Business, Infrastructure and Growth Committee, Thursday 25 June 2026 at 7.00pm

Demolition of 34 Kingston Road, Staines-upon-Thames (Oast House & Kingston Road Site)

Approved Committee 3 papers

AI summarySpelthorne's Business, Infrastructure and Growth Committee approved demolition of 34 Kingston Road, Staines, at an estimated £33,000 to £68,000, to remove a health and safety risk on a regeneration site.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPlanning application and contractor procurement approved
Money£33,000 to £68,000 estimatedMet from £100k 2026/27 capital budget
What happens nextSubmit planning applicationThen procure and carry out demolition
Who it affectsAll WardsProperty is in Staines-upon-Thames

What was decided

The Committee approved the Group Head of Assets submitting a planning application to demolish 34 Kingston Road and procuring a contractor to carry out the demolition. Report P9

Demolition is preferred over making the building safe and continuing to hold the property, which would cost up to £75,000 in council tax over 12 to 24 months. Report P12, 3.1

Why

The property is unsafe, in very poor condition, and has been vacant for over 15 years, attracting neighbour complaints and presenting a health and safety concern. Report P11, P12

Making the building safe would cost c. £50,000 and full repair up to £350,000, while the property costs the Council c. £12,350 per year in empty home council tax at the 300% surcharge. Report P12

The property forms part of the Oast House and Kingston Road regeneration site, and including it maximises the redevelopment opportunity. Report P12

What happens next

Submit a planning application for demolition; if consent is granted, procure a demolition contractor and carry out the demolition. Report P11, P9

Demolition, if approved, is to be undertaken in October or March when bats are least likely to be present, with bat boxes installed as alternative roosts if needed. Report P12

Await the final bat emergence survey report due by the end of June and revised demolition quotes due 12 June. Report P12

The money

  • c. £12,350 Annual empty home council tax charge for 2026/27 at 300% surcharge Report P11, P12
  • c. £50,000 Estimated cost to make the building safe Report P12
  • up to £350,000 Estimated cost to bring the property back into use Report P12
  • £33,000 to £68,000 Estimated total cost of planning application, bat measures and demolition Report P12
  • £100k Approved 2026/27 Capital Programme budget to meet demolition costs Report P16
  • up to £24,700 Two-year holding cost if property is not demolished Report 3.1
  • up to c. £75,000 Council tax cost for 12 to 24 months if property is retained Report P12
  • £14,000 to £42,000 Range of previous demolition quotes received Report P12

Options considered

  • Chosen: Demolish the property (subject to planning consent). Removes health and safety risk, stops neighbour complaints, most cost-effective, and ceases holding costs. Report 3.1, P12
  • Rejected: Make the building safe and continue to hold it. Costs c. £50,000 to make safe plus c. £24,700 in holding costs, and the property is likely to be demolished by a future purchaser anyway.
  • Rejected: Secure the property with hoarding and steel sheets. Cheaper short term but the building will continue to deteriorate, risking roof collapse and emergency works or full demolition.

Implications

  • Financial: Estimated demolition cost of £33,000 to £68,000 is met from the £100,000 2026/27 capital budget, and annual empty home council tax of c. £12,350 is saved. Report P16
  • Legal: The Group Head of Assets has delegated authority to submit the planning application under the Scheme of Delegations where financial impact does not exceed £100,000, and procurement must comply with the Council's Contract Standing Orders. Report P17, P20
  • Equalities: No perceived implications on equality and diversity from accepting the recommendation. Report P21
  • Climate: Future development can meet newer environmental standards, but embodied carbon in the existing building could be lost if materials are not retained or repurposed; this should be considered in the demolition contract. Report P22
  • Risk: Not demolishing risks building collapse; uncertainty over bats, asbestos in upper parts, and method statement all need to be managed, with the demolition contractor's method to be signed off by health and safety. Report P15

Who and where

  • All wards in Spelthorne, as the property is a Council asset Report P9
  • Neighbours of 34 Kingston Road, who have raised complaints about the property's poor condition Report P11
  • The wider Oast House and Kingston Road regeneration site Report P12
  • Ecology and bat species potentially roosting in the building Report P12

Timeline

  • 2019: Council purchased the site with 34 Kingston Road already vacant and in poor repair Report P11
  • 2023: Initial surveys indicated bats might be present and roosting in the building Report P12
  • By end of June 2026: Final bat emergence survey report expected Report P12
  • 12 June 2026: New demolition quotes due (re-tendered on the basis bats may or may not be present) Report P12
  • 25 June 2026: Committee decision taken to approve demolition and procurement Report P8
  • If approved, immediately: Recommendation to be implemented, starting with planning application submission Report P23
  • October or March: Window for demolition, when bats are least likely to be present Report P12

Plain English for the jargon

  • Council Tax 300% surcharge: Premium charged on properties considered a 'second' home for Council Tax purposes, applied because 34 Kingston Road has been empty for over 15 years.
  • Regulation 3 application: A planning application made by a local authority to itself for development on its own land, under the Town and Country Planning General Regulations 1992.
  • Bat licence: A licence required to disturb or relocate bats and their roosts, granted subject to providing suitable alternative roosts.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item33/26

Resolved

The Committee resolved to approve the Group Head of Assets’ submission of a Planning Application for the demolition of 34 Kingston Road, Staines-upon-Thames and the procurement of a contractor to carry out the demolition.
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Business, Infrastructure and Growth Committee

Committee Report Checklist

Please submit the completed checklists with your report. If final draft report does not include all the information/sign offs required, your item will be delayed until the next meeting cycle.

