12,000 + VAT and £425 adjudication fee Final amount paid to supplier 3ti for design costs Report P18

Options considered

  • Chosen: Terminate the project completely due to risks, additional costs and changed funding situation. Risks deemed severe and CIL funding not feasible, conflicting with Best Value Directives to reduce debt Report P17, P18

Implications

  • Financial: Council will not carry the financial risk of the £1.32m project; avoids ongoing project management and Phase 2 contract variation costs; loses estimated £4.9m revenue over 24 years. Report P18
  • Legal: Cancellation aligns with statutory directions from the Best Value Inspection; best value duty under the Local Government Act 1999 noted; external legal advice on utilities and energy law would have been required. Report P18
  • Equalities: Decision will be implemented with care so as not to impact any particular group or organisation. Report P20
  • Climate: Loss of estimated 137 tonnes per year carbon saving that would have contributed to the Council's climate emergency commitments and scope 3 footprint. Report P21
  • Risk: All solar canopy project risks will be removed; a possible DESNZ call for evidence on mandating solar canopies for car parks may lead the successor unitary to revisit the idea. Report P18, P21

Who and where

  • Eclipse Leisure Centre users and operator Report P16
  • All wards of Spelthorne Borough Council Report P9
  • Successor unitary authority (from 1 April 2027) Report P16, P20
  • Supplier 3ti Report P16, P18

Timeline

  • July 2024: Solar canopy concept first presented to CPRC and agreed for further development Report P16
  • September 2024: Further report to CPRC with permission to go to tender Report P16
  • December 2024: Supplier 3ti awarded design and installation contract by CPRC and Full Council Report P16, P23
  • May 2025: Best Value Inspection Report and Directives published by Secretary of State Report P16
  • 8 September 2025: CPRC resolved to recommend cancellation of the project to Council Report P18
  • 20 April 2026: Committee formally agreed to end the project Report P21
  • 1 April 2027: Spelthorne Borough Council ceases to exist as a sovereign council under reorganisation Report P16

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure
  • CPRC: Corporate Policy and Resources Committee of Spelthorne Borough Council
  • RACI: Responsibility assignment matrix: Responsible, Accountable, Consulted, Informed
  • Passivhaus: A high-performance building standard focused on energy efficiency
  • Attenuation tanks: Underground structures that manage stormwater runoff
  • Phase 2 works: Demolition of the old leisure centre and construction of a new car park
  • MRTP: Mid-Term Review of the Capital Programme
  • DESNZ: Department for Energy Security and Net Zero
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item44/26

Resolved

The Committee resolved to agree to formally end the solar canopy project.
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Corporate Policy and Resources Committee

Committee Report Checklist

Please submit the completed checklists with your report. If final draft report does not include all the information/sign offs required, your item will be delayed until the next meeting cycle.

Stage 1 Report checklist – responsibility of report owner ITEM Yes / No Date Councillor engagement / input from Chair prior to Yes CNWG briefing Relevant Group Head review Yes 12/9/25 MAT+ review (to have been circulated at least 5 Yes 12/9/25 working days before Stage 2) This item is on the Forward Plan for the relevant committee Reviewed by Finance comments (circulate to Finance) Risk comments (circulate to Lee O’Neil) Legal comments (circulate to Legal team) Jo Clare 14.12.25 HR comments (if applicable)

For reports with material financial or legal implications the author should engage with the respective teams at the outset and receive input to their reports prior to asking for MO or s151 comments.

Do not forward to stage 2 unless all the above have been completed.

Stage 2 Report checklist – responsibility of report owner ITEM Completed Date rec’d by Monitoring Officer commentary – at least 5 working L Heron 27/03/26 days before MAT S151 Officer commentary – at least 5 working days T.Collier 25/3/26 before MAT Commissioner engagement J. Kingston 31/03/2026 o.b.o. Cmmrs

Delete as No issues applicable: Confirm final report cleared by MAT Corporate Policy and Resources Committee

Date of meeting 20 April 2026

Title Solar Canopy Project Closure report Purpose of the report To make a decision Report Author Tim Snook Sustainability and Resilience Lead Sandy Muirhead Group Head Commissioning and Transformation Ward(s) Affected All Wards Exempt No Exemption Reason Not Applicable Corporate Priority Community Resilience Environment Recommendations Committee is asked to: Agree to formally end the project.

Reason for The risks to the project due to issues with ground conditions in Recommendation the car park were deemed to be severe enough as to impact the installation of a solar canopy for the Eclipse Leisure Centre car park. The project needs formal closure.

1. Executive summary of the report (expand detail in Key Issues section below)

What is the situation Why we want to do something

• Site specific constraints have been • Due to a number of reasons this project identified in the project increasing cost cannot be implemented and therefore and delivery risks. formal closure is required • There was a proposal to look at funding the capital works from Community Infrastructure Levy (CIL) but this was not feasible and with additional debt financing required for the project it was formally a closing constraint. The project originally aligned with the Council’s commitment to the climate emergency plan and was in keeping with the design and ethos of the Passivhaus Eclipse leisure centre

This is what we want to do about it These are the next steps

• To seek a formal decision on closing the • To formally close the project as a result of project as the risks are now clear with the the issues associated with ground required project design changes and conditions. challenges of financing the scheme. • Integrate the lessons learned from this project, specifically the proper use of a RACI matrix into the project process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Log /26Appendix 1Risk 116 KB Download
PDF
Solar Canopy Project Closure ReportReport 586 KB DownloadRead as text
PDF
View item 44/26 as HTML 67 KBReport 67 KB Copy on its way

At this meeting

Whole meeting

Who was there

12 of 27 attended
JS
Councillor Joanne SextonChair, present
CB
Councillor Chris BatesonVice-Chair, present
MA
Councillor Maureen AttewellCommittee Member, apologies
JB
Councillor John BoughtflowerCommittee Member, apologies, sent representative
MB
Councillor Med BuckCommittee Member, absent
JB
Councillor Jon ButtonCommittee Member, present
DC
Councillor Darren ClarkeCommittee Member, present
SD
Councillor Sue DoranCommittee Member, present
MG
Councillor Michele GibsonCommittee Member, present
ML
Councillor Matthew LeeCommittee Member, apologies
SM
Councillor Sinead MooneyCommittee Member, apologies
LN
Councillor Lawrence NicholsCommittee Member, present

All 27 on the meeting page

More from Spelthorne Corporate Policy and Resources Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Write Offs - Sundry Debts and Housing BenefitsCommittee resolved to approve the write-offs set out in the Appendix 1 and 2 of the report which totalled £52,026 and... Approved Open
12 Oct 2026 Proposed ICT Server ProcurementThe Committee resolved to: 1. Authorise the Council’s ICT Manager to commence a procurement process for the purchase ... Decided Open
12 Oct 2026 Governance Assurance Update - EDI and Financial ManagementThe Committee resolved to: 1. Note the current overall assurance level for the Governance Assurance Areas under the r... Noted Open
12 Oct 2026 Annual Commercial Property Report for Financial Year 2025/26The Committee received the Annual Commercial Property Report for Financial Year 2025/2026. The Committee resolved to:... Approved Open
12 Oct 2026 Procurement of resource to support the LGR transition and transformation processThe Committee resolved not to approve the procurement to modify the contract of the Head of LGR and Special Projects ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies