Joint CCTV Executive, Thursday 29 March 2018 at 6.00pm

Presentation on SG1 and the Implications for the CCTV Control Room

Noted Executive 1 paper

Joint CCTV Executive noted this item on Thursday 29 March 2018. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

The Committee received a presentation from the Stevenage Regeneration Team that outlined the plans for the SG1 Development following the appointment of MACE as the Stevenage Regeneration Delivery Partner in February 2018. The scheme submitted by the preferred development partner, MACE, had timetabled the demolition of Swingate House (the location of the CCTV Control Room) in the first phase of work. It was therefore necessary to relocate the Control Room. The cost of the relocation would be met by Stevenage Borough Council (SBC) Relocation in alternative SBC owned buildings and privately owned accommodation had been considered but it was noted that partner authorities might wish for other site options to be considered. It was suggested that whilst Herts Constabulary had indicated that there was insufficient space to relate the control room at the Stevenage Police Station, the Headquarters in Welwyn might be a possible alternative. Officers agreed to make relevant enquiries. Officers outlined what they believed to be the technical requirements in terms of relocation but following a number of questions from Members it was accepted that detailed technical advice was required to fully understand what options could be realistically considered including relocation outside of Stevenage. Members expressed concern that to successfully relocate the control room with minimum downtime and disruption, a 12 month timetable was ambitious. Officers explained that the detailed contract with MACE had not yet been signed and so there could be flexibility with the timelines. In response to questions raised by Members as to why the Joint CCTV Executive had not been consulted at an earlier stage regarding the relocation, Officers explained that the timetable was dependent upon which developer’s bid was successful. The detailed proposals from some of the bidders had the demolition of Swingate House timetabled for 2021, therefore it was only when MACE were confirmed as the preferred bidder, was the 2019 demolition date confirmed. Whilst the decision as to the preferred bidder had not been taken until the end of January, Officers apologised that the Joint Executive had not been consulted at an earlier stage. Members were of the view that this had been very unsatisfactory and had led to serious concerns regarding the operation of the Partnership. However, it was accepted that the proposed governance review would address these issues. In response to a Member’s question Officers stated that if the costs of relocation of the Control Room was more than the £1 million budget secured SBC would seek to ensure that there was sufficient capital allocation for the work to proceed. It was concluded that any further consideration regarding the relocation of the Control Room was dependent upon technical information regarding the specifications for connectivity, capacity, broadband speed etc. Therefore external technical advice would be sought with the report then circulated to all Members. Detailed discussions should take place at the Officer Management Board who would also consider the report in relation to options for relocation put forward by Partners and a protocol for the decision making for the relocation. ...
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Joint CCTV Executive

Background

The regeneration of Stevenage Town Centre is the top priority for the residents of Stevenage and Stevenage Borough Council. The council adopted the Stevenage Central Framework in 2015 which set out for how this regeneration will take place. In 2017 Stevenage Borough Council began the process of securing a development partner for SG1, the first phase of this regeneration, a £350m Town Centre regeneration scheme in the heart of Stevenage. The private investment for SG1 has been secured by utilising public sector assets, working in partnership to lay the foundations for the transformation of Stevenage.

The SG1 red line area is shown below and includes Swingate House, surface level carparks, the current SBC offices, Bus Station, The Plaza, Health and library sites. This site was chosen as it has very high levels of public ownership enabling the greatest control of a scheme.

Over the past twelve months, the Council has conducted an OJEU competitive dialogue procurement process for SG1, and has now secured Mace as its development partner, bringing the plans a step closer to reality. The Council still needs to finalise the Development Agreement and go through the planning process, but delivery plans are now being formalised across multiple areas.

As the Council moves from a procurement stage to a delivery stage, consideration is being given to the closure and redevelopment of Swingate House and other public sector assets included in the early phases. This necessitates the relocation of the existing CCTV control room to an alternative location. Key Principles

As landlord, and a committed member of the CCTV Partnership, we recognise our duty to relocate the facility. The following principles have been developed thus far:

- Relocate the control room with minimum downtime and disruption possible; new control room to be built before the existing is de-commissioned - Relocate and Replace equipment on at least a like for like basis, as well as identify opportunities for upgrades that could be undertaken as spend to save options. These opportunities will come back to the Board. - Ensure external technical expertise is engaged from the start of the project

Members may wish to comment upon the principles.

Steps taken to date

The following actions have already been taken:

- £1m of funding secured for the relocation of the control room - Appointment of SGW technical consultants through a competitive tender process to provide technical advice and support - Development of a specification to procure an integrator conpany for the technical design, implementation, testing and maintenance of the new facility - Identification of parameters for a new site, which will minimise technical disruption and ensure a high-quality facility can be delivered

Next steps

SBC has suggested relocating the Control Room to its depot at Cavendish Road. However it is noted that the partner authorities may wish for other site options to be explored subject to the sites being able to meet the technical requirements. That being the case it would be helpful to know what the other site options are in the near future in order that they may be considered accordingly.

SGW consultants, supported by resource from SBC are finalising the technical specification and developing options for the relocation of the control room. The specification and parameters for a new site will be shared with the partner authorities for comment. Post consideration the next steps are as follows:

- Finalise tender specification and secure a specialist integrator to design and implement the new facility. This will be weighted in favour of quality to ensure an industry-leading company is secured. - Present technical solution to the CCTV Board leading to a preferred site being selected - Build and fit-out new facility prior to de-commissioning the existing facility

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Presentation on SG1 and the Implications for the CCTV Control RoomAgenda 120 KB DownloadRead as text

At this meeting

Whole meeting

More from Stevenage Joint CCTV Executive

All decisions
MeetingDecisionOutcome
24 Oct 2024 Election of chairRESOLVED that Councillor Conor McGrath be elected to serve as Chair of the Joint CCTV Executive Committee for this me... Decided Open
24 Oct 2024 Minutes - 24 june 2024It was RESOLVED that the minutes of the Joint CCTV Executive meeting held on 24 June 2024 be approved as a correct re... Approved Open
24 Oct 2024 Terms of referenceIt was RESOLVED that the Terms of Reference for the Committee, as agreed by the Annual Council Meeting on 22 May 2024... Agreed Open
24 Oct 2024 Cctv operations reportIt was RESOLVED that the CCTV Operations Report be noted. Noted Open
24 Oct 2024 Cctv officer management board reportIt was RESOLVED that the CCTV Officers Management Board Report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies