CONSTRUCTION OF A NEW STATION NORTH MULTI-STOREY CAR PARK AND CYCLE HUB AS PART OF A SUSTAINABLE TRANSPORT INTERCHANGE

Decided Executive 7 papers

Executive (up to May 2024) decided this item on Wednesday 8 December 2021. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

The Executive considered a report with regard to the proposed construction of a new Station North Multi-Storey Car Park (MSCP) and Cycle Hub as part of a Sustainable Transport Interchange. The following comments were made by Members: · Officers were asked to give consideration to the re-instatement of the Fairlands Valley Showground “Park and Ride” bus service for the duration of the construction works on the new MSCP; · In view of the ever-changing car parking landscape in the town, Officers were requested to add a new section to the SBC website showing visitors where to park in the Town Centre, which could be regularly updated as changes were brought about through the various stages of the Town Centre Regeneration Programme; · Officers undertook to investigate and report back to Members on the provision of disabled parking spaces on the Station South Car Park whilst construction of the new MSCP was taking place on the Station North Car Park; · Following conclusion of the planning process, officers were asked to report back to Members to update them on Hertfordshire County Council’s comments with regard to any highway impacts of the proposed development; and · The Assistant Director (Regeneration) was asked to give provide an overview of the project to the next meeting of the Overview & Scrutiny Committee. It was
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Executive (up to May 2024)

Part I

Meeting Executive

Portfolio Area Regeneration

Date 8 December 2021

CONSTRUCTION OF A NEW STATION NORTH MULTI-STOREY CAR PARK AND CYCLE HUB AS PART OF SUSTAINABLE TRANSPORT INTERCHANGE

KEY DECISION

1. PURPOSE 1.1. This report follows the item previously presented to Executive in November 2020 relating to the construction of a new Multi-Storey Car Park & Cycle hub (MSCP), which recognised the long-term need to consolidate the parking offer in Stevenage Town Centre. That report also considered the impact of the Covid-19 pandemic on parking and the resulting temporary reduction in demand. 1.2. New developments within the town centre are now underway (Matalan/Guinness & Marshgate Life Sciences redevelopments) increasing the pressure on long-stay parking capacity. Car park usage has also increased significantly following the lifting of restrictions imposed during the pandemic, although these have yet to return to 2019 levels. 1.3. In order ensure adequate capacity - and prevent future loss of parking revenue, it is now appropriate to consider the construction of a new MSCP taking into account: overall parking capacity, planned changes to existing car parks, increasing demand, construction materials availability, build times and pricing challenges. 1.4. This report provides an update on the feasibility and design process, a design & build contractor having been appointed and design & feasibility work having been completed. 1.5. A detailed cost plan has been produced and the sources of funding for the project have been identified and relevant documents have been prepared for the purposes of seeking planning approval. 1.6. Finally this report notes that further work is necessary to set out the extent of any council borrowing and impact on revenue during the construction as well phase as what mitigation will be required to meet parking demand until the new provision is in place. This work will be reported to Executive in early in the New Year (2022).

2. RECOMMENDATIONS 2.1. That Executive note: 2.1.1. the impact of new and existing redevelopments in the town centre and the impact it will have on car parking capacity and locations; 2.1.2. that an application for planning approval is being prepared for submission for the MSCP & cycle hub facility; 2.1.3. the emerging design for the MSCP, which can be refined during and after the planning process; 2.1.4. the total estimated budget for the scheme is £9.7m, with a target construction price of £8.9m; 2.1.5. the decision-making gateways for the project; 2.1.6. the revenue impact of any borrowing to fund the capital cost and any forecasted one-off income loss during construction are key financial considerations for the General Fund , authority will be sought from Council to delegate to Executive approval of the additional borrowing and change to the Treasury Management Strategy, subject to the revenue impacts falling within current Executive delegated limits.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CONSTRUCTION OF A NEW STATION NORTH MULTI-STOREY CAR PARK AND CYCLE HUB AS PART OF A SUSTAINABLE TRANSPORT INTERCHANGEReport 486 KB DownloadRead as text
PDF
Item 6: Appendix A: MSCP Proposed Site PlanAppendix 2.5 MB Download
PDF
Item 6: Appendix B: MSCP Proposed General Arrangement South ElevationAppendix 1.6 MB Download
PDF
Item 6: Appendix C: MSCP West ElevationAppendix 15 MB Download
PDF
Item 6: Appendix D: MSCP East ElevationAppendix 3.3 MB Download
PDF
Item 6: Appendix E: MSCP Stair Cores Design ProposalAppendix 296 KB Download
PDF
Item 6: Appendix F: MSCP Night Time CGIAppendix 87 KB Download

At this meeting

Whole meeting

Who was there

6 of 8 attended
ST
Sharon Taylor OBE CCChair, present
JL
Mrs Joan LloydVice-Chair, present
LB
Lloyd BriscoeCommittee Member, present
RB
Rob BroomCommittee Member, apologies
JG
John GardnerCommittee Member, present
RH
Richard HenryCommittee Member, present
JH
Jackie HollywellCommittee Member, apologies
JT
Jeannette ThomasCommittee Member, present

More from Stevenage Executive (up to May 2024)

All decisions
MeetingDecisionOutcome
13 Mar 2024 Apologies for absence and declarations of interestApologies for absence were submitted on behalf of Councillors Richard Henry (Chair), Sandra Barr and [name removed]. ... Decided Open
13 Mar 2024 Minutes - 7 february 2024It was RESOLVED that the Minutes of the meeting of the Executive held on 7 February 2024 be approved as a correct rec... Approved Open
13 Mar 2024 Minutes of overview & scrutiny committee and select committeesThe Portfolio Holder for Environment and Performance thanked the Chair and Members of the Environment & Economy Selec... Noted Open
13 Mar 2024 Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program... Agreed Open
13 Mar 2024 Housing consumer standards - social housing (regulation) act 2023The Executive considered a report in respect of the Social Housing (Regulation) Act 2023, which introduced wide rangi... Decided Open