Resolved
It was RESOLVED that Planning Permission be GRANTED subject to conditions as per the recommendations in the report.
Planning and Development Committee decided this item on Tuesday 4 December 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
It was RESOLVED that Planning Permission be GRANTED subject to conditions as per the recommendations in the report.
Part I – Release to Press
Meeting: Planning and Development Agenda Item: Committee Date: 4 December 2018 Author: James Chettleburgh 01438 242266 Lead Officer: Chris Berry 01438 242257 Contact Officer: James Chettleburgh 01438 242266
Application No: 18/00400/FP Location: Land located between Blenheim Way, the A602 and Hertford Road, Stevenage.
Proposal: Proposed development of a new community centre, cycle path running through the site, associated parking and landscaping.
Drawing Nos.: 16059.03.SU1.01A;16059.03.SU01.02A;16059.03.wd2.01G;16059.03.wd 2.10D; 16059.03.wd2.101 B; 16059.03.wd2.102 B. Applicant: Stevenage Borough Council Date Valid: 11 October 2018 Recommendation: GRANT PLANNING PERMISSION.
Plan for information purposes only 1. SITE DESCRIPTION 1.1 The application site is located on a plot of land which lies adjacent to the junction of Blenheim Way and Hertford Road. The site is designated as “Principal Open Space” and consists of a number of mature trees and amenity grassland along with access to the cycleway. To the east and north/east of the site lies the A602 cycleway and main trafficked highway along with associated underpass. Immediately to the north of the site is the new traffic light controlled junction which serves Hertford Road and the A602. To the west of the site lies Blenheim Way which is a trafficked highway and to the south is a residential development of two-storey semi-detached houses which fronts onto Blenheim Way.
1.2Turning to the surrounding area, to the east of the application site beyond the A602 is Stevenage Golf Course. To the south, beyond the area of principal open space is Pembridge Gardens which comprises a mixture of town houses terraced properties and residential blocks of flats. In regards to development along Blenheim Way, this comprises a mixture of semi-detached and terraced two-storey properties along with two and three storey residential blocks of flats. These properties and the blocks of flats are generally uniform in design constructed from red brick with concrete tiled roofs. In terms of their fenestration detailing, the properties and flat blocks comprise of uPVC windows and doors which are symmetrical, vertically aligned and evenly spaced. Turning to the flat blocks, they generally comprise of external balconies with metal balustrades, double mono-pitched roof and timber cladding on their flank elevations at the upper levels.
2. RELEVANT PLANNING HISTORY 2.1 There is no relevant planning history to this site.
3. THE CURRENT APPLICATION
3.1The originally submitted application sought permission for the erection of a community centre and a residential block of apartments with twelve units. The proposal also comprised a shared vehicle and pedestrian access with a cycleway through route. The scheme has now been amended with the residential block of apartments being omitted.
3.2The amended application before the Council now seeks permission for the erection of a community centre, cycle path running through the site with associated parking and landscaping. The proposed community centre would measure approximately 11.17m in length, span 32.5m in width with an eaves height of 2.87m with an overall height of 6.76m. The community centre would comprise of a meeting room, 2 no. halls, a coffee bar, kitchen, toilets, offices, plant room and associated storage areas. In terms of construction, the community centre would generally be clad in interlocking diamond shaped zinc, including the gable-end roof, with the principal façade finished in facing brick. The eastern elevation of the community centre consists of curtain wall glazing at full height which is recessed with a zinc roof overhang. The roof of the building would also consist of photo-voltaic (PV) panels positioned on the southern roof slope.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
18/00400/FP: LAND LOCATED BETWEEN BLENHEIM WAY, THE A602 AND HERTFORD ROAD, STEVENAGEReport | 318 KB | DownloadRead as text |
Follow Planning and Development Committee at Stevenage and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Oct 2026 | 26/00427/fpm - lister hospital, coreys mill laneRESOLVED that planning permission be GRANTED subject to the applicant having first entered into a Unilateral Undertak... | Decided | Open |
| 8 Oct 2026 | Information report - delegated decisionsRESOLVED that the Information Report – Delegated Decisions be noted. | Noted | Open |
| 8 Oct 2026 | Information report - appeals/called in applicationsRESOLVED that the Information Report – Appeals / Called In Decisions be noted. | Noted | Open |
| 8 Oct 2026 | Exclusion of the press and publicRESOLVED : 1. That under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the m... | Decided | Open |
| 8 Sep 2026 | 26/00531/fph - 134 shephall viewIt was agreed that the matter could be discussed outside the meeting to consider whether any further action could be ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.