SIAS INTERNAL AUDIT PLAN 2020/21 - PROGRESS REPORT

Noted Finance 1 paper

Audit Committee noted this item on Wednesday 24 March 2021. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Simon Martin from Shared Internal Audit Service (SIAS) provided an update on the progress made by the SIAS in delivering the Council’s 2020/21 Internal Audit Plan. He advised Members that the following final reports had been issued since the last Audit Committee meeting on 9 February 2021: · Housing Repairs · Cash and Banking · Tree Management · Landlord Health and Safety Compliance It was RESOLVED : · That the Internal Audit Progress report be noted. · That the Status of Critical and High Priority Recommendations be noted. That the Proposed Changes to SIAS Audit Opinions be approved.
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Audit Committee

Recommendation

Members are recommended to: a) Note the Internal Audit Progress Report b) Note the Status of Critical and High Priority Recommendations c) Approve Proposed Changes to SIAS Audit Opinions SIAS Internal Audit Progress Report Stevenage Borough Council

Contents

1 Introduction and Background 1.1 Purpose 1.2 Background

2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.4 Internal Audit Plan Changes 2.5 Critical and High Priority Recommendations 2.7 Performance Management 2.9 Proposed Changes to SIAS Audit Opinions

Appendices: A Progress against the 2020/21 Audit Plan B Implementation Status of Critical and High Priority Recommendations C Internal Audit Plan Items (April 2020 to March 2021) - Indicative start dates agreed with management D Assurance Definitions / Priority Levels SIAS Internal Audit Progress Report Stevenage Borough Council

1 Introduction and Background Purpose of Report

1.1To provide Members with:

a) The progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s 2020/21 Internal Audit Plan as at 5 March 2021. b) The findings for the period 1 April 2020 to 5 March 2021. c) Details of any proposed changes to the approved Internal Audit Plan. d) The implementation status of previously agreed audit recommendations. e) An update on performance management information as at 5 March 2021. f) Details of proposed changes to SIAS audit opinions.

Background

1.2Internal Audit’s Annual Plan for 2020/21 was approved by the Audit Committee at its meeting on 9 June 2020. The Audit Committee receive periodic updates against the Internal Audit Plan.

1.3The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit function is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed changes to the agreed Annual Internal Audit Plan.

2 Audit Plan Update Delivery of Audit Plan and Key Audit Findings

2.1As at 5 March 2021, 74% of the 2020/21 Audit Plan days have been delivered (the calculation excludes contingency days that have not yet been allocated).

2.2The following final reports have been issued since the last committee meeting on 9 February 2021:

Date of Assurance Number of Audit Title Issue Level Recommendations

Housing Repairs Feb 2021 Satisfactory Three Medium priority

Cash & Banking Feb 2021 Good None

Tree Management Feb 2021 Good Two Medium priority Landlord Health & Two High, one Medium, Feb 2021 Limited Safety Compliance one Low priority

2.3The table below summarises the position regarding 2020/21 projects as at 5 March 2021. Appendix A provides a status update on each individual project within the 2020/21 Internal Audit Plan.

Page 1 SIAS Internal Audit Progress Report Stevenage Borough Council

Status No. of Audits at this Stage % of Total Audits

Final Report Issued 10 29

Draft Report Issued 5 14 In Fieldwork/Quality 12 34 Review In Planning/Terms of 2 6 Reference Issued Allocated 0 0

Not Yet Allocated 0 0

Cancelled 6 17 Total 35 100%

Proposed Audit Plan Changes

2.4There has been no proposed change to the Internal Audit Plan since the last committee meeting.

Critical and High Priority Recommendations

2.5Members will be aware that a Final Audit Report is issued when it has been agreed (“signed off”) by management; this includes an agreement to implement the recommendations that have been made.

2.6The schedule attached at Appendix B details any outstanding Critical and High priority audit recommendations.

Performance Management

2.7The 2020/21 annual performance indicators were approved at the SIAS Board meeting in March 2020.

2.8The actual performance for Stevenage Borough Council against the targets that can be monitored in year is set out in the table below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SIAS INTERNAL AUDIT PLAN 2020/21: PROGRESS REPORTReport 494 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
TC
Teresa CallaghanChair, present
JG
John GardnerVice-Chair, present
SB
Sandra BarrCommittee Member, present
SB
Stephen BoothCommittee Member, apologies
LC
Laurie ChesterCommittee Member, present
DC
David CullenCommittee Member, apologies
LK
Lizzy KellyCommittee Member, present
GL
Graham LawrenceCommittee Member, present
GG
Geoffrey GibbsCo-Optee, present

On this subject at Stevenage

Search all
  1. SIAS INTERNAL AUDIT PLAN 2020/21 - PROGRESS REPORTThis decision
  2. Sias annual assurance statement and internal audit report 2025/26Noted
  3. Shared internal audit service (sias) progress reportNoted
  4. Sias annual assurance statement and internal audit report 2024/25Noted
  5. Shared internal audit service (sias) internal audit plan 2025/26Noted
  6. Shared internal audit service (sias) internal audit plan 2024/25Approved

More from Stevenage Audit Committee

All decisions
MeetingDecisionOutcome
2 Jun 2026 Sias annual assurance statement and internal audit report 2025/26RESOLVED that: · The Annual Assurance Statement and Internal Audit Annual Report 2025/26 be noted. · The results of t... Noted Open
2 Jun 2026 2025/26 annual governance statement and local code of corporate governanceRESOLVED that the report be noted. Noted Open
2 Jun 2026 Annual report of the audit committeeRESOLVED that the report be noted. Noted Open
2 Jun 2026 Exclusion of public and pressRESOLVED : 1. That, under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the ... Decided Open
2 Jun 2026 Strategic risk registerRESOLVED that the report be noted. Noted Open