Governance Assurance update - Organisational Resilience and Cyber Resilience
DecidedCommittee6 papers
AI summarySpelthorne's Corporate Policy and Resources Committee received the current governance assurance levels and considered updates on organisational and cyber resilience.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedNo new decision, item was for noting and review
MoneyNot stated
What happens nextNot stated
Who it affectsCouncil governance registerNine assurance areas under the committee's remit
What was decided
The Committee received the overall assurance level for the Governance Assurance Areas under its remit, as set out in Appendix A. Report P1
The Committee considered key areas of focus on Organisational Resilience (Appendix B) and Cyber Resilience (confidential Appendix C). Report P2, P3
Why
The Governance Assurance Register covers nine areas within the Committee's remit, and Appendix A records the current assurance level for each. Report P1
Organisational Resilience and Cyber Resilience are reported separately to the Committee, with Cyber Resilience dealt with as confidential business. Report P2, P3
Who and where
Spelthorne Borough Council's Corporate Policy and Resources Committee Report P1
Timeline
2026-09-08: Corporate Policy and Resources Committee meeting
Plain English for the jargon
Governance Assurance Register: The Council's record of assurance levels across its governance areas, here covering nine areas under the Committee.
CPRC: Corporate Policy and Resources Committee, the Spelthorne committee receiving this update.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
The Committee resolved to: 1. Receive the current overall assurance level for the Governance Assurance Areas under the remit of the Corporate Policy & Resources Committee (Appendix A), which form part of the Council’s Governance Assurance Register; and 2. Consider the key areas of focus concerning the Governance Assurance Areas relating to Organisational Resilience (Appendix B) and Cyber Resilience (Confidential Appendix C).
Word for word from the decision Spelthorne published for this meeting.Source: democracy.spelthorne.gov.uk
Report to Corporate Policy and Resources Committee
Committee Report Checklist
Please submit the completed checklists with your report. If final draft report does not include all the information/sign offs required, your item will be delayed until the next meeting cycle.
Stage 1 Report checklist – responsibility of report owner ITEM Yes / No Date Councillor engagement / input from Chair prior to briefing Relevant Group Head review Y 14/08/26 MAT+ review (to have been circulated at least 5 Y 12/08/26 working days before Stage 2) This item is on the Forward Plan for the relevant Y committee Reviewed by Finance comments (circulate to Finance) Risk comments (circulate to Lee O’Neil) LO 12/08/26 Legal comments (circulate to Legal team) LH 14/08/26 HR comments (if applicable)
For reports with material financial or legal implications the author should engage with the respective teams at the outset and receive input to their reports prior to asking for MO or s151 comments.
Do not forward to stage 2 unless all the above have been completed.
Stage 2 Report checklist – responsibility of report owner ITEM Completed Date rec’d by Monitoring Officer commentary – at least 5 working L Heron 14/08/26 days before MAT S151 Officer commentary – at least 5 working days T.Collier 13/8/26 before MAT Commissioner engagement L.O’Neil Delete as applicable: Comments in S. 7 Confirm report signed off for publishing for MAT by L.O’Neil 20/08/26 relevant member of Management Team Confirm final report cleared by MAT L.O’Neil 20/08/26 Corporate Policy and Resources Committee
8 September 2026
Title Governance Assurance update – Organisational Resilience and Cyber Resilience Purpose of the report To inform and assure Report Author Lee O’Neil, Deputy Chief Executive Ward(s) Affected All Wards Exempt Main report and Appendices A & B – No Appendix C - Yes Exemption Reason Appendix C contains exempt information within the meaning of Part 1 of Schedule 12A to the Local Government Act 1972, as amended by the Local Government (Access to Information) Act 1985 and by the Local Government (Access to Information) (Variation) Order 2006 Paragraph 3 – Information relating to the financial or business affairs of any particular person (including the authority holding that information) and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information because, disclosure to the public could expose vulnerabilities and control weaknesses, thereby compromising the Council’s security and ability to manage cyber risk effectively. Corporate Priority Community Addressing Housing Need Resilience Environment Services Recommendations Committee is asked to:
a. Receive the current overall assurance level for the Governance Assurance Areas under the remit of the Corporate Policy and Resource Committee (Appendix A), which form part of the Council’s Governance Assurance Register.
b. Consider the key areas of focus concerning the Governance Assurance Areas relating to Organisational Resilience (Appendix B) and Cyber Resilience (confidential Appendix C). Reason for To enable the Corporate Policy and Resources Committee to Recommendation review progress with implementation of the Governance Assurance Framework and scrutinise performance for key governance areas relating to its remit.
1. Executive summary of the report (expand detail in Key Issues section below)
What is the situation Why we want to do something
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Policy and Resources Committee at Spelthorne and we tell you when its next papers are published, before the meeting rather than after it.
Proposed ICT Server ProcurementThe Committee resolved to: 1. Authorise the Council’s ICT Manager to commence a procurement process for the purchase ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.