Disposal of Communications House, Staines

Deferred Committee 4 papers

AI summarySpelthorne committee recommends deferring the disposal of Communications House in Staines until the Staines Masterplan has been agreed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredRecommend Council defer disposal until Masterplan agreed
MoneyNot stated
What happens nextGoes to full CouncilCommittee will recommend deferral to Council
Who it affectsCommunications House, StainesCouncil owned property in Staines town centre

What was decided

The Committee resolved to recommend that Council defer any decision on the disposal of Communications House until the Staines Masterplan has been agreed.

Why

The papers do not set out the reasons for deferral beyond the link to the Staines Masterplan.

What happens next

The recommendation will go to a meeting of the full Council for a decision.

Options considered

  • Rejected: Approve the disposal terms and delegate authority to officers to complete the sale. Committee instead chose to defer the decision
  • Chosen: Defer the disposal decision until the Staines Masterplan is agreed

Implications

  • Other: The original disposal proposal, including the Heads of Terms, schedule of bids, valuation, financial information and Knight Frank recommendation, is held in exempt appendices and is not in the public papers. Report P1

Who and where

  • Spelthorne Borough Council, as owner of Communications House Report P1

Timeline

  • 2026-10-12: Corporate Policy and Resources Committee recommends deferral of the disposal

Plain English for the jargon

  • Staines Masterplan: A plan for the future of Staines, which the papers do not describe in detail.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item107/26

Resolved

The Committee resolved to make a recommendation to Council to: Defer any decision on the disposal of Communications House until the Staines Masterplan has been agreed.
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Corporate Policy and Resources Committee

Committee Report Checklist

Please submit the completed checklists with your report. If final draft report does not include all the information/sign offs required, your item will be delayed until the next meeting cycle.

Stage 1 Report checklist – responsibility of report owner ITEM Yes / No Date Councillor engagement / input from Chair prior to briefing Relevant Group Head review N/A MAT+ review (to have been circulated at least 5 working Yes 11/9 days before Stage 2) This item is on the Forward Plan for the relevant committee Reviewed by Finance comments (circulate to Finance) Risk comments (circulate to Lee O’Neil) LO 11/09/26 Legal comments (circulate to [email protected]) JC 11/09/26 HR comments (if applicable) N/A

For reports with material financial or legal implications the author should engage with the respective teams at the outset and receive input to their reports prior to asking for MO or s151 comments.

Do not forward to stage 2 unless all the above have been completed.

Stage 2 Report checklist – responsibility of report owner ITEM Completed Date rec’d by Monitoring Officer commentary – at least 5 working L Heron 15/09/26 days before MAT S151 Officer commentary – at least 5 working T.Collier 11/09/26 days before MAT Commissioner engagement Delete as No issues applicable: Comments in S. 7 Relevant MAT member sign-off PM 15/09/26 Report reviewed by Management Team Corporate Policy & Resources Committee Monday 12th October 2026

Title Disposal of Communications House, Staines Purpose of the report To make a recommendation to Council Report Author Coralie Holman – Group Head Assets Ward(s) Affected All Wards Exempt Report – No Appendices 1-5 (inclusive) - Yes Exemption Reason Appendices 1-5 (inclusive) contain exempt information within the meaning of Part 1 of Schedule 12A to the Local Government Act 1972, as amended by the Local Government (Access to Information) Act 1985 and by the Local Government (Access to Information) (Variation) Order 2006 Paragraph 3 – Information relating to the financial or business affairs of any particular person (including the authority holding that information) and in all circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information because, disclosure to the public would prejudice the financial position of the authority in any contract or other type of negotiation with a prospective purchaser who could then know the position of the Council. Corporate Priority Resilience Recommendations Committee is asked to: 1) Consider the proposed disposal terms as set out in this report (summarised in Appendix 1); and

2) Recommend that the Council:

2.1Approve the disposal terms set out in this report

2.2Delegate authority to the Chief Finance Officer and Group Head of Assets, in consultation with Chair and Vice Chair of Corporate Policy and Resources Committee to agree minor variations to the Heads of Terms and adjustments to the sale price; and

2.3Delegate authority to Group Head of Corporate Governance to enter into a transfer to complete the disposal and any ancillary legal documentation required in relation to the proposed disposal. Reason for Agreement to the recommendations in this report will enable the Recommendation approved Asset Rationalisation plan to be progressed towards achieving the agreed target level of capital receipts by 31st March 2027.

1. Executive summary of the report

What is the situation Why we want to do something

• The Council approved an asset • The recommendation in this report rationalisation programme in December implements relevant work required to 2025. further asset rationalisation.

This is what we want to do about it These are the next steps

• To progress the disposal of • Report to be considered at Full Council on Communications House and generate a 22nd October 2026. capital receipt. • Enter into a contract to sell Communications House

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Disposal of Communications House: Part 1 Public Report for CPRC /26Report 899 KB DownloadRead as text
PDF
Disposal of Communications House, StainesReport 901 KB Download
PDF
View as HTML (107/26/2) 92 KBReport 92 KB Copy on its way
PDF
View item 107/26 as HTML 93 KBReport 93 KB Copy on its way

At this meeting

Whole meeting

Who was there

0 of 23 attended
GN
Councillor Greg NeallChair, expected
CB
Councillor Chris BatesonVice-Chair, expected
MA
Councillor Maureen AttewellCommittee Member, expected
JB
Councillor John BoughtflowerCommittee Member, expected
MB
Councillor Med BuckCommittee Member, expected
JB
Councillor Jon ButtonCommittee Member, expected
DC
Councillor Darren ClarkeCommittee Member, expected
SD
Councillor Sue DoranCommittee Member, expected
RG
Councillor Rebecca GeachCommittee Member, expected
SG
Councillor Suraj GyawaliCommittee Member, expected
ML
Councillor Matthew LeeCommittee Member, expected
DS
Councillor Denise SaliagopoulosCommittee Member, expected

All 23 on the meeting page

More from Spelthorne Corporate Policy and Resources Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Write Offs - Sundry Debts and Housing BenefitsCommittee resolved to approve the write-offs set out in the Appendix 1 and 2 of the report which totalled £52,026 and... Approved Open
12 Oct 2026 Proposed ICT Server ProcurementThe Committee resolved to: 1. Authorise the Council’s ICT Manager to commence a procurement process for the purchase ... Decided Open
12 Oct 2026 Governance Assurance Update - EDI and Financial ManagementThe Committee resolved to: 1. Note the current overall assurance level for the Governance Assurance Areas under the r... Noted Open
12 Oct 2026 Annual Commercial Property Report for Financial Year 2025/26The Committee received the Annual Commercial Property Report for Financial Year 2025/2026. The Committee resolved to:... Approved Open
12 Oct 2026 Procurement of resource to support the LGR transition and transformation processThe Committee resolved not to approve the procurement to modify the contract of the Head of LGR and Special Projects ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies