Resolved
It was RESOLVED that the update be noted.
Housing Management Advisory Board noted this item on Thursday 12 September 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
It was RESOLVED that the update be noted.
Housing Development
Housing Management Advisory Board September 2019 Update Agenda • Schemes in Construction • Update on progress at current sites
• Pipeline Schemes • Update on progress at future sites Schemes in Construction Gresley Way • 15 Homes – mix of 1 & 2 bed houses and flats
• Handover scheduled for 20th September Schemes in Construction
• 15 Homes – mix of 1 & 2 bed flats
• Handover scheduled for November 2019
• All Social Rented properties for the HRA
Burwell Court Schemes in Construction
• 10 Homes – mix of 1 & 2 bed flats
• Handover scheduled for December 2019
• Private sale properties used to subsidise further Council building Ditchmore Lane Pipeline Schemes North Road – 21 homes • Planning achieved in May 2019
• Contractor procured in July 2019
• Start on site imminent
• Anticipated completion in early 2021.
• Private sale properties used to subsidise further Council building. Pipeline Schemes Symonds Green – 29 homes • Planning achieved in May 2019
• Contractor procured in July 2019
• Start on site imminent
• Anticipated completion in early 2021. 29 homes are all for social rent and will include: - 19 x 1 bed - 7 x 2 bed - 3 x 3 bed Pipeline Schemes
Shephall Way – 9 homes • Planning achieved in May 2019
• Contractor procured in July 2019
• Start on site imminent
• Anticipated completion in September 2020. Kenilworth Scheme
• Total of 236 homes • 118 Homes for Council rent • 118 Homes for private sale
• Brand new state of the art independent living scheme • New retail offering • New community facilities Kenilworth Scheme - Progress to Date Demolition We have procured a demolition contractor – Work ongoing to disconnect utilities and complete asbestos surveys. Site hoarding being erected. Demolition expected to be completed by November.
Future Build The process to select the main contractor for the development will begin imminently. The build is expected to be phased in two sections, lasting a total of 4 years.
Phase 1 will include the new independent living scheme and new retail elements. 187 New HOMES so far … 40 MORE IN CONSTRUCTION… 295 MORE IN THE PIPELINE Questions, discussion
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HOUSING DEVELOPMENT UPDATEReport | 1.7 MB | DownloadRead as text |
Follow Housing Management Advisory Board at Stevenage and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Sep 2019 | Minutes - 15 august 2019It was RESOLVED that the minutes of the Housing Management Advisory Board meeting held on 15 August 2019 be approved ... | Approved | Open |
| 12 Sep 2019 | Independent living allocation review reportIt was RESOLVED that the review be noted. | Noted | Open |
| 15 Aug 2019 | Housing service performance report q1It was agreed that future performance reports should include a commentary on management voids as a mitigation against... | Agreed | Open |
| 15 Aug 2019 | Repairs and voids updateIt was RESOLVED that the update be noted. | Noted | Open |
| 15 Aug 2019 | Housing all under one roof updateIt was RESOLVED that the update be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.