The Executive considered a report with regard to the proposed construction of a new Station North Multi-Storey Car Park (MSCP) and Cycle Hub as part of a Sustainable Transport Interchange. The following comments were made by Members: · Officers were asked to give consideration to the re-instatement of the Fairlands Valley Showground “Park and Ride” bus service for the duration of the construction works on the new MSCP; · In view of the ever-changing car parking landscape in the town, Officers were requested to add a new section to the SBC website showing visitors where to park in the Town Centre, which could be regularly updated as changes were brought about through the various stages of the Town Centre Regeneration Programme; · Officers undertook to investigate and report back to Members on the provision of disabled parking spaces on the Station South Car Park whilst construction of the new MSCP was taking place on the Station North Car Park; · Following conclusion of the planning process, officers were asked to report back to Members to update them on Hertfordshire County Council’s comments with regard to any highway impacts of the proposed development; and · The Assistant Director (Regeneration) was asked to give provide an overview of the project to the next meeting of the Overview & Scrutiny Committee. It was
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
CONSTRUCTION OF A NEW STATION NORTH MULTI-STOREY CAR PARK AND CYCLE HUB AS PART OF SUSTAINABLE TRANSPORT INTERCHANGE
KEY DECISION
1. PURPOSE 1.1. This report follows the item previously presented to Executive in November 2020 relating to the construction of a new Multi-Storey Car Park & Cycle hub (MSCP), which recognised the long-term need to consolidate the parking offer in Stevenage Town Centre. That report also considered the impact of the Covid-19 pandemic on parking and the resulting temporary reduction in demand. 1.2. New developments within the town centre are now underway (Matalan/Guinness & Marshgate Life Sciences redevelopments) increasing the pressure on long-stay parking capacity. Car park usage has also increased significantly following the lifting of restrictions imposed during the pandemic, although these have yet to return to 2019 levels. 1.3. In order ensure adequate capacity - and prevent future loss of parking revenue, it is now appropriate to consider the construction of a new MSCP taking into account: overall parking capacity, planned changes to existing car parks, increasing demand, construction materials availability, build times and pricing challenges. 1.4. This report provides an update on the feasibility and design process, a design & build contractor having been appointed and design & feasibility work having been completed. 1.5. A detailed cost plan has been produced and the sources of funding for the project have been identified and relevant documents have been prepared for the purposes of seeking planning approval. 1.6. Finally this report notes that further work is necessary to set out the extent of any council borrowing and impact on revenue during the construction as well phase as what mitigation will be required to meet parking demand until the new provision is in place. This work will be reported to Executive in early in the New Year (2022).
2. RECOMMENDATIONS 2.1. That Executive note: 2.1.1. the impact of new and existing redevelopments in the town centre and the impact it will have on car parking capacity and locations; 2.1.2. that an application for planning approval is being prepared for submission for the MSCP & cycle hub facility; 2.1.3. the emerging design for the MSCP, which can be refined during and after the planning process; 2.1.4. the total estimated budget for the scheme is £9.7m, with a target construction price of £8.9m; 2.1.5. the decision-making gateways for the project; 2.1.6. the revenue impact of any borrowing to fund the capital cost and any forecasted one-off income loss during construction are key financial considerations for the General Fund , authority will be sought from Council to delegate to Executive approval of the additional borrowing and change to the Treasury Management Strategy, subject to the revenue impacts falling within current Executive delegated limits.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.