Resolved
It was RESOLVED that the prioritisation of the Cycling and Connectivity project pot, including the progression of the Cycle Hire scheme, be approved. Annie Piper (SBC Regeneration Manager) then gave a presentation on spend performance to date on the Towns Fund Programme. She requested Board endorsement to a spend re-profiling recommendation. It was RESOLVED that the Towns Fund underspend from 2023/24 be moved to 2025/26, and it be noted that distinct pressures remained on the Enterprise Centre, SITEC and Diversification of Retail projects for 2024/25. Lucy King (SBC Assistant Programme Manager) explained how Towns Fund Project Adjustment Requests (PARs) worked. There were two routes, namely Delegated (which allowed for changes to outputs and re-allocation of project funding up to 30%) and Standard (over the above delegation, but requiring DLUHC approval within 20 working days). A PAR Form must be submitted for either route. She provided some examples to the Board. Lucy commented that a PAR Form would be required for the Enterprise Centre project, and that this required the endorsement of the Board. She reminded the Board that it had supported recommendations relating to the progression of the Enterprise Centre Scheme earlier in the meeting (See Minute 8) above. It was RESOLVED that authorisation be given for the submission of a Project Adjustment Requests (PAR) Form for the Enterprise Centre project, regarding the change in location, with full details of the PAR being circulated for comment prior to submission.