AI summaryStockport Cabinet approves entering a funding agreement with GMCA, subject to Bee Network Committee approval, to deliver a temporary bus depot on Heaton Lane and Lundy sites so Stockport 8 Phase 1 with 435 homes can start on site in 2026/27.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to TfGM securing BNC approval
MoneyCosts in Confidential Appendix 2Construction funded via GMCA CRSTS programme
What happens nextDetailed design by May 2026Site works start August 2026 (subject to approvals)
Who it affectsStagecoach, TfGM, Stockport 8 LLPPlus future residents of 435 Phase 1 homes
What was decided
Approve the Council entering into a funding agreement with GMCA to deliver the temporary bus depot, subject to TfGM securing approval from the Bee Network Committee.
Delegate authority to the Deputy Chief Executive and the Director of Finance, in consultation with the Cabinet Member for Economy, Regeneration and Skills, to finalise the legal agreements and ancillary documentation.
Delegate authority to the Assistant Director of Governance to take all steps necessary to implement the resolutions.
Why
Relocating the Daw Bank bus depot is needed to unlock Stockport 8 Phase 1, which will deliver 435 new homes starting in 2026/27, with a total masterplan of 1300 new homes across three phases. Report 2.1, 2.5, 2.6
A permanent electrified bus depot will not be available until 2029/30, so a temporary facility is required to avoid disruption to bus services while Stockport 8 Phase 1 starts on site. Report 2.6, 2.13
Substantial progress has already been made, including the appointment of English Cities Fund as joint venture partner, selection of a preferred contractor in January 2025, and £41.3m of Good Growth funding from GMCA secured in November 2025. Report 2.4, 2.5, 7.1
What happens next
TfGM to seek Bee Network Committee approval of the project budget, after which the Council will enter a development agreement with the Stockport 8 LLP to deliver the works. Report 2.17, 7.4
Detailed design by the appointed building contractor is due to complete in May 2026, enabling a fixed price contract sum to be agreed. Report 2.15
Commencement of depot works on site is programmed for August 2026, subject to planning permission, highways approval and vacation of the Lundy site by TLC Facilities Management.
The money
£41.3m Good Growth funding secured from GMCA in November 2025 to support Stockport 8 delivery costs Report 2.5, 7.1
£350,000 p.a. Current rent paid by Stagecoach at Daw Bank, which will cease post vacant possession, increasing the net cost of the Investment and Development account Report 3.3
Options considered
Chosen: Deliver the temporary bus depot now to enable Stockport 8 Phase 1 to start on site in 2026/27. Avoids delay to Phase 1 housing delivery and protects the Council's joint venture with English Cities Fund and the repayment profile of investment to date Report 7.2, 7.4
Rejected: Delay Stockport 8 Phase 1 until a permanent depot is secured by TfGM in 2029/30. Would impact the deliverability of the existing joint venture with English Cities Fund and the repayment profile of the Council's investment to date
Implications
Financial: Construction costs are funded by TfGM/GMCA so do not directly burden the Council, but any scheme overspend would be borne by the Council and rent of £350,000 p.a. from Stagecoach will cease after vacant possession. Report 3.1, 3.3
Financial: Officers will work with GMCA to support timely drawdown of funding to mitigate short-term cashflow and cost risk until the funding is reclaimed. Report 3.2
Legal: The GMCA funding may meet the definition of a subsidy under the Subsidy Control Act 2022; further review will be undertaken as the scheme is finalised. Report 4.1
Legal: The proposed lease to TfGM for a term of less than seven years is treated as a short tenancy under Section 123 of the Local Government Act 1972. Report 4.2
Risk: Detailed cost risks are set out in Confidential Appendix 2; the Council is mitigating by ensuring a robust cost model with sufficient contingency. Report 3.1, 3.5
Other: There will be no provision for EV charging at the temporary bus depots; electrification is to be addressed on the permanent TfGM depot in 2030. Report 2.11
Other: There will be no changes to bus services operating in Stockport as a result of the transition to the temporary sites. Report 2.13
Who and where
Stagecoach, as the current bus operator at Daw Bank, to be granted a sub-lease from TfGM at the temporary sites Report 2.8, P26
Transport for Greater Manchester (TfGM), to take a head lease of the temporary sites and secure Bee Network Committee approval of the budget Report 2.13, 2.17, P26
The Stockport 8 LLP, the joint venture with English Cities Fund, to act as Development Manager and procure the building contractor Report 2.14, 2.17
Bus passengers in Stockport, who will see no change in bus services during the transition Report 2.13
Future residents of 435 new homes in Stockport 8 Phase 1 Report 2.1, 2.5
Timeline
October 2023: The Stockport 8 LLP was incorporated between the Council and English Cities Fund Report 2.4
January 2025: Preferred contractor selected for Stockport 8 Report 2.5
November 2025: £41.3m of Good Growth funding secured from GMCA, and completion of Pre-construction Services Agreement Report 2.5
Late 2025: Heaton Lane car park demolished to support the project
December 2025: Planning application submitted by the LLP for the temporary relocation of the bus depot Report 2.7, 7.3
May 2026: Detailed design of the temporary depot anticipated to complete Report 2.15
August 2026: Commencement of depot works on site programmed (subject to planning, highways and vacation of Lundy site)
2026/27: Delivery of Stockport 8 Phase 1 scheduled to commence on site, starting with demolition of Daw Bank Report 2.6
2029/30: Permanent electrified TfGM bus depot anticipated to be available Report 2.6, 2.13
Up to five years: Period for which temporary planning consent has been sought Report 2.13
Plain English for the jargon
TfGM: Transport for Greater Manchester
GMCA: Greater Manchester Combined Authority
BNC: Bee Network Committee, which approves transport funding in Greater Manchester
CRSTS: City Region Sustainable Transport Settlement, the funding programme via which the temporary depot is to be funded
ECF: English Cities Fund, the joint venture partner in the Stockport 8 LLP
LLP: The Stockport 8 LLP, the joint venture vehicle between the Council and English Cities Fund
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24
Resolved
RESOLVED - (1) That subject to TfGM securing approval from the BNC, approve the Council entering into a funding agreement with GMCA as outlined in this report and using the funding to deliver the temporary bus depot. (2) That authority be delegated to the Deputy Chief Executive and the Director of Finance - Section 151 Officer, in consultation with the Cabinet Member for Economy, Regeneration & Skills to finalise the terms of the supporting legal agreements outlined in the report and Confidential Appendix 2 along with any other ancillary agreements and formally enter into the documentation required to give effect to those such terms; (3) That authority be delegated to the Assistant Director – Governance to do all things necessary or incidental to the implementation of the above-mentioned resolutions.
Word for word from the decision Stockport published for this meeting.Source: democracy.stockport.gov.uk
Report title: Stockport 8 - Temporary Bus Depot Relocation
Report to Housing, Economy & Environment Thursday, 5 March 2026 Cabinet Tuesday, 17 March 2026
Report of SMDC Managing Director: Catherine Chilvers
Cabinet Member for Economy, Regeneration & Skills
1. Summary & Purpose of Report:
1.1The Daw Bank site is currently owned by the Council and occupied by Stagecoach as an operational bus depot. The relocation of the depot is necessary to unlock Stockport 8 Phase 1 starting on site and the delivery of 435 new homes.
1.2In December 2025 a planning application was submitted by Stockport 8 LLP for the temporary relocation of the operational bus depot from Daw Bank to two nearby sites on Heaton Lane and Lundy, Chestergate.
1.3It is intended that the project delivery costs associated with the new facilities will be funded via Greater Manchester Combined Authority (GMCA) under the CRSTS programme and governed by the Bee Network Committee (BNC). Transport for Greater Manchester (TfGM) will shortly seek BNC approval to the project budget outlined in this report and for the funding to be allocated as such. The project has already been referenced at the last BNC meeting which was held on 11 December 2025.
1.4The bus depot works are anticipated to start on site in August 2026 and post completion will unlock the demolition of the current Daw Bank site and importantly enable a start on site for Stockport 8 Phase 1.
1.5Subject to TfGM securing approval from the BNC, this paper seeks Cabinet approval: 1.5.1 for the Council to enter into a funding agreement with GMCA and to use the funding to deliver the temporary bus depot via Stockport 8 LLP; and
1.5.2 to delegate authority to relevant officers to agree final terms to the suite of agreements and contracts outlined in the report needed to deliver the project.
2. Summary of Recommendations:
Cabinet is requested to:
2.1Subject to TfGM securing approval from the BNC, approve the Council entering into a funding agreement with GMCA as outlined in this report and using the funding to deliver the temporary bus depot;
2.2Delegate authority to the Deputy Chief Executive and the Director of Finance - Section 151 Officer, in consultation with the Cabinet Member for Economy, Regeneration & Skills to finalise the terms of the supporting legal agreements outlined in the report and Confidential Appendix 2 along with any other ancillary agreements and formally enter into the documentation required to give effect to those such terms;
2.3Delegate authority to the Assistant Director – Governance to do all things necessary or incidental to the implementation of the above-mentioned resolutions.
3. Any Policy Implications:
3.1There are no policy implications.
4. Alternative options considered and rejected
4.1Not to enter into a delivery funding agreement or deliver a temporary bus depot. This would delay the delivery of Stockport 8 Phase 1 until a permanent new facility is secured and delivered by TfGM, anticipated in 2029/30. Delay to the delivery of Phase 1 would result in substantial inflationary cost pressure potentially rendering the scheme unviable and would place the £41.3m GMCA Good Growth funding secured at risk. Delay and the implications to scheme viability would also impact the repayment profile of the Council’s investment to date into Stockport 8.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.