ANNUAL TREASURY MANAGEMENT REVIEW 2025/26 AND PRUDENTIAL INDICATORS
ApprovedExecutive1 paper
AI summaryCabinet received Stevenage Borough Council's 2025/26 Treasury Management Review, noting compliance with prudential indicators and recommending the report to Council for approval. Investments returned an average 4.35%, generating £2.6m interest.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to Audit Committee comments
Money£2.6m interest earned on investmentsAverage 4.35% return on £51.9m treasury portfolio
What happens nextReferral to Council for approvalAfter Audit Committee consideration
Who it affectsCouncil treasury and capital positionBorrowing, investments, prudential indicators
What was decided
Cabinet received the 2025/26 Annual Treasury Management Review, which reported that the treasury management outturn was sound with compliance, liquidity and risk control maintained while generating strong returns on balances held for approved future use. Report P14, P26
The 2025/26 Annual Treasury Management Review is recommended to Council for approval, subject to any comments made by the Audit Committee. Report 2.1, P2
Officers confirmed that borrowing was only undertaken for a capital purpose and that the statutory authorised borrowing limit was not breached during the year. Report P26, 4.4
Why
The Council is required by regulations under the Local Government Act 2003 and by the CIPFA Treasury Management and Prudential Codes to produce an annual review of treasury activity and the actual prudential and treasury indicators. Report 3.1, P8, P10
The report records compliance with the Treasury Management Strategy, Treasury Management Practices, and the requirement to operate a balanced budget, with cash being available when needed. Report P14, P15, P26, P120
Member training on treasury management was provided on 22 January 2026 to support the scrutiny role set out in the regulatory framework. Report P13
What happens next
The Audit Committee is asked to consider the review and then refer it to Council, where it will be considered for approval alongside any Cabinet comments. Report 2.2, P4, 2.3, P6
Officers will ensure that any changes to the Prudential and Treasury Management codes from 2026/27 are reflected in treasury operations and reporting. Report P122
Capital receipts expected in 2026/27 and 2027/28 are expected to significantly reduce the General Fund's MRP funding requirement, which will be reflected in future reporting.
The money
£53,041K Total capital expenditure actual 2025/26 Report P18
£51,865K Treasury investments under 1 year at 31 March 2026 Report P23, P63
£815K Minimum Revenue Provision charged to the General Fund in 2025/26 Report P39, P42
£12 Million New PWLB loan taken 26 January 2026 to 24 January 2031 at 4.31% to refinance HRA internal borrowing Report 4.11, P91, P93
£8.5 Million Interest paid on PWLB borrowing by the Housing Revenue Account during 2025/26 Report 4.11
£40K Interest paid on PWLB borrowing by the General Fund during 2025/26 Report 4.11
£2.6 Million Interest earned on treasury investments to 31 March 2026 (GF £1.1m, HRA £1.5m) against a working budget of £2.56m Report 4.13, P111
4.35% Average interest rate earned on average £60m of funds available for investment during 2025/26 Report 4.13, P111
4.46% Council's weighted average rate of return on investments against a model range of 3.93% to 4.28% Report 4.13, P111
Options considered
Chosen: Recommend the 2025/26 Annual Treasury Management Review to Council for approval (subject to Audit Committee comments). Required by the CIPFA Code and statutory framework; the outturn was sound and compliant Report 2.1, P2
Chosen: Maintain an internal borrowing position with limited external borrowing. Near-term investment rates were equal to or higher than long-term borrowing costs, and long-term rates are expected to fall; the Council sought to avoid long-term borrowing at elevated levels Report P91
Chosen: Take £12m of PWLB borrowing to refinance HRA internal borrowing. To keep the cashflow position resilient and avoid taking large amounts of borrowing at potentially higher future rates Report 4.11, P91, P93
Rejected: Invest surplus cash with a wider range of counterparty types beyond banks, building societies, money market funds and other local authorities. In line with the approved strategy, only conventional cash investments were used Report 4.13, P111
Implications
Financial: Investment income of £2.6m slightly exceeded the £2.56m working budget; performance of the investment portfolio exceeded the upper return range of the MUFG model benchmark for 20 local authorities. Report 4.13, P111
Financial: General Fund financing cost ratio moved from (9)% in 2024/25 to (2)% in 2025/26, reflecting increased MRP costs on unfunded capital expenditure; capital receipts expected in 2026/27 and 2027/28 are expected to reduce this requirement.
