In respect of a Member’s query regarding the High Priority Recommendations in relation to Cyber Security, particularly the Management Comment that it was “very rare (if ever) that someone connects an external device to the IT network”, the SIAS Client Audit Manager agreed to clarify this comment with the ICT Strategic Partnership Manager and advise Members of the Committee. It was
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
Members are recommended to: a) Note the Internal Audit Progress Report b) Approve Amendments to the Internal Audit Plan as at 25 October 2019 c) Note the Status of Critical and High Priority Recommendations SIAS Internal Audit Progress Report Stevenage Borough Council
Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.4 Proposed Audit Plan Amendments 2.5 Performance Management 2.7 Critical and High Priority Recommendations
Appendices: A Progress Against the 2019/20 Audit Plan B Implementation Status of Critical and High Priority Recommendations C Audit Plan Items (April 2019 to March 2020) - Indicative Start Dates Agreed with Management D Assurance Definitions / Priority Levels SIAS Internal Audit Progress Report Stevenage Borough Council
1 Introduction and Background Purpose of Report
1.1To provide Members with:
a) The progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s 2019/20 Internal Audit Plan as at 25 October 2019. b) The findings for the period 1 April 2019 to 25 October 2019. c) The proposed amendments required to the approved Internal Audit Plan. d) The implementation status of previously agreed audit recommendations. e) An update on performance management information as at 25 October 2019.
Background
1.2Internal Audit’s Annual Plan for 2019/20 was approved by the Audit Committee at its meeting on 19 March 2019. The Audit Committee receive periodic updates against the Annual Internal Audit Plan.
1.3The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that the internal audit function is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed Annual Internal Audit Plan.
2 Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 25 October 2019, 46% of the 2019/20 Audit Plan days have been delivered (calculation excludes contingency days that have not yet been allocated).
2.2Final reports for the following audits and projects have been issued or completed so far this financial year:
Assurance Number of Audit Title Date of Issue Level Recommendations
Two High, One Medium, Stevenage Museum July 2019 Satisfactory Five Low/Advisory priority Herts Home Seven High, Eight Medium, Improvement Agency July 2019 Limited Three Low/Advisory priority (2018/19) * Cemeteries August 2019 Satisfactory Four Medium priority One Medium, One Insurance August 2019 Good Low/Advisory priority Rechargeable Works Sept 2019 Good One Medium priority
Page 1 SIAS Internal Audit Progress Report Stevenage Borough Council
Safeguarding Sept 2019 Good Three Low/Advisory priority Homelessness Sept 2019 Good None Reduction Act Health & Safety Oct 2019 Good One Medium priority
* This was a Hertfordshire County Council led internal audit which has been distributed to the Council as a contributing partner of the Hertfordshire Home Improvement Agency.
2.3The table below also summarises the position regarding 2019/20 projects as at 25 October. Appendix A provides a status update on each individual project within the 2019/20 Internal Audit Plan. Details of indicative start dates for the individual projects are also shown in Appendix C.
Status No. of Audits at this Stage % of Total Audits
Final Report Issued 7 19%
Draft Report Issued 7 19% In Fieldwork/Quality 4 12% Review In Planning/Terms of 8 22% Reference Issued Allocated 8 22%
Not Yet Allocated 1 3%
Deferred/Cancelled 1 3%
Total 36 100%
Proposed Audit Plan Amendments
2.4The audit of Land Charges, due to start during July 2019, has been cancelled and the audit days returned to contingency. This was due to Land Charges staff having insufficient availability.
Performance Management
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.