Resolved
That the SIAS Internal Audit progress report be noted. 2. That the changes to the Internal Audit Plan be approved. 3. That the status of Critical and High Priority Recommendations be noted.
Audit Committee noted this item on Tuesday 6 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the SIAS Internal Audit progress report be noted. 2. That the changes to the Internal Audit Plan be approved. 3. That the status of Critical and High Priority Recommendations be noted.
Members are recommended to: a) Note the Internal Audit Progress Report b) Approve the Internal Audit Plan Changes c) Note the Status of Critical and High Priority Recommendations SIAS Internal Audit Progress Update Stevenage Borough Council
Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Internal Audit Plan and Key Findings 2.4 Internal Audit Plan Changes 2.5 Critical and High Priority Recommendations 2.7 Performance Management
Appendices: A Progress against the 2023/24 Internal Audit Plan B Implementation Status of Critical and High Priority Recommendations C Internal Audit Plan Items (April 2023 to March 2024) - Indicative start dates agreed with management D Assurance Definitions / Priority Levels SIAS Internal Audit Progress Update Stevenage Borough Council
1 Introduction and Background Purpose of Report
1.1To provide Members with: a) The progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s 2023/24 Internal Audit Plan to 19 January 2024. b) The findings for the period 19 August 2023 to 19 January 2024. c) Details of any changes required to the approved Internal Audit Plan. d) The implementation status of previously agreed audit recommendations. e) An update on performance management information to 19 January 2024.
1.2Internal Audit’s Annual Plan for 2023/24 was approved by the Audit Committee at its meeting on 27 March 2023. The Audit Committee receive periodic updates against the Internal Audit Plan. This is the second update report for 2023/24.
1.3The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit function is fulfilling its statutory obligations. It is considered good practice that progress reports also include details of changes to the agreed Annual Internal Audit Plan.
2 Audit Plan Update Delivery of Internal Audit Plan and Key Audit Findings
2.1As of 19 January 2024, 64% of the 2023/24 Internal Audit Plan days have been delivered (the calculation excludes contingency days that have not yet been allocated).
2.2The following final reports have been issued since 19 August 2023:
Date of Assurance Number of Audit Title Issue Level Recommendations
Performance Indicators Sept 2023 Substantial None Four Medium IT Malicious Software (2022/23) Sept 2023 Reasonable Priority S106 Spend Arrangements Sept 2023 Substantial None
Local Land Charges Oct 2023 Substantial None
Housing Benefits Dec 2023 Substantial None
Council Tax Jan 2024 Substantial Two Low Priority
Page 1 SIAS Internal Audit Progress Update Stevenage Borough Council
See definitions for the above assurance levels and recommendation priorities at Appendix D.
2.3The table below summarises the position regarding delivery of the 2023/24 approved projects to 19 January 2024. Appendix A provides a status update on each individual project within the 2023/24 Internal Audit Plan.
Status No. of Audits at this Stage % of Total Audits
Final Report Issued 9 31%
Draft Report Issued 6 21% In Fieldwork/Quality 6 21% Review In Planning/Terms of 3 10% Reference Issued Allocated 3 10%
Not Yet Allocated 0 0%
Cancelled/Deferred 2 7%
Total 29 100%
Internal Audit Plan Changes
2.4The planned internal audit of Bed and Breakfast Accommodation has been cancelled. This is because there have been very few cases in the year to date. The unused audit days have been returned to contingency and may be reallocated to other work in progress, or any emerging issues during the remainder of the financial year.
Critical and High Priority Recommendations
2.5Members will be aware that a Final Audit Report is issued when it has been agreed (“signed off”) by management; this includes an agreement to implement the recommendations that have been made.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INTERNAL AUDIT PLAN 2023/24: PROGRESS REPORTReport | 300 KB | DownloadRead as text |
Follow Audit Committee at Stevenage and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2026 | Sias annual assurance statement and internal audit report 2025/26RESOLVED that: · The Annual Assurance Statement and Internal Audit Annual Report 2025/26 be noted. · The results of t... | Noted | Open |
| 2 Jun 2026 | 2025/26 annual governance statement and local code of corporate governanceRESOLVED that the report be noted. | Noted | Open |
| 2 Jun 2026 | Annual report of the audit committeeRESOLVED that the report be noted. | Noted | Open |
| 2 Jun 2026 | Exclusion of public and pressRESOLVED : 1. That, under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the ... | Decided | Open |
| 2 Jun 2026 | Strategic risk registerRESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.