Stevenage Borough Council
Planning and Development Committee, Thursday 12 February 2026 at 6.30pm

26/00002/FP - STEVENAGE SWIMMING POOL ST GEORGES WAY

Approved Planning 1 paper

AI summaryStevenage Borough Council's planning committee approved the partial demolition of the Stevenage Swimming Centre's single storey element, paving the way for a new Leisure Centre.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor partial demolition of Swimming Centre
MoneyNot stated
What happens nextDecision notice to be issuedAssistant Director may amend conditions
Who it affectsStevenage Swimming Centre siteOn St Georges Way, near town centre

What was decided

Planning permission was granted for partial demolition of the single storey element of the Stevenage Swimming Centre, subject to conditions and with delegated authority to the Assistant Director of Planning and Regulation to amend conditions in consultation with the Committee Chair. Report P82

The development must begin within three years of the permission date and must follow the approved plans and the Demolition Plan of Works Method Statement dated 10.11.25. Report P84, P85, P86

Why

The principle of demolishing the swimming centre was already established by the earlier resolution to grant permission for a new Leisure Centre under application 25/00424/FPM, and permitted development rights do not allow partial demolition. Report P43, P44, P45, P46

Environmental Health raised no objection subject to a condition securing the method statement, with mitigation measures including dust suppression, acoustic screens and working hours of 8:00 to 17:00 Monday to Friday. Report P17, 5.1, P56, P57

Officers concluded the partial demolition would have a neutral impact on the nearby Town Centre Conservation Area, the Grade II listed Church of St Andrew and St George, and the William Mitchell wall mural, causing no harm to heritage assets. Report P72, P73, P74

What happens next

A decision notice will be issued, with delegated authority for the Assistant Director of Planning and Regulation to amend or add conditions in consultation with the Committee Chair. Report P82

Demolition works must follow the Method Statement and the three year time limit applies from the date of the permission. Report P85, P86

Options considered

  • Chosen: Grant planning permission for partial demolition. Principle already established, no harm to heritage, environmental impacts can be mitigated by conditions Report P82, P81, P72

Implications

  • Legal: Permission granted subject to conditions under the Town and Country Planning Act 1990, with biodiversity net gain considered below the de minimis threshold. Report P85, P99
  • Equalities: Officers considered the partial demolition would not affect accessibility or use of the Swimming Centre and would have no material impact on protected characteristic groups. Report P80
  • Other: The development enables earlier implementation of the approved new Leisure Centre on the site, ahead of the issue of the decision for application 25/00424/FPM. Report 3.2, P47

Who and where

  • Residents of Brent Court and Harrow Court, the nearest residential blocks, at least 90m from the site Report P55
  • Users and operators of the Bowes Lyon Centre to the south of the site Report 1.1
  • The applicant, Stevenage Borough Council Report P3

Timeline

  • 10.11.25: Demolition Plan of Works Method Statement dated Report P56, P86
  • 5 January 2026: Application validated Report P3
  • 12 February 2026: Planning and Development Committee considered the application Report P2

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge on new development to fund local infrastructure
  • Biodiversity Net Gain: A requirement for developments to leave biodiversity in a better state than before
  • De Minimis: Below the threshold at which a particular requirement, here biodiversity net gain, applies
  • Method Statement: A document setting out how demolition or construction works will be carried out and what measures will reduce impacts
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item3

Resolved

RESOLVED that planning permission be GRANTED subject to the following conditions, and Authority would be given to the Assistant Director of Planning and Regulation in consultation with the Chair of Planning Committee, to amend or add to the suggested draft conditions set out in this report, prior to the decision notice being issued, where such amendments or additions would be legally sound and most effectively deliver the development that the Planning Committee has resolved to approve. These suggested conditions are as follows: Conditions The development hereby permitted shall be carried out in accordance with the following approved plans: SSLH-FBA-01-ZZ-D-A-0109-P02; SSLH-FBA-01-ZZ-D-A-0108-P02; SSLH-FBA-01-ZZD-A-0184-P02 The development hereby permitted shall be begun before the expiration of three years from the date of this permission. The development shall be carried out in accordance with the measures as contained in 'Demolition Plan of Works - Method Statement' (dated 10.11.25) for the duration of the demolition. INFORMATIVES Building Regulations To obtain advice regarding current Building Regulations please contact Hertfordshire Building Control Ltd. by emailing us at [email removed] or phoning us on 01438 879990. To make a building regulations application please apply through our website portal at https://www.hertfordshirebc.co.uk/contact-us/ payment can be made online or by phoning the above number after the application has been uploaded. Please phone Hertfordshire Building Control for fees guidance on 01438 879990. Hertfordshire Building Control can also be contacted by post at Hertfordshire Building Control Ltd, Campus East, Welwyn Garden City, Hertfordshire, AL8 6AE. Once a building regulations application has been deposited with relevant drawings and fee building work may commence. You will be advised in their acknowledgement letter of the work stages we need to inspect but in most instances these are usually: Excavation for foundations Damp proof course Concrete oversite Insulation Drains (when laid or tested) Floor and Roof construction Work relating to fire safety Work affecting access and facilities for disabled people Completion Please phone Hertfordshire Building Control on 01438 879990 before 10.00am to ensure a same day inspection (Mon - Fri). 2. Biodiversity Net Gain Applications where Biodiversity Net Gain is not required as development is considered De Minimis The effect of ... view the full minutes text for item 3.
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Planning and Development Committee

Part I – Release to Press

The Meeting: Planning and Development Agenda Item: Committee Date: 12 February 2026 Author: Rebecca Elliott Lead Officer: Alex Robinson Contact Officer: Rebecca Elliott Application Nos: 26/00002/FP Location: Stevenage Swimming Centre St. Georges Way Stevenage. Proposal: Partial demolition of existing Swimming Centre.

