Resolved
It was RESOLVED that the minutes of the Planning & Development Committee held on 8 December 2020 are approved as a correct record and signed by the Chair.
Planning and Development Committee approved this item on Wednesday 6 January 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
It was RESOLVED that the minutes of the Planning & Development Committee held on 8 December 2020 are approved as a correct record and signed by the Chair.
STEVENAGE BOROUGH COUNCIL
PLANNING AND DEVELOPMENT COMMITTEE MINUTES
Date: Tuesday, 8 December 2020 Time: 6.30pm Place: Virtual (via Zoom)
Present: Councillors: Simon Speller (Chair), Maureen McKay (Vice Chair), Doug Bainbridge, Sandra Barr, Laurie Chester, Michael Downing, Michelle Gardner, Jody Hanafin, Lizzy Kelly, Graham Lawrence, John Lloyd, Graham Snell and Tom Wren
Start / End Start Time: 6.30pm Time: End Time: 10.40pm
1 APOLOGIES FOR ABSENCE AND DECLARATIONS OF INTEREST
There were no apologies for absence and no declarations of interest.
2 MINUTES - 4 NOVEMBER 2020
It was RESOLVED that the Minutes of the meeting of the Planning and Development Committee held on 4 November 2020 be approved as a correct record and signed by the Chair.
3 UNIT B3, COCKERELL CLOSE, STEVENAGE (20/00548/FPM)
The Committee considered an application for the installation of a mezzanine floor and enclosed external compound.
The Planning Officer gave an introduction to the Committee. She advised that the main issues for consideration in the determination of this application were the acceptability in land use policy terms, the impact on the character and appearance of the area, impact upon neighbouring amenities, parking provision and highway implications of the mezzanine floor and storage compound only.
The Committee was advised that the use of the premises by FIRA Elements was considered acceptable in land use policy terms and the installation of the mezzanine floor and external storage compound were not considered to harm the visual amenities of the area or the amenities of neighbouring residential dwellings and businesses. It was accepted that the car parking provision was below the recommended standard as laid out in the Car Parking Provision SPD (2020), however the site was in a highly sustainable location and offered excellent opportunities of non-car modes of transport and so, on balance, it was considered acceptable in this instance to allow a shortfall in car parking provision.
In response to a question regarding cycle parking, the Planning Officer advised that
1 the car parking provision SPD stated that for this size of business, 5 cycle spaces should be provided. A condition had therefore been imposed requesting details of cycle storage prior to the occupation of the premises.
It was RESOLVED:
That planning permission be granted subject to the following conditions:
1. The development hereby permitted shall be carried out in accordance with the following approved plans: 1980-01A; 1980-02; 1980-03A; 1980-04A; 1980-05A; 1980-06A; 1980-07; 1980-08; 1980-09; 1980-10; 1980-11; 1980-12; 1980-13; 1980-14; 1980-15; 1980-16; 1980-17; 1980-18; 1980-Location; 1980 Block 500;
2. The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
3. No demolition or construction work relating to this permission shall be carried out on any Sunday, Public or Bank Holiday nor at any other time, except between the hours of 08:00 and 18:00 on Mondays to Fridays and between the hours of 09:00 and 13:00 on Saturdays.
4. Prior to the first occupation of the development hereby permitted, details of secure cycle parking provision shall be submitted to and approved in writing by the Local Planning Authority. The secure cycle parking facility shall thereafter be implemented in accordance with the approved details.
5. The external storage compound hereby approved shall be constructed in accordance with the approved plans.
6. There shall be no open storage of refuse, goods or materials other than in compounds or areas specifically set aside for this purpose and shown on a plan submitted to and approved by the Local Planning Authority in writing.
Informative
1. Community Infrastructure Levy
Stevenage Borough Council adopted a Community Infrastructure Levy (CIL) Charging Schedule at Full Council on 27 January 2020 and started implementing CIL on 01 April 2020.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTES: 8 DECEMBER 2020Minutes | 183 KB | DownloadRead as text |
Follow Planning and Development Committee at Stevenage and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Oct 2026 | 26/00427/fpm - lister hospital, coreys mill laneRESOLVED that planning permission be GRANTED subject to the applicant having first entered into a Unilateral Undertak... | Decided | Open |
| 8 Oct 2026 | Information report - delegated decisionsRESOLVED that the Information Report – Delegated Decisions be noted. | Noted | Open |
| 8 Oct 2026 | Information report - appeals/called in applicationsRESOLVED that the Information Report – Appeals / Called In Decisions be noted. | Noted | Open |
| 8 Oct 2026 | Exclusion of the press and publicRESOLVED : 1. That under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the m... | Decided | Open |
| 8 Sep 2026 | 26/00531/fph - 134 shephall viewIt was agreed that the matter could be discussed outside the meeting to consider whether any further action could be ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.