Planning and Development Committee approved this item on Thursday 7 December 2023. Below is the council's own wording, with the papers it was decided on.
The Committee received a report relating to the Council’s revised Contaminated Land Inspection Strategy. It was RESOLVED that the publication of the Contaminated Land Inspection Strategy be approved for external consultation until 4 February 2024.
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
Part I – Release to Press Agenda item: ## Meeting Planning and Development Committee
Portfolio Area Environment and Performance
Date 7 December 2023
REVISED CONTAMINATED LAND INSPECTION STRATEGY
NON KEY DECISION
Authors Christine Walker-Wells | 2247
Lead Officers Maurice Clay | 2175
Contact Officer Christine Walker-Wells | 2247
1 PURPOSE 1.1 To consider the Council’s revised Contaminated Land Inspection Strategy.
2 RECOMMENDATIONS 2.1 That the Planning and Development Committee approves the publication of the attached draft contaminated land inspection strategy for external consultation until 4 February 2024.
3 BACKGROUND 3.1 Section 78B(1) of Part 2A of the Environmental Protection Act 1990 (EPA 1990) places a duty on local authorities to inspect their areas to identify contaminated land and confers regulatory powers to deliver against that duty. 3.2 Contaminated Land Statutory Guidance produced by the Department for Environment, Food and Rural Affairs in 2012 sets out how local authorities should meet these duties, including the need to have a written strategy setting out their strategic approach. The proposed Contaminated Land Inspection Strategy is intended to meet this requirement and provides a brief overview of the contaminated land regime, its aims and objectives. 3.3 Any Part 2A inspection undertaken by the Council must be at its own expense and by its nature can consist of numerous phases under the supervision of environmental consultants. 3.4 Where contaminated land assessments conclude that there are unacceptable risks, as per Statutory Guidance, the Council must ensure these are addressed, typically through the completion of remedial works. Such works could comprise excavation of contaminated ground and sending to landfill, encapsulating the ground or cleaning the soil in situ. 3.5 Where no responsible party can be identified (e.g. landowner, developer, polluter), the cost may fall to the Council. Such costs have the potential to escalate to seven figure sums. 3.6 The Contaminated Land Capital Grants programme from central Government was previously available to local authorities to bid for funds to carry out such investigations and remediation work. This funding programme was withdrawn in 2013 and has subsequently not been replaced with an alternative, leaving many authorities unable to fund such inspections. 3.7 However, it is important to note that while Part 2A gives the Council powers to proactively deal with contaminated land, in the vast majority of cases such land is assessed and dealt with through the development control system.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the press and publicRESOLVED : 1. That under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the m...
26/00531/fph - 134 shephall viewIt was agreed that the matter could be discussed outside the meeting to consider whether any further action could be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.