In reply to Members’ queries, the SIAS Client Audit Manager commented: · As referred to earlier in the meeting, the High Priority Recommendations relating to the CCTV Partnership were scheduled to be addressed by the Joint CCTV Partnership Committee at its meeting to be held on 10 April 2019; · The Client Satisfaction Performance Indicator had met the 100% target, although it was noted that only 11 of 29 questionnaires had been completed and returned to SIAS, despite regular reminders. The Assistant Director (Corporate Services & Transformation) undertook to raise this issue with Senior Leadership Team colleagues; and · Joint Reviews – only 2 out of 4 billable audit days had been delivered during 2018/19 (relating to the CCTV Partnership review). There had been no appetite during the year for any further Joint Review audit work. It was
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
Members are recommended to: a) Note the Internal Audit Progress Report b) Approve Amendments to the Audit Plan as at 1 March 2019 c) Note the Status of Critical and High Priority Recommendations SIAS Internal Audit Progress Update Stevenage Borough Council
Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.4 Proposed Audit Plan Amendments 2.5 Critical and High Priority Recommendations 2.7 Performance Management
Appendices: A Progress against the 2018/19 Audit Plan B Implementation Status of Critical and High Priority Recommendations C Audit Plan Items (April 2018 to March 2019) - Indicative start dates agreed with management D Assurance Definitions / Priority Levels SIAS Internal Audit Progress Update Stevenage Borough Council
1 Introduction and Background Purpose of Report
1.1To provide Members with:
a) The progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s 2018/19 Internal Audit Plan as at 1 March 2019. b) The findings for the period 1 April 2018 to 1 March 2019. c) The proposed amendments required to the approved Internal Audit Plan. d) The implementation status of previously agreed audit recommendations. e) An update on performance management information as at 1 March 2019.
Background
1.2Internal Audit’s Annual Plan for 2018/19 was approved by the Audit Committee at its meeting on 26 March 2018. The Audit Committee receive periodic updates against the Annual Internal Audit Plan.
1.3The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit function is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed Annual Internal Audit Plan.
2 Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 1 March 2019, 95% of the 2018/19 Audit Plan days have been delivered (calculation excludes contingency days that have not yet been allocated).
2.2Final reports for the following audits and projects have been issued or completed since the last Audit Committee:
Assurance Number of Audit Title Date of Issue Level Recommendations
Risk Management February 2019 Good None
Corporate Governance February 2019 Good None
Creditors March 2019 Good Two Low/Advisory
Development Management March 2019 Good One Low/Advisory
Housing Development March 2019 Good None
Page 1 SIAS Internal Audit Progress Update Stevenage Borough Council
2.3The table below also summarises the position with regard to 2018/19 projects as at 1 March 2019. Appendix A provides a status update on each individual project within the 2018/19 Internal Audit Plan. Details of start dates for the individual projects are also shown in Appendix C.
Status No. of Audits at this Stage % of Total Audits
Final Report Issued 19 58%
Draft Report Issued 7 21% In Fieldwork/Quality 5 15% Review In Planning/Terms of 0 0% Reference Issued Allocated 0 0%
Deferred/Cancelled 2 6%
Total 33 100%
Proposed Audit Plan Amendments
2.4The audit of Land Charges, due to be undertaken during March 2019, has been deferred until July 2019 and the audit days returned to contingency. This is due to staff having insufficient availability in the period leading up to the local elections in May. In addition the audit of Homelessness Reduction Act, due to be undertaken in March 2019, has been deferred until June 2019 and the audit days returned to contingency. Provision for both audits has been made in the Proposed Audit Plan for 2019/20.
Critical and High Priority Recommendations
2.5Members will be aware that a Final Audit Report is issued when it has been agreed (“signed off”) by management; this includes an agreement to implement the recommendations that have been made.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.