25/00854/FPM - 40-60 QUEENSWAY TOWN CENTRE STEVENAGE

Decided Planning 1 paper

AI summaryStevenage Planning and Development Committee grants permission for change of use and two-storey upward extension at 40-60 Queensway to create 26 flats, with no affordable housing on viability grounds and a Section 106 review mechanism.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to conditions, delegated to Director of Planning
Money£50,695 + £41,404 + £8,034 requestedSchool and ambulance contributions sought
What happens nextSection 106 legal agreementIncluding late-stage viability review mechanism
Who it affects40-60 Queensway Town CentrePart change of use, two-storey extension, 26 flats

What was decided

Planning permission granted for change of use of part of ground floor retail at 46 Queensway and second floor offices at 40-56 Queensway from Use Class E to Use Class C3, a two-storey upward extension, new bin store and rear access to provide 26 flats. Report P9, P49

Delegated authority given to the Director of Planning and Regulation in consultation with the Chair of the Planning and Development Committee to amend or add to conditions.

Why

The site is previously developed land in a highly accessible town centre location and the proposal makes a meaningful contribution to the Borough's housing requirement, consistent with Policies SP7 and HO5. Report P97, P98, P108

Officers accepted the independently reviewed financial viability evidence showing the scheme cannot support affordable housing, with a Section 106 review mechanism providing a safeguard against improved viability. Report P124, P125, P126, P127

The less than substantial harm identified to the Town Square Conservation Area and nearby listed and locally listed buildings was weighed against the public benefits of providing 26 homes and the council concluded the scheme is acceptable. Report P164, P165, P153, P154

What happens next

A Section 106 legal agreement will be completed to secure the late-stage viability review mechanism and any agreed contributions. Report P126, P127

Conditions will be imposed covering cycle and bin storage prior to occupation, construction management plan, flood emergency plan, fire hydrants, noise mitigation, mechanical ventilation and contaminated land remediation if needed. Report P61, 5.8, P180, P195, P202

Outstanding conditions and contributions from consultees (including school and ambulance requests) will be resolved through the S106 and condition process. Report 5.2, 5.3, P126

The money

  • £50,695 Herts County Council request towards new primary school Report 5.2
  • £41,404 Herts County Council request towards new secondary school at former Barnwell East site Report 5.2
  • £8,034 East of England Ambulance Service request for EV charging at Stevenage Ambulance Hub Report 5.3
  • -£404,762.00 Applicant's financial viability appraisal negative residual land value on 100% private basis Report P124
  • -£135,753 Aspinall Verdi independent review negative residual land value Report P125
  • £500 Defibrillator annual maintenance cost for 10 years noted by East of England Ambulance Service Report 5.3

Options considered

  • Chosen: Grant planning permission (officer recommendation). Scheme acceptable in principle, design, heritage balance, viability, flood risk resolved; cycle parking deficit and lack of affordable housing offset by other considerations and S106 review mechanism Report P14, P126, P165, P199
  • Rejected: Refuse planning permission. Not pursued; officer assessment found the scheme acceptable subject to conditions and S106 Report P14

Implications

  • Financial: Zero affordable housing on viability grounds, with a late-stage review mechanism secured via Section 106 to capture any uplift in viability. Report P122, P123, P126, P127
  • Legal: Section 106 legal agreement required; statutory duties under sections 66 and 72 of the Planning (Listed Buildings and Conservation Areas) Act 1990 considered. Report P150, P151, P126
  • Equalities: 100% of dwellings to be built to M4(2) accessible and adaptable standard; no M4(3) wheelchair units required as policy is applied flexibly. Report P129, P130
  • Climate: Air quality impact assessed as negligible; green roofs proposed; Herts Police Crime Prevention Design advisor recommended Secured by Design engagement on carbon reduction. Report P140, P208, 5.5
  • Risk: Less than substantial harm identified at higher end of scale to Town Square Conservation Area and lower end to nearby listed and locally listed buildings, weighed against public benefits. Report P164, P165
  • Risk: Initial Lead Local Flood Authority objection on safe access and egress in flood event was withdrawn after further information; flood emergency plan condition recommended. Report 5.7, P61

Who and where

  • Future residents of 26 new flats (23 one-bedroom and 3 two-bedroom) Report P100, P49
  • Existing retail occupiers of 40-60 Queensway ground floor units Report P111, P113, P115
  • Residents of Park Place and other neighbouring properties Report P169, P170
  • Hertfordshire County Council education and highways authorities Report 5.2, P56
  • East of England Ambulance Service and NHS Report 5.3, 5.13

Timeline

  • 18 December 2024: Prior approval granted for conversion of part of offices to 18 one-bedroom flats under 24/00786/CPA Report 2.2
  • 31 January 2025: Permission granted for 71 residential units at 80 Queensway and Forum Chambers under 23/00502/FPM Report 2.20
  • 27 November 2025: Application validated Report P13
  • 22 July 2026: Stevenage adopted revised Community Infrastructure Levy Charging Schedule (SCIL2) Report P91
  • 4 August 2026: Planning and Development Committee resolved to grant planning permission subject to conditions and S106 Report P3

Plain English for the jargon

  • Use Class E: Commercial, business and service uses including shops, offices and certain leisure uses
  • Use Class C3: Dwellinghouses used as a main residence by individuals or families
  • SCIL2: Stevenage Community Infrastructure Levy revised Charging Schedule adopted 22 July 2026
  • M4(2) and M4(3): Building regulation optional accessibility and adaptability standards: M4(2) accessible and adaptable dwellings, M4(3) wheelchair user dwellings
  • Section 106: Legal agreement under the Town and Country Planning Act 1990 used to secure planning obligations including affordable housing review mechanisms
  • FVA: Financial Viability Appraisal
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

RESOLVED that planning permission be GRANTED subject to the conditions set out below and delegated authority be given to the Director of Planning and Regulation in consultation with the Chair of the Planning and Development Committee, to amend or add to the conditions subject to which the permission would be granted, where such amendments or additions would satisfy the relevant national policy tests ... view the full minutes text for item 5.
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Planning and Development Committee

Part 1 – Release to Press

Meeting: Planning and Development Agenda Item: Committee

Date: 4 August 2026

Author: Linda Sparrow

Lead Officer: Alex Robinson

Contact Officer: Linda Sparrow

Application No : 25/00854/FPM

Location : 40 - 60 Queensway Town Centre

Proposal : Change of use of part of ground floor retail unit (46 Queensway), second floor office units (40-56 Queensway) from Use Class (E) to residential Use Class (C3) to provide 26 flats. Extension of two additional storeys and creation of new bin store and rear access with associated external alterations.

Drawing Nos.: 1294.11.02.001; 1294.11.02.002; 1294.11.01.030; 1291.11.02.010; 1291.11.02.011; 1291.11.02.012; 1291.11.02.013; 1291.11.02.100; 1291.11.02.101; 1291.11.02.102; 1291.11.02.103; 1291.11.02.103; 1291.11.02.104; 1291.11.02.105; 1291.11.02.200; 1291.11.02.201; 1291.11.02.202; 1294.11.02.020; 1294.11.02.021; 1294.11.02.022;

Applicant : ABC Commercial Stevenage 2 Ltd

Agent: Bidwells LLP

Date Valid: 27 November 2025

Recommendation: GRANT PLANNING PERMISSION

DC88 1. SITE DESCRIPTION 1.1 The application site comprises a three-storey row of shops and offices on the western side of Queensway, to the south of the entrance to Westgate One shopping precinct. The ground floor is mostly made up of shops, whilst the upper floors comprise incidental storage space for the shop units and separate offices. Access is pedestrian only and can be taken from various points on Queensway as well as from the rear service yard on Westgate.

1.2The site is located within the Town Centre Shopping Area. In the adopted Local Plan (2019), policy TC8 states that at ground floor, units 40 to 48 are primary retail frontages and units 50 to 60 are secondary frontages. It should be noted that through the Local Plan Partial Review, primary and secondary retail frontages have been deleted.

1.3Units 40 to 44 are within the Town Centre Conservation Area.

