STEVENAGE BOROUGH COUNCIL
ENVIRONMENT & ECONOMY SELECT COMMITTEE MINUTES
Date: Monday, 29 July 2019 Time: 6.00pm Place: Autun Room, Daneshill House, Danestrete
Present: Councillors: Michael Downing (Chair), Adam Mitchell CC (Vice-Chair) , Doug Bainbridge, Adrian Brown, Teresa Callaghan, Jody Hanafin and Loraine Rossati.
Also Present: Councillor Lloyd Briscoe (Portfolio Holder for Economy, Enterprise & Transport) [name removed] (Turnback Project Manager, Network Rail) [name removed] (Stakeholder Manager, Govia Thameslink Railway) [name removed] (Principal Engineer – Transport & Policy, Hertfordshire County Council)
Start / End Start Time: 6.00pm Time: End Time: 6.57pm
1 APOLOGIES FOR ABSENCE AND DECLARATIONS OF INTEREST
Apologies for absence were received from Councillors Stephen Booth and Jim Brown.
There were no declarations of interest.
2 MINUTES - 25 JUNE 2019
It was RESOLVED that the Minutes of the meeting of the Environment & Economy Select Committee meeting held on 25 June 2019 be approved as a correct record and signed by the Chair.
The Chair drew Members’ attention to the provisional date of 3 September 2019 for the Select Committee’s next meeting, at which it was hoped that consideration would be given to the provision of Post Office services in the Borough. He asked Members to pencil in this date in their diaries/calendars.
3 STEVENAGE RAIL STATION UPDATE
The Network Rail (NR) and Govia Thameslink Railway (GTR) representatives gave presentations which provided updates on the Stevenage Turnback (5th Platform) project, the Govia Thameslink Spring 2019 timetable and the wider works along the East Coast Main Line (ECML) in support of the King’s Cross remodelling project.
1 The Network Rail (NR) representative advised that the Stevenage Turnback (5th Platform) project would provide a new bi-directional running line (2km) running parallel with the existing ECML into the new platform where services would terminate, also enabling passengers to interchange. Major works were planned as part of the upcoming engineering work on the ECML in August 2019, Christmas 2019 and February 2020. Access to the new platform would be via a new footbridge, with stairs and a lift down to platform level.
The NR representative showed a series of slides regarding the proposed new layout and some photographs of the work that had already been completed on site. He also introduced some design images of the north end of the new Platform 5, looking from various directions.
In terms of the current status and progress of works, the NR representative advised that planning permission had been obtained; there were ongoing land negotiations with the Council and land had been acquired from Legal & General; operational readiness discussions were ongoing with the Department of Transport and Govia Thameslink Railway; re-grading works were ongoing at the south end of the site; sheet piling was underway at north and south ends of the site; overhead line piling and track excavation had been completed in the north and central areas; and the changeover of a telecommunications mast and removal of the old mast had been completed.
In respect of future works, the Committee was informed that overhead line works were planned for the August 2019 Bank Holiday weekend, detailed design for the remaining works was continuing and integration would take place with other projects, such as the King’s Cross Track Improvement scheme.
The Govia Thameslink Railway (GTR) representative referred to the major incidents that had occurred on 25 July 2019 due to the extremely hot weather. Three areas of track lost overhead power cables. One of these, the Midland Main Line just north of St. Pancras, was still to be fully repaired, and had been operating on a reduced service. It was hoped that normal service would resume on 30 July 2019.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTES: 29 JULY 2019Minutes | 79 KB | DownloadRead as text |
Follow Environment & Economy Select Committee at Stevenage and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Exclusion of public and pressRESOLVED : 1. That under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the m... | Decided | Open |
| 16 Jun 2026 | Terms of referenceRESOLVED that the Terms of Reference be noted. | Noted | Open |
| 19 Mar 2026 | Update on delivery of the committee's work programme for 2025-26It was RESOLVED that the action tracker would be refreshed and brought back to a future meeting for review. | Decided | Open |
| 24 Feb 2026 | Apologies for absence and declarations of interestThat Councillor Ceara Roopchand be appointed as Chair Apologies for absence were received from Councillors Leanne Bra... | Decided | Open |
| 28 Jan 2026 | Minutes of the previous meeting of the committee held on 24 november 2025RESOLVED that the minutes of the Environment and Economy Select Committee meeting held on 24 November were approved a... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.