The Leader commented that the National Audit Office (NAO) had publically criticised local authorities for their level of investment in commercial property. She considered that such activity had been necessitated by the continual reduction in local government funding, and advised that the District Councils Network would be sending a robust reply to the NAO on this matter. It was RESOLVED that the following proposals be recommended to Council on 26 February 2020: 1. That the final 2020/21 General Fund Capital Programme, as summarised in the report, be approved. 2. That the final 2020/21 HRA Capital Programme, as summarised in the report, be approved. 3. That the updated forecast of resources, as summarised in the report, be approved. 4. That the Council’s investment strategy for non-treasury assets, as set out in Section 3.2 of the report, be approved. 5. That the approach to resourcing the General Fund capital programme, as outlined in the report, be approved. 6. That the actions required to ensure the General Fund programme is funded, as outlined in Paragraphs 4.9.3-4.9.9 of the report, be noted. 7. That the approach and progress on Locality Reviews and the target to realise receipts for 2020/21 be noted. 8. That the growth bids now included in the Capital Strategy be approved. 9. That the return of Right to Buy one for one receipts, as outlined in Section 4.14 of the report, be noted. 10. That the 2020/21 de- minimis expenditure limit (Section 4.15 of the report) be approved. 11. That the 2020/21 contingency allowance (Section 4.16 of the report) be approved. 12. That the work undertaken by Leader’s Financial Security Group (LFSG) on behalf of the Executive in reviewing and challenging the General Fund Capital Strategy be noted. Reason for As contained in report. Other Options considered: As contained in report.
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
Authors Clare Fletcher x 2933 Contributors Senior Leadership Team Lead Officers Clare Fletcher x 2933 Contact Officer Clare Fletcher x 2933
1. PURPOSE 1.1 To approve revisions to the 2019/20 General Fund and Housing Revenue Account Capital Programme and approve the final Capital Programme for 2020/21 for consideration by Council. 1.2 To provide Members with an update on the Council’s draft five Year Capital Strategy and the resources available to fund the Capital Strategy. 1.3 To provide Members with an update on government changes to prudential borrowing requirements. 1.4 To provide Members with an update on the Council’s investment strategy as required by the updated prudential code. 1.5 To set out the Council’s approach to funding its key Future Council priorities. 1.6 To set out the work of the Leader’s Financial Security Group (LFSG) in reviewing all General Fund capital bids prior to inclusion in the 2020/21 onwards Capital Strategy.
2. RECOMMENDATIONS EXECUTIVE: That the following proposals be recommended to Council on 26 February 2020: 2.1 That the final 2020/21 General Fund Capital Programme as summarised in the report be approved. 2.2 That the final 2020/21 HRA Capital Programme as summarised in the report be approved. 2.3 That the updated forecast of resources as summarised in the report be approved. 2.4 That the Council’s investment strategy for non-treasury assets, section 3.2 of the report be approved. 2.5 That the approach to resourcing the General Fund capital programme as outlined in the report be approved. 2.6 That the actions required to ensure the General Fund programme is funded as outlined in paragraphs 4.9.3-4.9.9 of the report be noted. 2.7 That the approach and progress on Locality Reviews be noted and the target to realise receipts for 2020/21. 2.8 That the growth bids now included in the Capital Strategy be approved. 2.9 That the return of Right to Buy one for one receipts as outlined in section 4.14 of the report be noted. 2.10 That the 2020/21 de-minimis expenditure limit (section 4.15 of the report) be approved. 2.11 That the 2020/21 contingency allowance (section 4.16 of the report) be approved. 2.12 That the work undertaken by LFSG on behalf of the Executive in reviewing and challenging the General Fund Capital Strategy be noted.
3. BACKGROUND 3.1 Introduction 3.1.1 This report is an update on the Council’s Draft General Fund and HRA capital strategy 2020/21- 2024/25 presented to the January 2020 Executive meeting. This report gives updates on the 2019/20 and 2020/21 budgets and resourcing for the General Fund and HRA programme 3.1.2 The draft General Fund programme totalled £62.38Million (subject to sufficient resources being available and is summarised in the table below. This did not include any changes as a result of the approval of the Kenilworth tender at the January Executive. General Fund Capital 2020/21-2024/25 £'000 £55,870 £60,000 £50,000 £40,000 £30,000 £20,000 £10,000 £1,826 £1,190 £2,495 £1,000 £0 already Health & Safety Reviewed Bids scored 1.5 Deferred approved works previously -2 Works budget agreed bids
3.1.3 The HRA programme included in the Draft Capital Strategy totalled £231Million and was in line with the Business Plan, with the exception of changes arising from the Kenilworth scheme as summarised below.
Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.