Financial: Movement in the General Fund CFR of £7m mainly reflects £7.5m of additional lending to Swingate LLP as part of the joint venture with Mace, partly offset by £814k of MRP applied to reduce borrowing. Report P46
Risk: There is a risk that the Council may need to take borrowing at higher rates than budgeted if cash balances fall, which would increase revenue costs; the policy of internal borrowing is kept under ongoing review. Report P123
Risk: There is a risk to the HRA Business Plan's ability to fund its approved 30-year spending plans if interest rates remain high; this will be included in the HRA MTFS forecast for 2026/27. Report P123
Legal: The report is intended to ensure compliance with relevant legislation and best practice, including the Local Government Act 2003, MHCLG Guidance, and the CIPFA Codes; the authorised borrowing limit was not breached. Report P121, 4.4
Equalities: Officers assessed that the Treasury Management Policy has no potential to discriminate on grounds of age, disability, gender, ethnicity, sexual orientation, religion or financial exclusion; no detailed Equality Impact Assessment was undertaken. Report 5.4, P125, P126
Other: There are no specific climate change implications arising from this report. Report 5.5, P128
Who and where
Stevenage Borough Council as a whole, through its General Fund and Housing Revenue Account Report P18, P19, P20, P21, P22
Council taxpayers and rent payers, who fund the net revenue stream used in the financing cost ratio Report P59
Counterparties used for investments, including banks, building societies, money market funds and other local authorities Report P69, P70, P132
Subsidiaries and joint ventures receiving loans or equity from the Council, including Marshgate Ltd, Swingate Developments LLP and Hertfordshire Building Control Ltd Report P76
Timeline
26 February 2025: Treasury Management Strategy 2025/26 and MRP Policy approved by Council Report P9, P79, P128
17 December 2025: Mid-year Treasury Management Review and Prudential Indicators reported to Council Report P9, P128
22 January 2026: Member training on treasury management undertaken to support scrutiny role Report P13
26 January 2026: New £12m PWLB loan taken at 4.31% to 24 January 2031 to refinance HRA internal borrowing Report 4.11, P93
25 March 2026: Latest interest rate forecast updated; market expecting Bank Rate to increase to 4% or 4.25% Report P91
10 September 2026: Cabinet received the 2025/26 Annual Treasury Management Review and resolved to recommend it to Council subject to Audit Committee comments Report 2.1, P2
Plain English for the jargon
Treasury Management: The management of the Council's cash flows, borrowing and investments to support its services.
Prudential Indicators: Measures set under the Prudential Code that show whether the Council's borrowing, capital expenditure and financing are affordable, prudent and sustainable.
Capital Financing Requirement (CFR): The Council's underlying need to borrow to fund capital expenditure, including internal and external borrowing.
Minimum Revenue Provision (MRP): The annual revenue charge the Council is required to make to reduce the General Fund element of the Capital Financing Requirement.
Public Works Loan Board (PWLB): A government body that lends money to local authorities for capital projects.
Local Enterprise Partnership (LEP): A body bringing together local authorities and businesses; here it relates to a regeneration loan.
WARoR: Weighted Average Rate of Return on investments, used to benchmark investment performance.
Authorised Limit: The statutory affordable borrowing limit set under Section 3 of the Local Government Act 2003, which the Council must not exceed.
Operational Boundary: The expected borrowing position of the Council during the year, set within the authorised limit.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
Cabinet received the Annual Treasury Management Report for 2025/26 including the actual 2025/26 prudential and treasury indicators. The Portfolio Holder for Resources and Performance advised that the Treasury Management outturn was sound, having maintained compliance, liquidity and effective risk control while generating strong returns on balances held for approved future use. He advised that, subject to comments from Cabinet and the Audit Committee, the review would then be referred to Council for approval. It was RESOLVED that subject to any comments made by the Audit Committee, the 2025/26 Annual Treasury Management Review be recommended to Council for approval.
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
That, subject to any comments made by the Audit Committee to the Council, the 2025/26 Annual Treasury Management Review be recommended to Council for approval.
2.2Audit Committee
That, subject to any comments by the Cabinet to the Council, the 2025/26 Annual Treasury Management Review be recommended to Council for approval.
2.3Council
That, subject to any comments from the Audit Committee and the Cabinet, the 2025/26 Annual Treasury Management Review be approved. 3 BACKGROUND
3.1Regulatory Requirement
3.1.1 The Council is required by regulations issued under the Local Government Act 2003 to produce an annual treasury management review of activities and the actual prudential and treasury indicators for 2025/26. This report meets the requirements of both the CIPFA Code of Practice on Treasury Management, (the Code), and the CIPFA Prudential Code for Capital Finance in Local Authorities, (the Prudential Code).
3.1.2 During 2025/26 the minimum reporting requirements were that the Council should receive the following reports: • an annual treasury strategy in advance of the year (Council 26 February 2025) • a mid-year treasury update report (Council 17 December 2025) • an annual review following the end of the year describing the activity compared to the strategy (this report).
3.1.3 In December 2017, CIPFA revised the Code to require, all local authorities to report on: • a high-level overview of how capital expenditure, capital financing and treasury management activity contribute to the provision of services; • an overview of how the associated risk is managed; and • the implications for future financial sustainability. These elements are covered in the annual Capital Strategy reported to Council in February each year.
3.1.4 The regulatory environment places responsibility on Members for the review and scrutiny of treasury management policy and activities. This report is, therefore, important in that respect, as it provides details of the outturn position for treasury activities and highlights compliance with the Council’s policies previously approved by Members.
3.1.5 This report summarises: • Capital activity during the year; • Impact of this activity on the Council’s underlying indebtedness (the Capital Financing Requirement); • The actual prudential and treasury indicators; • Overall treasury position identifying how the Council has borrowed in relation to this indebtedness, and the impact on investment balances; • Summary of interest rate movements in the year; • Detailed debt activity; and • Detailed investment activity.
3.1.6 Officers confirm that they have complied with the requirement under the Code to give prior scrutiny to all of the above treasury management reports by the Audit Committee and the Cabinet before they were reported to the Council. 2 3.1.7 Member training on treasury management issues was undertaken during the year on 22 January 2026 in order to support members’ scrutiny role.
Executive summary
3.2.1 During 2025/26, the Council complied with its legislative and regulatory requirements as outlined in paragraph 3.1.1 above. These requirements include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.