Resolved
The Executive considered a report in respect of the Capital Programme Outturn position for 2019/20. It was As contained in report. Other Options considered: As contained in report.
Executive (up to May 2024) decided this item on Wednesday 8 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
The Executive considered a report in respect of the Capital Programme Outturn position for 2019/20. It was As contained in report. Other Options considered: As contained in report.
2.1That the 2019/20 General Fund capital expenditure outturn of £13.1Million be noted, (subject to the completion of the 2019/20 external audit of accounts).
2.2That the 2019/20 HRA capital expenditure outturn of £30.4 Million be noted (subject to the completion of the 2019/20 external audit of accounts).
2.3That the funding applied to the 2019/20 General Fund capital programme be approved as summarised in paragraph 4.2.1.
2.4That the funding applied to the 2019/20 HRA capital programme be approved as summarised in paragraph 4.5.1. 2.5 That the 2020/21 General Fund capital programme net increase of £517K be approved comprising of: £3.9Million slippage from 2019/20 (as detailed in para 4.3.8), £3.3Million re-profiled into 2021/22, £125K reduction to mitigate the impact of Covid-19 on revenue resources available to support the capital programme, and an additional net reduction of £10k funding no longer required in 2020/21 (as detailed in Appendix A to this report).
2.6That the 2020/21HRA capital programme net decrease of £0.4 Million, due to slippage into 2019/20, be approved as summarised in paragraph 4.6.1 and detailed in Appendix B to this report.
2.7That the use of £15K from the Deferred Works Reserve for 3 CCTV cameras which need to be replaced as set out in paragraph 4.3.4 be approved.
3.1The 2019/20 capital programme was last approved by Members at the March Executive as part of the 3 rd quarter monitoring report. At March Executive the 2019/20 revised General Fund capital programme was projected to be £17.3 Million and the 2019/20 revised HRA capital programme was projected to be £29.9 Million, a total of £47.2 Million.
3.2Since the Executive meeting the economic and social landscape has changed substantially with a country wide “lockdown” to mitigate the impacts of the Covid19 pandemic. A refreshed Medium Term Financial strategy was approved by Executive in June in the report ‘Review of the Medium-Term Financial Strategy and Impact of Covid 19 on the Council’s General Fund Revenue Budget’, to seek to mitigate the immediate impact on the Council’s resources. Included in that report were changes to the financing of the 2019/20 and 2020/21 capital strategy, by the use of a Regeneration receipt to replace revenue contributions to capital, and the removal of schemes totalling £125k from the programme. Those changes have been incorporated into this report.
3.3The Accounts and Audit Regulations contain provisions on financial management, annual accounts and audit procedures. Within the amended regulations there is no requirement for Member approval of the Statement of Accounts prior to the completion of the external audit and only the Responsible Financial Officer must certify the presentation of the pre audit annual accounts. This would normally be by the 31 May 2020 for financial year end of 31 March 2020. However, in response to the COVID-19 crisis, the publication date for the 2019/20 pre audit accounts has been put back to 31st August and the publication date for the final, audited accounts has been moved from 31 July to 30 November 2020. The aim is to publish the draft Statement of Accounts on the Council’s website accompanied by the Annual Governance Statement by 30 June 2020.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL EXPENDITURE OUTTURN 2019/20Report | 590 KB | DownloadRead as text |
PDF |
Item 9: Appendix A: GF Capital Strategy OutturnAppendix | 284 KB | Download |
PDF |
Item 9: Appendix B: HRA Capital Strategy OutturnAppendix | 250 KB | Download |
Follow Executive (up to May 2024) at Stevenage and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Mar 2024 | Apologies for absence and declarations of interestApologies for absence were submitted on behalf of Councillors Richard Henry (Chair), Sandra Barr and [name removed]. ... | Decided | Open |
| 13 Mar 2024 | Minutes - 7 february 2024It was RESOLVED that the Minutes of the meeting of the Executive held on 7 February 2024 be approved as a correct rec... | Approved | Open |
| 13 Mar 2024 | Minutes of overview & scrutiny committee and select committeesThe Portfolio Holder for Environment and Performance thanked the Chair and Members of the Environment & Economy Selec... | Noted | Open |
| 13 Mar 2024 | Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program... | Agreed | Open |
| 13 Mar 2024 | Housing consumer standards - social housing (regulation) act 2023The Executive considered a report in respect of the Social Housing (Regulation) Act 2023, which introduced wide rangi... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.