2. RELEVANT PLANNING HISORY 2.1 12/00441/AD Installation of 1no internally illuminated fascia sign and 1no internally illuminated projection sign. 02.11.2012 ADGRAN

2.224/00786/CPA Prior approval for the conversion of part ground, first and second floors of office building (Use Class (E) to 18no. one bedroom flats (Use class (C3)) 18.12.2024 PAGRAN

2.302/00566/AD 1 internally illuminated fascia sign and 1 internally illuminated under canopy sign 26.02.2003 ADGRAN

2.400/00165/FP New Shopfront 16.05.2000 PER

2.501/00115/AD Internally illuminated fascia sign 01.05.2001 ADGRAN

2.699/00401/FP Two Storey Rear Extension 26.11.1999 PER

2.712/00419/AD Installation of 1 x internally illuminated fascia sign and installation of 1 x internally illuminated projection sign. 23.11.2012 SPLIT

2.800/00199/AD Illuminated Fascia Sign 26.05.2000 ADGRAN

2.900/00200/FP New Shopfront 26.05.2000 PER

2.1005/00429/FP Steel security shutter 13.12.2005 WDN

2.1111/00563/AD Retention of 1no. internally illuminated fascia sign and 1no. internally illuminated projecting sign 05.12.2011 ADGRAN

2.1211/00246/AD 1no. internally illuminated fascia sign and 1no. internally illuminated projecting sign 14.06.2011 ADGRAN 2.13 11/00247/FP Replacement shopfront 14.06.2011 PER

DC88 2.14 15/00470/AD Retrospective erection of 1 no. internally illuminated fascia sign and 2 no. internally illuminated hanging signs 05.10.2015 ADGRAN

2.1504/00427/AD 1 no illuminated facia sign and 1 no illuminated box sign 08.12.2004 ADGRAN

2.1606/00655/AD 3 x internally illuminated fascia signs and 1 x internally illuminated hanging sign 17.01.2007 ADGRAN

2.1706/00656/FP New shopfront and shutters 17.01.2007 PER

2.1819/00644/FP Continued use of the first floor as Use Class D2 (Leisure) with ancillary Use Class A1 (Retail) 11.12.2019 PER

2.1917/00311/FP Temporary Change of Use from Class B1 (Training Centre) to Mixed B1/D1 Use (Training Centre/Hearcare Audiologist) for a period of 18 months. 22.06.2017 PER

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/00854/FPM: 40-60 QUEENSWAY TOWN CENTRE STEVENAGEReport 619 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 23 attended
CP
Claire ParrisChair, present
NW
Nigel WilliamsVice-Chair, present
JA
Julie Ashley-WrenCommittee Member, present
FC
Forhad ChowdhuryCommittee Member, present
PC
Peter ClarkCommittee Member, present
LG
Lynda GuyCommittee Member, present
RH
Rob HenryCommittee Member, present
EP
Ellie PlaterCommittee Member, present
DB
Doug Bainbridge CCCommittee Member, present
JH
Jody HanafinCommittee Member, present
JH
Jackie HollywellCommittee Member, present
PW
Peter WilkinsCommittee Member, present

All 23 on the meeting page

On this subject at Stevenage

Search all
  1. 25/00854/FPM - 40-60 QUEENSWAY TOWN CENTRE STEVENAGEThis decision
  2. 23/00502/fpm - 58-90 queensway and forum chambers, stevenage, sg1 1eeDecided
  3. 19/00284/fpm - 85 - 103 queensway, stevenageApproved
  4. 18/00268/fpm - 85-103 queensway, stevenageDecided
  5. 18/00279/fpm - 85-103 queensway, stevenageDecided

More from Stevenage Planning and Development Committee

All decisions
MeetingDecisionOutcome
8 Oct 2026 26/00427/fpm - lister hospital, coreys mill laneRESOLVED that planning permission be GRANTED subject to the applicant having first entered into a Unilateral Undertak... Decided Open
8 Oct 2026 Information report - delegated decisionsRESOLVED that the Information Report – Delegated Decisions be noted. Noted Open
8 Oct 2026 Information report - appeals/called in applicationsRESOLVED that the Information Report – Appeals / Called In Decisions be noted. Noted Open
8 Oct 2026 Exclusion of the press and publicRESOLVED : 1. That under Section 100(A) of the Local Government Act 1972, the press and public be excluded from the m... Decided Open
8 Sep 2026 26/00531/fph - 134 shephall viewIt was agreed that the matter could be discussed outside the meeting to consider whether any further action could be ... Agreed Open