Stage 1 Report checklist – responsibility of report owner ITEM Yes / No Date Councillor engagement / input from Chair prior to briefing Relevant Group Head review CH 29/05/26 MAT+ review (to have been circulated at least 5 Yes 29/05/26 working days before Stage 2) This item is on the Forward Plan for the relevant Yes 25/06/26 committee Reviewed by Finance comments (circulate to Finance) AB 03/06/26 Risk comments (circulate to Lee O’Neil) LO 29/05/26 Legal comments (circulate to Legal team) JC 03/06/26 HR comments (if applicable) n/a

For reports with material financial or legal implications the author should engage with the respective teams at the outset and receive input to their reports prior to asking for MO or s151 comments.

Do not forward to stage 2 unless all the above have been completed.

Stage 2 Report checklist – responsibility of report owner ITEM Completed Date rec’d by Monitoring Officer commentary – at least 5 working DMO 05/06/26 days before MAT J. Clare S151 Officer commentary – at least 5 working days T.Collier 03/06/26 before MAT Commissioner engagement DM 09/06/26

Delete as No issues applicable: Confirm final report cleared by MAT Business, Infrastructure & Growth Committee

25 June 2026

Title Demolition of 34 Kingston Road, Staines-upon-Thames (Oast House & Kingston Road Site) Purpose of the report To make a decision Report Author Bruce Strong – Investment Asset Manager Ward(s) Affected All Wards Exempt No Exemption Reason N/A Corporate Priority Community Environment Recommendations Committee is asked to:  Approve the Group Head of Assets’ submission of a Planning Application for the demolition of 34 Kingston Road, Staines-upon-Thames and the procurement of a contractor to carry out the demolition. Reason for 34 Kingston Road is in a poor state of repair and is a health and Recommendation safety concern. It is not cost effective to bring the property back into a good state of repair. In addition, the property is costing the Council c. £12,350 pa in empty home council tax. If the property is demolished, this charge will cease.

1. Executive summary of the report

What is the situation Why we want to do something • 34 Kingston Road forms part of the • The property is unsafe and dangerous. Oast House and Kingston Road car • As the property is vacant and park regeneration site. When the site considered a ‘second’ property for was purchased in 2019 the property Council Tax purposes it attracts a 300% was vacant, and in poor repair and we surcharge, making the Council Tax for understand has been unoccupied for 2026/27 c. £12,350. over 15 years. • It is not economically viable to bring the • Over the past 7 years the property has property back into residential use. remained vacant due to potential • The property is in an exceptionally poor redevelopment of the site and has condition making it a blight to the deteriorated further. It was not immediate area, which is causing economically viable to bring the complaints by neighbours. property back into repair. This is what we want to do about it These are the next steps • Submit a planning application to • Submit a planning application for demolish the property, subject to consent to demolish the property and necessary consents and in so doing should the Application be successful, remove any safety concerns with the undertake the demolition. property and save the ongoing council tax costs of c. £12,350 per annum.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Condition Report: 34 Kingston Road Staines /26Appendix 1 1.5 MB Download
PDF
Demolition of 34 Kingston Road, Staines-upon-Thames (Oast House & Kingston Road Site)Report 465 KB DownloadRead as text
PDF
View item 33/26 as HTML 66 KBReport 66 KB Copy on its way

At this meeting

Whole meeting
27/26MinutesOn the agenda
33/26Demolition of 34 Kingston Road, Staines-upon-Thames (Oast House & Kingston Road Site)This decision
34/26Proposed Council Transitional Corporate Plan 2026/27Decided 37/26Forward PlanOn the agenda

Who was there

10 of 17 attended
HW
Councillor Howard WilliamsChair, present
SG
Councillor Suraj GyawaliVice-Chair, present
CB
Councillor Chris BatesonCommittee Member, present
SB
Councillor Sean BeattyCommittee Member, present
MB
Councillor Med BuckCommittee Member, present
DC
Councillor Darren ClarkeCommittee Member, apologies
RG
Councillor Rebecca GeachCommittee Member, present
MG
Councillor Michele GibsonCommittee Member, present
KH
Councillor Karen HowkinsCommittee Member, present
JS
Councillor Joanne SextonCommittee Member, apologies, sent representative
MB
Councillor Malcolm BeecherSubstitute, present as substitute
CH
Coralie HolmanOfficer, expected

All 17 on the meeting page

More from Spelthorne Business, Infrastructure and Growth Committee

All decisions
MeetingDecisionOutcome
12 Nov 2026 Economic Development KPI Report Quarter 2 2026-27The Committee resolved to acknowledge the Economic Development KPIs for Quarter 2 2026-27. Decided Open
1 Oct 2026 Ashford Business Improvement District (BID) proposalThe Committee resolved to: 1. Acknowledge the BID Proposal, Draft Operating Agreement, Draft Baseline Agreement, BID ... Agreed Open
25 Jun 2026 Proposed Council Transitional Corporate Plan 2026/27The Committee considered the proposed Transitional Corporate Plan and resolved to provide comments on areas relevant ... Decided Open
13 Mar 2025 Appointment of a Director to the Board of Visit Staines (the Business Improvement District in Staines upon Thames)The Committee resolved to appoint the Economic Development Manager as a director to the board of Visit Staines Ltd, t... Decided Open
13 Mar 2025 Council Land and Property DisposalsThe Committee resolved to proceed with the re-marketing of Thameside House offering the unencumbered freehold. Decided Open