Stevenage Borough Council
Executive (up to May 2024), Wednesday 15 November 2023 at 2.00pm

FIRST AND SECOND QUARTER CAPITAL BUDGET MONITORING 2023/24

Decided Executive 4 papers

Executive (up to May 2024) decided this item on Wednesday 15 November 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

The Executive considered a report in respect of First and Second Quarter Capital Budget Monitoring 2023/24. The Strategic Director (CF) confirmed that £447,000 of the increased budget costs for 2023/24 related to additional third party (including grants) funding received by the Council. It was As contained in report. Other Options considered: As contained in report. As contained in report. Other Options considered: As contained in report.
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Executive (up to May 2024)

Recommendations

2.1That net budget increases of £447K be approved (2023/24 £316K, 2024/25 £131K), (see paragraph 4.4).

2.2That reprofiling of £15.016Million from 2023/24 to 2024/25 be approved (see paragraph 4.5).

2.3That Executive note the content of Appendix C ‘Treasury Management Update Quarter Ended 30th June 2023. The 2021 Prudential Code and TM Code introduce a new requirement that monitoring of the treasury management indicators should be reported quarterly (along with the other prudential indicators) as part of the authority’s general revenue and capital monitoring. Quarter 2 will be reported in the 2023/24 Mid-Year Treasury Management Review and Prudential Indicators report.

Background

3.1The 2023/24 original capital programme budget was approved by Council on 22 February 2023, General Fund £34.02Million and HRA £62.42Million.

Executive 15th November 2023 Part I Release to Press 3.2 Quarterly revisions to the budgets are agreed by Members at Executive as part of the Council’s Capital Monitoring process.

4. REASONS FOR RECOMMENDED COURSE OF ACTION AND OTHER OPTIONS

4.1The total Capital Programme, detailing all programmes with the relevant approval to spend, is detailed in Appendix A and B. It shows the revised budget position inclusive of carry forwards from 2022/23.

4.2The capital budget for the current financial year is summarised in Table One below and provides the latest position reflecting updated programme expenditure profiles as advised by programme managers.

2024/25 TOTAL Table One 2023/24 £'000 £'000 £'000 Actuals Q1 Q2 Q2 Q2 23/24 Variance Working Revised Revised Revised Pd1 - Q1 v Q2 Budget Budget Budget Budget Pd6 Capital Programme General Fund Schemes SDS £6,283 £776 £6,539 £256 £1,321 £7,860 Housing Development £2,679 £125 £2,590 (£89) £17,775 £20,366 Finance & Estates £2,207 £151 £1,725 (£482) £707 £2,432 Digital & £602 £3 £602 £0 £104 £707 Transformation Regeneration £18,501 £912 £12,532 (£5,969) £21,587 £34,118 Communities & £2,327 £1,319 £2,269 (£58) £146 £2,415 Neighbourhoods Planning & Regulatory £538 £16 £604 £67 £421 £1,025 Deferred Works £1,346 £0 £1,279 (£67) £230 £1,510 Reserve Total GF £34,483 £3,302 £28,140 (£6,343) £42,292 £70,432 HRA Schemes £0 Housing Investment £24,641 £7,400 £24,641 £0 £20,070 £44,712 Special Projects & £26 £75 £48 £22 £25 £73 Equipment Housing Development £28,799 £5,255 £20,420 (£8,379) £43,565 £63,985 Digital & £447 £14 £447 £0 £51 £498 Transformation Total HRA £53,913 £12,744 £45,556 (£8,357) £63,711 £109,267 Total Capital £88,396 £16,045 £73,696 (£14,700) £106,003 £179,699 Programme Increases £316 Slippage (£15,016)

Executive 15th November 2023 Part I Release to Press 4.3 The overall changes between the Q1 Working Budget and the Q2 Revised Budget for 2023/24 to 2026/27 are as follows:

Table Two 2023/24 2024/25 TOTAL Variance Variance Variance Q1 v Q2 Q1 v Q2 Q1 v Q2 Capital Variances £'000 £'000 £'000 General Fund Schemes SDS £256 £0 £256 Housing Development (£89) £89 £0 Finance & Estates (£482) £522 (£40) Regeneration (£5,969) £5,969 £0 Communities & (£58) £101 £43 Neighbourhoods Planning & Regulatory £67 £131 £198 Deferred Works Reserve (£67) (£45) (£112) Total GF (£6,343) £6,768 £426 HRA Schemes Special Projects & Equipment £22 £0 £22 Housing Development (£8,379) £8,379 £0 Total HRA (£8,357) £8,379 £22 Total Capital Programme (£14,700) £15,147 £447 Of which the net changes are £316 £131 £447

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cap Mon: Appendix A: General Fund Q2Appendix 322 KB Download
PDF
Cap Mon: Appendix B: HRA Q2Appendix 234 KB Download
PDF
Cap Mon: Appendix C: TM Quarter 1 2023-24Appendix 240 KB Download
PDF
FIRST AND SECOND QUARTER CAPITAL BUDGET MONITORING 2023/24Report 493 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
TE
Test externalSecretary, expected
SN
Sian NichollsSecretary, expected
AH
Abbie HamiltonSecretary, expected
RH
Richard HenryChair, present
SB
Sandra BarrCommittee Member, present
LB
Lloyd BriscoeCommittee Member, present
JH
Jackie HollywellCommittee Member, present
JL
Mrs Joan LloydCommittee Member, apologies
LR
Loraine RossatiCommittee Member, present
SS
Simon SpellerCommittee Member, present
JT
Jeannette ThomasCommittee Member, present
LF
Luke FattorussoSecretary, expected

All 15 on the meeting page

More from Stevenage Executive (up to May 2024)

All decisions
MeetingDecisionOutcome
13 Mar 2024 Apologies for absence and declarations of interestApologies for absence were submitted on behalf of Councillors Richard Henry (Chair), Sandra Barr and [name removed]. ... Decided Open
13 Mar 2024 Minutes - 7 february 2024It was RESOLVED that the Minutes of the meeting of the Executive held on 7 February 2024 be approved as a correct rec... Approved Open
13 Mar 2024 Minutes of overview & scrutiny committee and select committeesThe Portfolio Holder for Environment and Performance thanked the Chair and Members of the Environment & Economy Selec... Noted Open
13 Mar 2024 Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program... Agreed Open
13 Mar 2024 Housing consumer standards - social housing (regulation) act 2023The Executive considered a report in respect of the Social Housing (Regulation) Act 2023, which introduced wide rangi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies