It was agreed that further consideration be given to the idea of a bid relating to Community Co-operative funding in respect of the long term management of the development should be given by the housing Development & Regeneration Executive Committee. It was further agreed that a Member Group should be convened to provide guidance to the approved developer on the street name of the development. It was RESOLVED : 1. That the Symonds Green scheme concept objectives, as developed by the Council’s Housing Development team in consultation with the Executive Housing Development Committee throughout 2018/19, be noted 2. That the Deputy Chief Executive be given delegated authority to award and finalise the terms of the contract with the winning bidder, after an officer panel has concluded an evaluation of tenders received and having consulted the Portfolio Holder for Housing, Health and Older People. Reason for As contained in report. Other options considered: As contained in report.
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
Portfolio Area Housing, Older People & Health / Resources
Date 10 July 2019
APPOINTMENT OF A PRINCIPAL CONTRACTOR AT SYMONDS GREEN
KEY DECISION
AUTHOR – ASH AHMED EXT. 2805
CONTRIBUTORS – SIMON NUTTALL EXT. 2968
LEAD/CONTACT OFFICERS – ASH AHMED EXT. 2805
1 PURPOSE 1.1 To seek approval to delegate authority for the appointment of a principal contractor of the development site at 145 Scarborough Avenue in the Symonds Green ward (the “Site”), which is also known as the Symonds Green Scheme (the “Scheme”). This will ensure an expedient tender award process and allow for a quicker mobilisation on the Site.
2 RECOMMENDATIONS 2.1 That the Executive notes the scheme concept objectives as developed by the Council’s Housing Development team in consultation with the Executive Housing Development Committee throughout 2018/19. 2.2 That the Deputy Chief Executive be given delegated authority to award and finalise the terms of the contract with the winning bidder after an officer panel has concluded an evaluation of tenders received and having consulted the Portfolio Holder: Housing, Health and Older People.
3 BACKGROUND 3.1 The Site has been subject to ongoing designs since January 2018. During this period the design proposal has evolved from an initial Scheme concept of nine homes, to a consented scheme for 29, one, two & three bedroom apartments set within a traditional urban street scene that blends into the environment without being overbearing. 3.2 Following ongoing consultation with the Housing Development Executive Committee, three separate consultations with local residents and advice from the Planning department, a final scheme of 29 properties, comprising a mix of one, two and three bed flats was submitted as a detailed planning application in February 2019. 3.3 Planning permission for the Scheme was granted on the 30 May 2019, as per Background Document 1. 3.4 PSW Building Consultancy were appointed following a competitive process in March 2019 to act for the Council as the employers agent for the scheme (the “Employer’s Agent”), and have been working in consultation with our internal Housing Investment team to produce a set of employers requirements which will determine the technical standards at which the development will be built at the Site. 3.5 The Employer’s Agent role brings external expertise in the fields of construction, site management and quantity surveying, and acts as the Council’s contract administrator for the Scheme. 3.6 The procurement documents for the Scheme were put out to tender on 30 May 2019 with the following proposed time frames:
Procurement Stage/Action Dates Invitation to Tender issued 30/05/19 Deadline for Tenderer Queries 12 noon 14/06/19 Deadline for Tenderer Clarifications to be (responses within 3 days of a published query) Tender Submission Date (by 12 noon on) 28/06/19 Evaluation Period Two weeks Decision to award (subject to call – in) 12/07/19 End of call – in period/Intention to Award the 30/07/19 Contract Announced
3.7The Scheme is an entirely social rented development, and the capital expenditure will contribute towards forecast spend on retained one for one receipts. This amplifies the benefits of achieving a rapid start on site as it ensures more receipts can be utilised and kept within the Council, rather than being returned to Central Government. 3.8 An ancillary issue relating to the Scheme is that it may feature in a proposal for a bid relating to Community Co-operative funding. The result of the bid may give rise to further considerations being needed in relation to the long term management of the Scheme. However, this will not affect the construction process nor the award of a contract for this Scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.