SIAS INTERNAL AUDIT PLAN 2021/22 - PROGRESS REPORT

Decided Finance 1 paper

Audit Committee decided this item on Monday 28 March 2022. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

The SIAS Client Audit Manager presented a progress report with regard to the SIAS Internal Audit Plan 2021/22 (up to 11 March 2022). The Committee requested the SIAS Client Audit Manager to re-instate the cancelled Quarter 4 IT Resilience audit into the Audit Plan for 2022/23. It was
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Audit Committee

Recommendation

Members are recommended to: a) Note the Internal Audit Progress Report b) Approve Changes to the Internal Audit Plan as at 11 March 2022 c) Note the Status of Critical and High Priority Recommendations SIAS Internal Audit Progress Report Stevenage Borough Council

Contents

1 Introduction and Background 1.1 Purpose 1.2 Background

2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.4 Internal Audit Plan Changes 2.5 Critical and High Priority Recommendations 2.7 Performance Management

Appendices: A Progress against the 2021/22 Audit Plan B Implementation Status of Critical and High Priority Recommendations C Internal Audit Plan Items (April 2021 to March 2022) - Indicative start dates agreed with management D Assurance Definitions / Priority Levels SIAS Internal Audit Progress Report Stevenage Borough Council

1 Introduction and Background Purpose of Report

1.1To provide Members with:

a) The progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s 2021/22 Internal Audit Plan to 11 March 2022. b) Final audit reports issued for the period 21 January 2022 to 11 March 2022. c) Details of any changes to the approved Internal Audit Plan. d) The implementation status of previously agreed audit recommendations. e) An update on performance management information to 11 March 2022.

Background

1.2Internal Audit’s Annual Plan for 2021/22 was approved by the Audit Committee at its meeting on 24 March 2021. The Audit Committee receive periodic updates against the Internal Audit Plan.

1.3The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit function is fulfilling its statutory obligations. It is considered good practice that progress reports also include details of changes to the agreed Annual Internal Audit Plan.

2 Audit Plan Update Delivery of Audit Plan and Key Audit Findings

2.1As of 11 March 2022, 87% of the 2021/22 Audit Plan days have been delivered (the calculation excludes contingency days that have not yet been allocated).

2.2The following final reports have been issued since the last Audit Committee meeting:

Date of Assurance Number of Audit Title Issue Level Recommendations Creditors Feb 2022 Reasonable One Medium Priority

Risk Management Follow Up Mar 2022 Not Assessed None

Corporate Governance Follow Mar 2022 Not Assessed None Up

Page 1 SIAS Internal Audit Progress Report Stevenage Borough Council

2.3The table below summarises the position regarding 2021/22 projects to 11 March 2022. Appendix A provides a status update on each individual project within the 2021/22 Internal Audit Plan.

Status No. of Audits at this Stage % of Total Audits

Final Report Issued 16 52%

Draft Report Issued 5 16% In Fieldwork/Quality 6 19% Review In Planning/Terms of 0 0% Reference Issued Allocated 0 0%

Not Yet Allocated 1 3%

Cancelled 3 10% Total 31 100%

Proposed Audit Plan Changes

2.4The following Audit Plan change was agreed with the audit sponsor. The Committee is asked to approve this change:

a) IT Resilience (6 days) – a joint audit with East Herts Council intended for quarter 4 has been cancelled. After discussions with the Interim Strategic ICT Partnership Manager, SIAS was advised that the service was unable to support an audit due to prioritising operational matters at the present time.

Critical and High Priority Recommendations

2.5Members will be aware that a Final Audit Report is issued when it has been agreed (“signed off”) by management; this includes an agreement to implement the recommendations that have been made.

2.6The schedule attached at Appendix B details the most recent management updates on the status of any outstanding Critical and High priority audit recommendations.

Performance Management

2.7The 2021/22 annual performance indicators were approved at the SIAS Board meeting in March 2021.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SIAS INTERNAL AUDIT PLAN 2021/22: PROGRESS REPORTReport 567 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
TC
Teresa CallaghanChair, present
JG
John GardnerVice-Chair, apologies
MA
Myla ArcenoCommittee Member, apologies
JA
Julie Ashley-WrenCommittee Member, apologies
SB
Stephen BoothCommittee Member, apologies
GL
Graham Lawrence CCCommittee Member, present
NL
Nick LeechCommittee Member, present
MM
Maureen McKayCommittee Member, present
CP
Claire ParrisCommittee Member, present
LR
Loraine RossatiCommittee Member, present
GG
Geoffrey GibbsCo-Optee, expected
RS
Ramin ShamsSecretary, expected

All 17 on the meeting page

On this subject at Stevenage

Search all
  1. SIAS INTERNAL AUDIT PLAN 2021/22 - PROGRESS REPORTThis decision
  2. Sias annual assurance statement and internal audit report 2025/26Noted
  3. Shared internal audit service (sias) progress reportNoted
  4. Sias annual assurance statement and internal audit report 2024/25Noted
  5. Shared internal audit service (sias) internal audit plan 2025/26Noted
  6. Shared internal audit service (sias) internal audit plan 2024/25Approved

More from Stevenage Audit Committee

All decisions
MeetingDecisionOutcome
2 Jun 2026 Sias annual assurance statement and internal audit report 2025/26RESOLVED that: · The Annual Assurance Statement and Internal Audit Annual Report 2025/26 be noted. · The results of t... Noted Open
2 Jun 2026 2025/26 annual governance statement and local code of corporate governanceRESOLVED that the report be noted. Noted Open
2 Jun 2026 Annual report of the audit committeeRESOLVED that the report be noted. Noted Open
2 Jun 2026 Exclusion of public and pressRESOLVED : 1. That, under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the ... Decided Open
2 Jun 2026 Strategic risk registerRESOLVED that the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies