The following matters were discussed: · The advantages and disadvantages of appointing a single contractor to undertake the works; · Consideration of the potential to include external decent homes works into the contract; · The importance of fitting carbon monoxide detectors as part of the refurbishment of Council stock; · The possibility of bringing forward the insourcing of the contract to a period of less than 3 years and the approach to ensure the Repairs and Voids Team were adequately resourced to achieve this. It was As contained in report. Other Options considered: As contained in report.
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
2.1That approval be given for officers to procure a contract to conduct essential refurbishment work to various HRA properties as identified in the Asset Management Strategy.
2.2That a single Contractor is appointed to undertake the works for reasons as set out in section 4.1 of this report.
2.3That the contract be offered to market at an estimated contract value of £1.7m per annum for a term of three years, with the option to extend the term by an additional three years.
2.4That the price and quality aspects of the tender are evaluated based on a ratio of 40/60 (price/quality).
2.5That the procurement route is through a restricted process for reasons set out in section 4.4 of this report
2.6That the Strategic Director be given delegated authority to award and finalise the terms of the contract with the winning bidder after officer evaluation of tenders received and having consulted the Portfolio Holder – Housing, Health and Older People.
Part 1 - Executive – 12 June 2019 3. BACKGROUND
3.1This Procurement report has been prepared following the early termination of the Contract for Decent Homes, comprising kitchen, bathroom, heating, rewires and disabled adaptation works that commenced on 4 October 2016.
3.1Following the end of the contract with Axis in December 2017, Stevenage Borough Council entered into a short term contract with United Living under an existing Framework agreement. While this approach has ensured continuity of service and value for money it was not intended to provide a long term solution to the requirements and will end, subject to two 6-month extensions, in December 2019.
3.2The Asset Management plan has identified the need for a programme of refurbishment works to approximately 300-450 homes within the Borough. The total value of the contract is estimated to be approximately £1.7m per annum and it is proposed that the contract commences in February 2020 and is offered to market as a three year contract with an option to extend for a further three years. The option to extend would be subject to funding and both parties agreement. The budget provision for these works is included in the approved capital programme.
3.3The work is necessary to ensure that the stock remains well maintained, compliant with regards to statutory obligations towards electrical installations as well to ensure compliance with the Housing Health and Safety Rating System.
3.4The work is also critical in order for SBC to maintain the “Decent Homes” standard. The Decent Homes standard is being reviewed as part of the Social Housing Green Paper. It is not anticipated that, as part of this review, any changes in the standards will have an impact on this proposed procurement and programme of works. The Decent Homes target is for 90% of the stock to be classified as decent at the end of each year.
3.5The scope of works for the contract includes;
Electrical rewires; Boiler and central heating installations; Replacement bathrooms and associated decorations; Replacement kitchens and associated decorations; Level access showers;
3.6As part of the review of the scope of works the In-house Repairs & Voids team will continue to carry out low-level aids and adaptations works. At this stage more complex works are assessed and carried out on an individual basis through the Councils quotation or tender process.
Part 1 - Executive – 12 June 2019 3.7 Procurement Project Team
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.