It was RESOLVED that the Minutes of the meetings of the Audit Committee held on 12 November 2019 and 27 November 2019 be approved as correct records and signed by the Chair. The Chair announced that a presentation on the progress of the Council’s ICT Strategy would be submitted to the next meeting of the Committee to be held on 17 March 2020. In respect of Minute 3 of the meeting of the Committee held on 27 November 2019, it was noted that an appropriate senior officer in the Regeneration Team would be invited to a future meeting in the summer of 2020 to provide an update on the financial risks associated with the Queensway LLP. In terms of the 2018/19 external audit, the Assistant Director (Finance & Estates) advised that Ernst & Young had 5 outstanding queries. Due to priority work on the Council’s budget for 2020/21, she had been unable to respond to these queries, but would do so during February 2020, thereby enabling the Statement of Accounts to be signed off. The Assistant Director (Finance & Estates) commented that Hertfordshire CFO’s would be collectively writing to the Public Sector Audit Appointments (PSAA) regarding clarification about EY’s move to for a 30 September deadline for 2019/20 audit of accounts from the 31 July for audit sign off of the accounts. It is the CFO’s preference that if the Finance Team are required to publish their unaudited accounts by the end of May each year, it would be backward step to wait until the end of September for the accounts to signed off.
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
Present: Councillors: Maureen McKay (Chair), John Gardner (Vice-Chair), Sandra Barr, Lizzy Kelly and Graham Lawrence.
Start / End Start Time: 6.00pm Time: End Time: 7.02pm
1 APOLOGIES FOR ABSENCE AND DECLARATIONS OF INTEREST
Apologies for absence were received from Councillors Stephen Booth, Laurie Chester and David Cullen, and from [name removed] (Independent Co-opted Member).
There were no declarations of interest.
2 MINUTES - 10 SEPTEMBER 2019
It was RESOLVED that the Minutes of the Audit Committee meeting held on 10 September 2019 be approved as a correct record and signed by the Chair.
3 EXTERNAL AUDIT 2018/19 - PROGRESS REPORT
The Finance Manager (Technical) gave a verbal update on progress with regard to the 2018/19 External Audit.
The Finance Manager (Technical) advised that the External Auditors, Ernst & Young, had been on site at SBC since 30 September 2019. Two new significant risks had been identified in relation to the Queensway development, namely the decision-making process and the method of asset valuation. There were also a few outstanding issues in respect of the value for money conclusions.
The Finance Manager (Technical) commented that the External Auditors were also looking at the Medium Term Financial Strategy, with a view to assuring that the General Fund budget position was not being propped up by the Queensway project. The Group Accounts also needed to be agreed to reflect the valuation of Queensway and until this was completed the Statement of Accounts and audit could not be finalised. Ernst & Young aimed to complete this work by the due deadline, but it could be that the Statement of Accounts are published with any outstanding information to follow.
1 The Committee was informed that Ernst & Young had raised concerns that the Annual Governance Statement (AGS) made no mention of the Queensway and SG1 developments, and so it was likely that the Statement of Accounts/Audit Committees would be requested to approved an updated AGS at their joint meeting on 27 November 2019.
It was RESOLVED that the verbal progress report in respect of the 2018/19 External Audit be noted.
4 PROGRESS WITH DELIVERY OF 2019/20 ANTI-FRAUD PLAN
The Shared Anti-Fraud Manager presented a progress report on the Anti-Fraud Plan 2019/20.
The Shared Anti-Fraud Manager drew attention to Appendix B to the report, the Shared Anti-Fraud Service (SAFS) Action Plan 2019/20. He was pleased to report that all key actions were on target to be delivered by the end of March 2020. SAFS was currently working with the SBC Human Resources Team to develop an E- Learning package on fraud.
In respect of fraud referrals, the Shared Anti-Fraud Manager advised that 112 of these had now been received, in excess of the target of 100. Of the 71 lives cases still under investigation, the estimated fraud loss and savings combined was estimated to exceed £320,000.
The Shared Anti-Fraud Manager explained that the joint work between the SBC Parking Enforcement Officers and SAFS Team on Blue Badge fraud was going well. He also drew attention to the 2018/19 National Fraud Initiative data-sharing exercise, which had identified 1,612 potential matches. As at the end of September 2019 161 high risk matters had been reviewed and savings of £184,000 recorded.
In reply to a series of Members’ questions, the Shared Anti-Fraud Manager commented as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.