AI summaryWest Surrey Shadow Authority Standards Committee recommended Procurement and Contract Procedure Rules for adoption from 1st April 2027, including a £100,000 internal threshold, and delegated amendments to the Monitoring Officer [D][1.2][P40][P61]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedMonitoring Officer may amend the Rules [D]
MoneyNo direct financial implications [P80]Different thresholds could require more resources [P81]
What happens nextShadow Authority approval required [D][4.4]Rules take effect on 1st April 2027 [1.2][D]
Who it affectsService and Procurement teams [P93]Duties change below £100,000 [P93]
What was decided
The Committee recommended the proposed Rules, as amended by the Constitution Working Group, to the West Surrey Shadow Authority for approval and adoption into the West Surrey Council Constitution from Vesting Day [D].
It delegated authority to the West Surrey Monitoring Officer to amend the Rules in line with the Standards Committee resolution and make minor and administrative amendments [D].
Why
An approved constitution, including procurement and contract procedure rules, is a legal requirement before Vesting Day [1.2][3.1]. Report 1.2, 3.1
The Rules support compliance with the Procurement Act 2023 and Procurement Regulations 2024 and provide a lawful, transparent, proportionate and accountable framework [P87][P88]. They also embed value for money through controls and governance and are intended to reduce the risk of financial loss [P80]. Report P87, P88, P80
Finance and procurement officers, shadow authority interim chief officers, other stakeholders and members helped develop the Rules. Public consultation was not considered necessary [7.1][7.2]. Report 7.1, 7.2
What happens next
The West Surrey Shadow Authority is next asked to approve and adopt the Rules. Its meeting date is to be confirmed [D][4.4]. The Rules would take effect in the West Surrey Council Constitution from Vesting Day [P12][1.2]. Report 4.4, P12, 1.2
The West Surrey Monitoring Officer may amend the Rules in line with the Standards Committee resolution and make minor and administrative amendments [D].
For procurements between £25,000 and £100,000, service teams must notify Procurement before starting and Procurement must approve before it proceeds [P44][P45]. Implementation also requires guidance, training and system access [P93]. Report P44, P45, P93
The money
£5million to £2.5million Contract award overspend threshold lowered for return to Executive approval [P23]. Report P23
£100,000 (ex VAT) Chosen Option 1 threshold for Procurement Service leadership [P40][P61]. Report P40, P61
between £25,000 and £100,000 Procurement oversight and approval range [P44][P45]. Report P44, P45
£25,000 (ex VAT) Rejected Option 2 threshold for Procurement Service leadership [P68]. Report P68
£100,000 Service procurement responsibilities apply below this threshold [P93]. Report P93
Options considered
Chosen: Set the internal threshold at £100,000 (ex VAT), with Procurement leading all procurements above it. Data analysis supported this level, and the final draft was based on it. Oversight, call in powers and training were proposed to manage the disadvantages [P40][P61][P65][P67]. Report P40, P61, P65, P67
Rejected: Set the internal threshold at £25,000 (ex VAT), with Procurement leading all procurements above it. Benchmarking made this unusual for authorities of this size, and expected contract volumes would exceed current Procurement resources [P68][P71][P72]. Report P68, P71, P72
Rejected: Set a variable internal threshold for Procurement team involvement. It was considered insufficiently robust and poor practice, with ambiguity and scope for failure to comply [P73][P77][P78]. Report P73, P77, P78
Implications
Legal: An approved constitution is legally required, including standing orders and procedure rules [P87]. The Rules support compliance with the Procurement Act 2023 and Procurement Regulations 2024 [P88]. Report P87, P88
Risk: Failure to adopt before Vesting Day risks procurement that does not comply, unlawful or procedurally defective awards, supplier challenge, service delay, reputational damage and financial exposure [P89]. The principal risk is contravention of Section 151 of the Local Government Act 1972 [8.1]. Report P89, 8.1
Financial: There are no direct financial implications from approval [P80]. West Surrey will face significant budget pressures and limited resources from 2027/28, with rising demand and costs, reduced government funding and greater reliance on Council Tax [P83][P84]. Report P80, P83, P84
Financial: Lower thresholds could require increased Procurement resources and budget, so they must be weighed against value for money [P81]. Report P81
Staffing: There are no direct staffing or employment implications. Service officers will take on procurement work below £100,000, requiring guidance, training and systems, with workload and capacity monitored [P93]. Report P93
Equalities: There are no direct equality impacts. Equality duties and impacts are considered for each procurement or financial transaction [P96]. Report P96
Climate: There are no direct climate or sustainability impacts from the report. The Rules require sustainability and environmental considerations for each applicable procurement [P98]. Report P98
Other: The Rules include social value requirements and due diligence on modern slavery, human trafficking and unethical labour practices [P31][P35]. Report P31, P35
Who and where
West Surrey Shadow Authority [D][4.4] Report 4.4
Future West Surrey Council [P12][1.2] Report P12, 1.2
Members, officers and the public [P91] Report P91
Service staff carrying out procurement below £100,000 [P93] Report P93
Procurement Service and hosted shared service [P93][P49] Report P93, P49
Procurement officers working across both new authorities [P49] Report P49
Suppliers and other contracting organisations [1.3][P89] Report 1.3, P89
Contract managers for significant contracts [P31] Report P31
Timeline
17 September 2026: Audit and Governance Committee and Constitution Sub-Committee discussed the proposed approach [P30]. Report P30
29th October 2026: Audit and Governance Committee considered the proposed Rules and provided feedback [4.1][4.5]. Report 4.1, 4.5
29 October 2026: Constitution Working Group considered the feedback and recommended the Rules with one amendment [4.6][P23]. Report 4.6, P23
2 November 2026: Standards Committee considered and recommended the amended Rules [4.3][D]. Report 4.3
early in the New Year: Final Rules are due to be agreed by the West Surrey Shadow Authority [1.4]. Report 1.4
date to be confirmed: Shadow Authority meeting to consider approval and adoption [4.4][D]. Report 4.4
1st April 2027: Vesting Day, when the Rules take effect in the West Surrey Council Constitution [1.2][P12][D]. Report 1.2, P12
2027/28: West Surrey faces significant budget pressures and limited financial resources [P83][P84]. Report P83, P84
Plain English for the jargon
Procurement and Contract Procedure Rules (PCPRs): Rules controlling how West Surrey Council authorises expenditure and manages resulting contracts [1.1][1.3].
Internal threshold: The contract value above which Procurement must undertake procurement activity [P39][P40].
Vesting Day: 1st April 2027, when the new unitary West Surrey Council begins operating [1.2].
Local Government Reorganisation (LGR): Formation of the new unitary authority, requiring new constitutional procurement and contract procedures [P29].
Procurement Act 2023 (PA23): Legislation governing local authority procurement and publishing requirements [P42][8.2].
Provider Selection Regime: The regime under which Procurement undertakes all contracts [P40].
Social Value Model: An outcomes focused methodology based on best practice, with outcomes aligned to strategic priorities [P32].
Convertible procurements: Contracts extended or modified so their value moves above the regulatory threshold [P42].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43/SD
Resolved
RESOLVED to: 1. Recommend the proposed Procurement and Contract Procedure Rules, as amended by the Constitution Working Group, to the West Surrey Shadow Authority for approval and adoption into the West Surrey Council Constitution with effect from Vesting Day; and 2. Delegate authority to the West Surrey Monitoring Officer to amend the Procurement and Contract Procedure Rules, in line with the resolution of the Standards Committee and to make any other minor and administrative amendments necessary.
Word for word from the decision Spelthorne published for this meeting.Source: democracy.spelthorne.gov.uk
Report to West Surrey Shadow Authority Standards Committee
Executive summary
1.1This report presents the final draft of the Procurement and Contract Procedure Rules (“PCPRs”, or “Rules”) section of the new constitution for West Surrey Council.
1.2Section 9P of the Local Government Act 2000 requires every local authority to prepare, maintain, and keep up to date a formal constitution. This document controls how the new unitary West Surrey Council operates, makes decisions, and handles its governance. It is therefore essential that the unitary authority of West Surrey Council establishes new Procurement and Contract Procedure Rules ahead of Vesting Day on 1st April 2027.
1.3The PCPRs set out how the Council authorises and manages expenditure and resulting commercial and other contracts with other organisations.
1.4The final PCPRs are due to be agreed by the West Surrey Shadow Authority, on a recommendation from the Standards Committee early in the New Year.
Recommendations
2.1It is recommended that the Audit and Governance Committee
2.1.1 Considers the proposed Procurement and Contract Procedure Rules, as attached at appendix 2 to this report, and proposes any amendments, comments or feedback, to be taken into account by the Constitution Working Group and Standards Committee;
2.2It is recommended that the Constitution Working Group
2.2.1 Considers the feedback from the Audit & Governance Committee and approves the proposed Procurement and Contract Procedure Rules, as attached at appendix 2 to this report, and recommends them to the Standards Committee for recommendation to the Shadow Authority;
2.3It is recommended that the Standards Committee:
2.3.1 Resolves to recommend the proposed Procurement and Contract Procedure Rules, as amended by the Constitution Working Group, to the West Surrey Shadow Authority for approval and adoption
2 West Surrey Constitution: Procurement and Contract Procedure Rules
into the West Surrey Council Constitution with effect from Vesting Day.
2.3.2 Delegates authority to the West Surrey Monitoring Officer to amend the Procurement and Contract Procedure Rules, in line with the resolution of the Standards Committee, and make any other minor and administrative amendments necessary.
3. Reason(s) for recommendation:
3.1It is a legal requirement for the new West Surrey Council to have an approved Constitution in time for Vesting Day, including standing orders or procedure rules governing Procurement and Contract matters.
4. Next steps
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow West Surrey Shadow Authority Standards Committee at Spelthorne and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.