GRENFELL INQUIRY PHASE 2 UPDATE REPORT

Approved Executive 2 papers

Cabinet approved this item on Wednesday 17 September 2025. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

Cabinet received a report providing an update to Cabinet on the Council’s response to the public inquiry into the Grenfell Tower fire. The public inquiry concluded in September 2024 with the publication of the phase 2 report which provided a summary of the key updates following the Inquiry. The report presented 58 recommendations aimed at improving fire safety, emergency preparedness, and accountability across multiple sectors, including local authorities and social housing providers. The Portfolio Holder for Housing advised that the Council was doing all it could to keep residents safe, to make sure lessons were learned and that safety was always paramount. The Council had been actively working with the Hertfordshire Local Resilience Forum and other local authorities to implement the ten new emergency planning recommendations. It is REVOLVED: 1. That the action being taken by the Council to strengthen its resilience position, including working in partnership with other Hertfordshire Local Authorities and other Category One Responders to ensure that emergency and business continuity plans across the county are current and robust be acknowledged. 2. That a comprehensive review of reception centres and support for individuals that may be impacted by local incidents be approved. This review will incorporate the introduction of digital processes to improve information capture and situational awareness and will explore ways to strengthen regional coordination during emergencies. As contained in the report Other Options Considered: As contained in the report
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Cabinet

Building Safety Act – Implementation Update

No Workstream Description Deadline Status Current Position Next Action 1 Council wide briefing April-23 Ongoing Various Briefings have now been held Ensure regular updates are fed through the across the Housing & Investment Team teams as they occur.

2 Duty Holders – Define Duty Holders April-23 Completed All roles defined, including all the Fire under the BSA Safety Team roles. Included in Building Safety Policy

3 Building Safety Signage Oct-23 Ongoing Trial of new digital noticeboard now Completed – all digital notice boards are in installed at The Towers. Trial to also be place and operational. installed at Silkin Court on screens in communal areas.

4 Building Safety Case(s) Oct-23 Completed Version one of all Building Safety cases have These will be regularly updated and reviewed, been logged with the regulator. as necessary. Register all HRRBs with Building Safety Completed All sites now registered Regulator Develop Building Safety Case for each Apr-24 Completed All information now collated, apart from Fire Engineer to finalise specification, to include HRRB remedial plan for External Wall System in wider refurbishment programme, including windows programme. The above is part of the high-rise improvement plan project. Likely to be split into two parts – we are hoping to move forward on flat front entrance fire doors and cross corridor communal doors this year. Building Assessment Certificates Ongoing - Safety case submissions for Brent - Following the outcome for Brent and Court and Harrow Court have not Harrow, we have engaged Vemco yet received approval from the Consultancy to support the next phase. Building Safety Regulator (BSR). - Vemco is currently revising the safety - The remaining three buildings have cases and coordinating additional received formal notice from the strategies and surveys to support BSR, with submissions expected compliance with BSR requirements. between July 2025 and March 2026.

1 5 Develop Building Safety Policy June-23 Completed Final Draft of Policy now completed and Agreed Exec 14th June 2023. signed off.

6 Update Fire Safety Policy to include new June-23 Completed Final Draft of Policy now completed and Agreed November 2023 legislation and best practice signed off. 7 External Wall Surveys July-23 Completed All surveys completed of external wall systems 8 Implement Fire Risk Assessment April-23 Completed FRA Programme uploaded into Prioritisation Prioritisation Tool Tool, confirmed that all FRA frequencies and types are correct

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
9 Grenfell Phase 1 and 2 RecommendationsReport 218 KB DownloadRead as text
PDF
GRENFELL INQUIRY PHASE 2 UPDATE REPORTReport 232 KB Download

At this meeting

Whole meeting

Who was there

7 of 18 attended
RH
Richard HenryChair, present
JT
Jeannette ThomasVice-Chair, present
MA
Myla ArcenoCommittee Member, present
RB
Rob BroomCommittee Member, present
CD
Coleen De FreitasCommittee Member, apologies
JH
Jackie HollywellCommittee Member, present
TP
Tom PlaterCommittee Member, apologies
LR
Loraine RossatiCommittee Member, present
SS
Simon SpellerCommittee Member, present
NW
Nigel WilliamsCommittee Member, apologies
LF
Luke FattorussoSecretary, expected
LJ
Lisa JeromeSecretary, expected

All 18 on the meeting page

More from Stevenage Cabinet

All decisions
MeetingDecisionOutcome
10 Sep 2026 Apologies for absence and declarations of interestThere were no apologies for absence and no declarations of interest. Decided Open
10 Sep 2026 Minutes - cabinet 15 july 2026It was RESOLVED that the Minutes of the meeting of the Cabinet held on 15 July 2026 be approved as a correct record f... Approved Open
10 Sep 2026 Minutes of the overview and scrutiny and select committeesCabinet received a summary of the issues covered at the most recent meetings of the Overview and Scrutiny and Select ... Noted Open
10 Sep 2026 General fund medium term financial strategy update (2026/27 - 2030/31)Cabinet received a report updating the General Fund Medium Term Financial Strategy (MTFS) for 2026/27 to 2030/31, set... Noted Open
10 Sep 2026 Hra medium term financial strategy reviewCabinet received a report updating them on the Housing Revenue Account (HRA) Medium Term Financial Strategy (MTFS) fo... Noted Open