Drawing Nos. SSLH-FBA-01-ZZ-D-A-0109-P02; SSLH-FBA-01-ZZ-D-A-0108-P02; SSLH-FBA-01-ZZ-D-A-0184-P02;; Applicant: Stevenage Borough Council Date Valid: 5 January 2026 Recommendation: GRANT PLANNING PERMISSION

Plan for information purposes only

1. SITE DESCRIPTION

1.1The proposal site is the existing Stevenage Swimming Centre and surrounding land. The site is located on the eastern side of St Georges Way and is bounded to the north by Fairlands Way. To the east is the Town Centre Gardens and residential flatted blocks which overlook the gardens. The Bowes Lyon Centre is sited to the south of the site, including an existing footway connecting St Georges Way to the Town Gardens. Beyond St Georges Way is the Town Centre, with the approved life sciences quarter to be immediately to the west on the site of the existing The Forum shopping area.

1.2The site is accessed by vehicles coming off St Georges Way to the south of the building, entering one of the two car parks serving the centre before heading north around the eastern side of the building to the second car park to the north. The site is exited to the north on to Fairlands Way. The existing building has a larger block located centrally, with single storey elements wrapping around the front and northern side of the building.

2. RELEVANT PLANNING HISTORY 2.1 There have been various permissions granted in the past for advertisements, but these are not relevant to this planning application.

2.2Full planning application reference 99/00492/FP for the refurbishment, recladding, refacing and entrance extension was approved on 28.02.2000.

2.3Planning permission reference 06/00181/FP for access road alteration, refurbishment of north car park and construction of new south car park including coach drop off point and canopy assembly point was approved on 25.06.2006.

2.4Planning permission reference 09/00397/FP for retention of combined heat and power unit adjacent to the north elevation of the building was approved on 13.01.2010.

2.5Planning permission reference 25/00424/FPM for the demolition of existing Swimming Centre and erection of new sports and leisure centre with associated parking, landscaping and access, has a resolution to grant planning permission as determined by the Committee subject to the signing of a S106 agreement and removal of outstanding LLFA objection.

2.6Lawful Development Certificate (proposed) reference 25/00700/CLPD for the construction of a replacement substation to the south of Stevenage Swimming Centre was issued on 22.10.2025.

3. THE CURRENT APPLICATION 3.1 The proposed development seeks full planning permission for the partial demolition of the single storey element of the existing Swimming Centre. The application follows the assessment of and approval in principle of the demolition of the Swimming Centre and erection of a new Leisure Centre.

3.2The application has been submitted to enable the partial demolition of the building ahead of the issuing of the decision for the new Leisure Centre (Planning reference: 25/00424/FPM). This will ensure works relating to the wider redevelopment of the site can be implemented more seamlessly and timely given the timeframes and parameters of this strategic project.

4. PUBLIC REPRESENTATIONS 4.1 Following notification of the application via letter to the Bowes Lyon Centre, and the posting of a site notice, no comments have been received at the time of drafting this report.

5. CONSULTATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
26/00002/FP: STEVENAGE SWIMMING POOL ST GEORGES WAYReport 300 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 25 attended
CP
Claire ParrisChair, present
CV
Carolina VeresVice-Chair, present
JA
Julie Ashley-WrenCommittee Member, present
SB
Stephen BoothCommittee Member, present
RB
Robert BoyleCommittee Member, present
KC
Kamal ChoudhuryCommittee Member, apologies
FC
Forhad ChowdhuryCommittee Member, apologies
PC
Peter ClarkCommittee Member, present
CD
Coleen De FreitasCommittee Member, present
AE
Akin ElekolusiCommittee Member, apologies
LG
Lynda GuyCommittee Member, present
RH
Rob HenryCommittee Member, present

All 25 on the meeting page

More from Stevenage Planning and Development Committee

All decisions
MeetingDecisionOutcome
8 Oct 2026 26/00427/fpm - lister hospital, coreys mill laneRESOLVED that planning permission be GRANTED subject to the applicant having first entered into a Unilateral Undertak... Decided Open
8 Oct 2026 Information report - delegated decisionsRESOLVED that the Information Report – Delegated Decisions be noted. Noted Open
8 Oct 2026 Information report - appeals/called in applicationsRESOLVED that the Information Report – Appeals / Called In Decisions be noted. Noted Open
8 Oct 2026 Exclusion of the press and publicRESOLVED : 1. That under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the m... Decided Open