Planning application 26/00714/FUL - Land Accessed from Sheep Walk, Shepperton

Approved Planning 2 papers

AI summarySpelthorne Borough Council approved the Sheep Walk access track for a flexible electricity generation facility, subject to six conditions and advice to secure the access against fly tipping [D]. It will generate business rates but no CIL Payment [7.47].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSix conditions apply; secure access against fly tipping is advised [D].
MoneyNo CIL Payment [7.47]Business rates arise, without New Homes Bonus or Council Tax [7.47].
What happens nextSix approval conditions [8.3]Surface, access, traffic and biodiversity details need approval [8.3].
Who it affectsSheep Walk access track [D]Provides access to the approved flexible generation facility [7.1] [7.2].

What was decided

The Council approved the application subject to the six listed conditions.

Informative 10 was added to the Decision Notice, advising the applicant to secure the access against fly tipping.

The permission provides a vehicular track from Sheep Walk to serve the approved flexible electricity generation facility. Report 7.1, 7.27

Why

The proposal is not inappropriate development in the Green Belt. Officers found that it met the grey belt exception and was in a sustainable location. Report 7.12, 7.13, 7.15, 7.16, 7.48

The access is essential for implementing the flexible electricity generation facility. Its wider benefit is aiding net zero and the transition to renewable energy. Report 7.39, 7.50

The Environment Agency, Natural England and the highway authority raised no objections. The track would be used infrequently for routine maintenance, with no lighting proposed. Officers found no harm to highway safety, biodiversity, flooding, character or neighbouring amenity. Report 7.19, 7.22, 7.23, 7.29, 7.32, 7.37, 7.49

What happens next

Development must begin before the expiration of three years from the date of this permission. It must follow the four approved plans received 09.07.2026. Report P69, P71, P72

Before development starts, the Council must approve the access surface materials and a construction transport management plan. The transport plan must cover parking, loading, storage, traffic, deliveries, routing, highway protection, repair funding and construction vehicle turning. Report P73, P78

Before first occupation, the Sheep Walk access must have a formal bell mouth, clear visibility zones and hardstanding installed 6.0m back from the highway boundary under approved schemes. Before development begins, a biodiversity gain plan must be submitted and approved by Spelthorne Borough Council. The applicant is advised to secure the access against fly tipping. Report P75, P77, P89

Options considered

  • Chosen: Approve the application as set out in the officer report. Officers considered it acceptable in planning terms and explained the reasons. Report 8.1
  • Chosen: Add Informative 10 to the Decision Notice. The applicant is advised to secure the access against fly tipping.
  • Rejected: Approve subject to additional or amended conditions and informatives. The report set out the conditions and informatives and said planning conditions should be kept to a minimum. Report P66
  • Rejected: Refuse the application. Officers considered the application acceptable in planning terms. Report P67

Implications

  • Financial: The proposal will generate business rates but no CIL Payment, New Homes Bonus or Council Tax payments. Report 7.47
  • Legal: The approved development site is not part of this application and may be implemented regardless of this proposal. Officers judged any interference with private and property rights to be lawful, proportionate and in the public interest. Report 7.2, 7.46
  • Climate: The access supports a facility allowed because it would assist renewable generation and the transition to low carbon energy. Report 7.39, 7.50
  • Risk: Highway conditions require a formal bell mouth, clear visibility zones, hardstanding and a construction transport management plan to protect safety and convenience. Report P75, P76, P77, P78, P79
  • Risk: The site is in Flood Zones 2 and 3a, with medium and high flood probability. The Environment Agency raised no concerns because permeable materials and no ground level raising were proposed, and confirmed that climate change allowances were applied. Report 7.31, 7.32
  • Risk: The access overlaps the proposed River Thames Scheme route. The Environment Agency said it would contact the landowner and developer to discuss delivery as scheme timescales become clearer. Report 7.33
  • Equalities: The assessment found it possible for people with disabilities to access the development and considered the proposal acceptable under the Equality Act 2010. Report 7.42
  • Other: The proposal provides 23.37% biodiversity net gain in habitat areas (3.28 unit gain) on another site, secured by BNG legislation. This meets the mandatory 10% biodiversity net gain requirement. Report 7.36

