INTERNAL AUDIT PLAN 2022/23 - PROGRESS REPORT

Noted Finance 1 paper

Audit Committee noted this item on Tuesday 7 February 2023. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

The SIAS Client Audit Manager presented a progress report with regard to the SIAS Internal Audit Plan 2022/23 (up to 20 January 2023). In response to a Member’s question, the SIAS Client Audit Manager advised that the two additional external partners appointed to assist in the work of SIAS for 2022/23 were BDO and Mazars. He added that he was confident that SIAS would have the necessary capacity to resource the existing (2022/23) and 2023/24 Internal Audit Plan. The Committee noted the comment made by the Strategic Director (CF) that the Shared Internal Audit Service provided a greater degree of audit resilience than would be the case should each of the partner authorities operated individual internal audit services. It was
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Audit Committee

Recommendations

Members are recommended to: a) Note the Internal Audit Progress Report b) Approve the Internal Audit Plan Changes c) Note the Status of Critical and High Priority Recommendations SIAS Internal Audit Progress Update Stevenage Borough Council

Contents

1 Introduction and Background 1.1 Purpose 1.2 Background

2 Audit Plan Update 2.1 Delivery of Internal Audit Plan and Key Findings 2.4 Internal Audit Plan Changes 2.6 Critical and High Priority Recommendations 2.8 Performance Management

Appendices: A Progress against the 2022/23 Internal Audit Plan B Implementation Status of Critical and High Priority Recommendations C Internal Audit Plan Items (April 2022 to March 2023) - Indicative start dates agreed with management D Assurance Definitions / Priority Levels SIAS Internal Audit Progress Update Stevenage Borough Council

1 Introduction and Background Purpose of Report

1.1To provide Members with: a) The progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s 2022/23 Internal Audit Plan to 20 January 2023. b) The findings for the period 20 August 2022 to 20 January 2023. c) Details of any changes required to the approved Internal Audit Plan. d) The implementation status of previously agreed audit recommendations. e) An update on performance management information to 20 January 2023.

Background

1.2Internal Audit’s Annual Plan for 2022/23 was approved by the Audit Committee at its meeting on 28 March 2022. The Audit Committee receive periodic updates against the Internal Audit Plan. This is the second update report for 2022/23.

1.3The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit function is fulfilling its statutory obligations. It is considered good practice that progress reports also include details of changes to the agreed Annual Internal Audit Plan.

2 Audit Plan Update Delivery of Internal Audit Plan and Key Audit Findings

2.1As of 20 January 2023, 57% of the 2022/23 Internal Audit Plan days have been delivered (the calculation excludes contingency days that have not yet been allocated).

2.2The following final reports have been issued since the last Progress Report to the Audit Committee:

Date of Assurance Number of Audit Title Issue Level Recommendations Homelessness & Housing Advice One Medium and Sep 2022 Reasonable 2021/22 Two Low Priority Off Street Parking 2022/23 Sep 2022 Substantial None

Cemeteries 2022/23 Sep 2022 Reasonable Two Low Priority

Refuse 2022/23 Sep 2022 Substantial One Low Priority Community Safety (SADA) Three Medium and Oct 2022 Reasonable 2021/22 One Low Priority Supply Chain Interruption Four Medium Nov 2022 Reasonable 2022/23 Priority

Page 1 SIAS Internal Audit Progress Update Stevenage Borough Council

Asset Management 2022/23 Dec 2022 Substantial None One High, Three Environmental Maintenance Jan 2023 Limited Medium and Two 2022/23 Low Priority

See definitions for the above assurance levels and recommendation priorities at Appendix D.

2.3The table below summarises the position regarding delivery of the 2022/23 approved projects to 20 January 2023. Appendix A provides a status update on each individual project within the 2022/23 Internal Audit Plan.

Status No. of Audits at this Stage % of Total Audits

Final Report Issued 8 25%

Draft Report Issued 6 19% In Fieldwork/Quality 5 16% Review In Planning/Terms of 1 3% Reference Issued Allocated 11 34%

Not Yet Allocated 0 0%

Cancelled/Deferred 1 3%

Total 32 100%

Internal Audit Plan Changes

2.4Members should note at Appendix C that four audits have been moved to quarter 4 from dates earlier in 2022/23. This is due to a combination of management requests and work reallocation by SIAS.

2.5The following Audit Plan change was agreed with the audit sponsor. The Committee is asked to approve this change:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT PLAN 2022/23: PROGRESS REPORTReport 277 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
TC
Teresa CallaghanChair, apologies
JG
John GardnerVice-Chair, present
MA
Myla ArcenoCommittee Member, present
SB
Stephen BoothCommittee Member, present
AF
Alex FarquharsonCommittee Member, present
JH
Jackie HollywellCommittee Member, present
GL
Graham Lawrence CCCommittee Member, present
MM
Maureen McKayCommittee Member, apologies
LR
Loraine RossatiCommittee Member, present
TW
Tom WrenCommittee Member, present
GG
Geoffrey GibbsCo-Optee, present
LF
Luke FattorussoSecretary, expected

All 15 on the meeting page

On this subject at Stevenage

Search all
  1. INTERNAL AUDIT PLAN 2022/23 - PROGRESS REPORTThis decision
  2. Sias annual assurance statement and internal audit report 2025/26Noted
  3. Shared internal audit service (sias) progress reportNoted
  4. Shared internal audit service updateNoted
  5. Shared internal audit service - progress reportNoted
  6. Sias annual assurance statement and internal audit report 2024/25Noted

More from Stevenage Audit Committee

All decisions
MeetingDecisionOutcome
2 Jun 2026 Sias annual assurance statement and internal audit report 2025/26RESOLVED that: · The Annual Assurance Statement and Internal Audit Annual Report 2025/26 be noted. · The results of t... Noted Open
2 Jun 2026 2025/26 annual governance statement and local code of corporate governanceRESOLVED that the report be noted. Noted Open
2 Jun 2026 Annual report of the audit committeeRESOLVED that the report be noted. Noted Open
2 Jun 2026 Exclusion of public and pressRESOLVED : 1. That, under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the ... Decided Open
2 Jun 2026 Strategic risk registerRESOLVED that the report be noted. Noted Open