Who and where

  • The applicant
  • People using the flexible electricity generation facility Report 7.50
  • Neighbouring residential properties
  • Businesses at Waymeadows Business Centre
  • People using local roads, bridleways, footpaths and cycle routes Report P75, P85
  • People with disabilities Report 7.42
  • The River Thames Scheme project Report 7.33
  • People using the land for motocross riding Report 7.27

Timeline

  • Before the expiration of three years from the date of this permission: Development must be begun before this time. Report P69
  • Before development begins: A biodiversity gain plan must be submitted and approved by Spelthorne Borough Council. Report P89
  • Before first occupation: The formal Sheep Walk bell mouth and site hardstanding must be provided. Report P75, P77
  • September 2024: The flexible electricity generation facility was approved. Report 7.28
  • circa 10 years ago: The existing Sheep Walk access was constructed unlawfully. Report P32
  • 09.07.2026: The four approved plans were received. Report P71
  • up to 3 months in advance: Applications for highway works must be submitted to the County Council's Street Works Team. Report P88
  • 17th September 2027: The existing approval for the flexible electricity generation facility may be implemented until this date. Report 7.1

Plain English for the jargon

  • Green Belt: Land kept permanently open to prevent urban sprawl, safeguard countryside and support urban regeneration [7.3] [7.5].
  • grey belt: Previously developed or other Green Belt land that does not strongly contribute to purposes a, b or d [7.11].
  • Biodiversity Net Gain: A gain in biodiversity habitat through creation, expansion, restoration, enhancement and management [7.36].
  • CIL: A payment the proposal will not generate because it is not CIL chargeable [7.47].
  • bell mouth: The formal vehicle entrance required at the existing Sheep Walk access, with full height kerbs and parking restrictions [P75].
  • hardstanding: A hard surface at the site entrance, installed with bound material 6.0m back from the highway boundary [P77].
  • Construction Transport Management Plan: A plan covering vehicle parking, loading, storage, works, deliveries, routing, highway protection, repair funding and construction vehicle turning [P78].
  • Flood Zones 2 and 3a: Areas with medium and high probability of flooding under national planning policy [7.31].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item32/26

Resolved

The application was approved subject to conditions as set out in Paragraph 8.1, 8.2 and 8.3 of the recommendations plus the additional informative being added to the Decision Notice: Informative 10 – The applicant is advised to make the access secure to safeguard the land from fly-tipping.
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Planning Committee

Planning Committee

14 October 2026 Application No. 26/00714/FUL Site Address Land Accessed from Sheep Walk, Shepperton Applicant Conrad Energy Limited Proposal Vehicular access track to serve the flexible electricity generation facility approved under planning application ref. 22/00569/FUL (appeal ref: APP/Z3635/W/23/3321476). Case Officer Matthew Clapham Ward Shepperton Town Called-in This application has been ‘called-in’ by Councillor Howkins on the grounds of inappropriate use of Green Belt land.

Application Target: Extension of Time Dates Valid: 09.07.2026 Expiry: 03.09.2026 until 16.10.2026 Executive The site is currently open land off Sheep Walk. There is an existing access Summary from Sheep Walk. To the south is open land recently granted planning permission for the storage of plants and associated / ancillary materials. To the north is also open land with a history of unlawful uses on it. The site is situated within the designated Green Belt and Flood Risk Zones 2 and 3a. The site is also located within an area safeguarded for the ‘River Thames Scheme - Areas and Land Under Consideration’.

It is proposed to lay down hardstanding to create an access track that leads to the west to an approved small-scale flexible electricity generation facility with associated ancillary infrastructure, access and boundary treatment. The original access to this facility was to be from Chertsey Road using the existing access to Priory Stables. However, the County Highway Authority did not agree to its use due to cabling and infrastructure issues.

The proposal is considered to have an acceptable impact on the Green Belt, biodiversity, the amenity of neighbouring properties and highway safety. It is also not considered to adversely affect the potential implementation of the River Thames Scheme. The proposal is recommended for approval.

It should be noted that this application does not include the electricity generation facility which has its own extant approval. This application is solely for the access to it.

Recommended Approve the application subject to conditions as set out in the Decision Recommendation section (paras. 8.1, 8.2 and 8.3). MAIN REPORT

1. Development Plan

1.1The following policies of the Spelthorne Local Plan 2024–2039/40 are of relevance: ➢ Policy ST1: Presumption in Favour of Sustainable Development ➢ Policy ST2: Planning for the Borough ➢ Policy PS1: Responding to the Climate Emergency ➢ Policy PS2: Designing Places and Spaces ➢ Policy E2: Biodiversity ➢ Policy E3: Managing Flood Risk ➢ Policy E4: Environmental Protection ➢ Policy ID2: Sustainable Transport for New Developments

1.2The policies contained within the National Planning Policy Framework (NPPF) (August 2026) are also relevant

2. Relevant Planning History 2.1 The site has the following planning and enforcement history: Reference Proposal Description Decision 18/01396/FUL Restoration of land - Refused Involving removal of 12.02.2019 material, crushing material and replacing with imported naturally occurring soils, topsoil and grassing. 22/00569/FUL Erection of a small-scale Refused 04.11.2022 flexible electricity Allowed on Appeal generation facility with APP/Z3635/W/23/3321476 associated ancillary 17.09.2024 infrastructure, access and boundary treatment 26/00297/FUL Change of use from Granted agriculture to storage of 30.07.2026 plants and associated / ancillary materials (Officer Note:) This is of relevance as it is located on the site immediately to the south of the proposed road and sharing the same access

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item A Officers Report 2600714FUL /26Report 367 KB DownloadRead as text
PDF
Planning application 26/00714/FUL: Land Accessed from Sheep Walk, SheppertonPlan 548 KB Download

At this meeting

Whole meeting

Who was there

0 of 20 attended
MG
Councillor Michele GibsonChair, expected
DG
Councillor Daniel GeraciVice-Chair, expected
LB
Councillor Laura BarkerCommittee Member, expected
CB
Councillor Chris BatesonCommittee Member, expected
SB
Councillor Sean BeattyCommittee Member, expected
MB
Councillor Med BuckCommittee Member, expected
TB
Councillor Tony BurrellCommittee Member, expected
RC
Councillor Rose ChandlerCommittee Member, expected
DC
Councillor Darren ClarkeCommittee Member, expected
KG
Councillor Kathy GrantCommittee Member, expected
KH
Councillor Karen HowkinsCommittee Member, expected
ML
Councillor Matthew LeeCommittee Member, expected

All 20 on the meeting page

On this subject at Spelthorne

Search all
  1. Planning application 26/00714/FUL - Land Accessed from Sheep Walk, SheppertonThis decision
  2. Planning application - 26/00739/FUL - Memorial Gardens, Market Square, Staines-upon-Thames TW18 4SDApproved
  3. Major Planning ApplicationsNoted
  4. Major Planning ApplicationsNoted
  5. Major Planning ApplicationsNoted
  6. Planning application 25/01482/FUL - The Feathers, The Broadway, Laleham, Staines-upon-Thames TW18 1RZApproved

More from Spelthorne Planning Committee

All decisions
MeetingDecisionOutcome
11 Nov 2026 Planning application - 26/00739/FUL - Memorial Gardens, Market Square, Staines-upon-Thames TW18 4SDThe application was approved subject to conditions as set out in the Recommendation Section of the report (paragraphs... Approved Open
11 Nov 2026 Planning Appeals ReportResolved that the report of the Planning Development Manager be received and noted. Noted Open
11 Nov 2026 Major Planning ApplicationsResolved that the report of the Planning Development Manager be received and noted. Noted Open
14 Oct 2026 Planning Appeals ReportResolved that the report of the Interim Planning Development Manager be received and noted. Noted Open
14 Oct 2026 Major Planning ApplicationsResolved that the report of the Interim Planning Development Manager be received and noted. Noted Open