AI summaryHeatons and Reddish Area Committee recommends advertising Traffic Regulation Orders covering bus lanes and bus gates at nine sites across Stockport, funded by Transport for Greater Manchester.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to no objections in 21 days
MoneyFunded by Transport for Greater ManchesterSubject to Full Business Case approval
What happens nextCabinet Member to consider approvalThen 21-day public consultation
Who it affectsNine bus lane and bus gate sites. Across multiple Stockport wards
What was decided
The committee recommended the Cabinet Member for Parks, Highways and Transport Services approve legal advertising of the Traffic Regulation Order and Moving Traffic Regulation Order in Appendix A.
The committee added a condition that, before the orders are made, there must be further discussions with Heatons South ward councillors on the element of the scheme on Didsbury Road to Park Road.
Why
The Council has a Delivery Agreement with Transport for Greater Manchester to deliver signing and lining schemes linked to a review of bus lanes across the borough. Report P2
The scheme aims to provide a safer environment for pedestrians and other road users, and to support a healthy, safe and attractive local environment. Report 8.1, 8.2
What happens next
If the Cabinet Member approves, the orders will be legally advertised and a 21-day objection period will run; if no objections are received, the orders will be made. Report 10.1
On-site installation of updated signage and road markings is envisaged to start in Autumn 2026. Report 7.1
Options considered
Chosen: Approve legal advertising of the TROs and MTROs subject to no objections and further Heatons South councillor discussions
Implications
Financial: Costs will be met by Transport for Greater Manchester, contingent on Full Business Case approval. Report 6.1
Legal: Several existing Traffic Regulation Orders will be revoked and replaced; new waiting and loading restrictions introduced. Report P17, P31, P41, P51, P124, P188
Equalities: The scheme supports the Council's aim of promoting equal life outcomes by tackling known inequalities across the borough. Report 8.1
Staffing: Legal work will be absorbed by the in-house legal team; enforcement will be carried out by the Council's Parking Services Team as part of their everyday duties. Report 9.2
Who and where
Bus and cycle users across Stockport, including on Lancashire Hill, Travis Brow, Portwood Roundabout, Didsbury Road, Macclesfield Road, Wellington Road South, Astley Street, Chestergate and Great Edgerton Street Report P15
Heatons South ward councillors, who will be consulted further on the Didsbury Road to Park Road element
Residents and businesses near the affected streets, who will have 21 days to object during legal advertising Report 10.1
Wards crossed by the orders: Reddish South, Heatons South, Brinnington and Stockport Central, Hazel Grove Report P16, P30, P40, P94, P108, P123, P187, P199
Timeline
2026-06-15: Area Committee recommends approval to advertise the TROs
Autumn 2026: On-site installation of updated signage and road markings envisaged to start, subject to approvals and TRO advertising outcome Report 7.1
Plain English for the jargon
TRO (Traffic Regulation Order): A legal order made by a local authority to regulate traffic on a road, including waiting, loading and movement restrictions.
MTRO (Moving Traffic Regulation Order): A legal order used to enforce moving traffic contraventions such as banned turns, one-way streets and bus gates.
Bus gate: A short section of road that only buses, cycles and sometimes taxis may use, used to keep routes clear for public transport.
Bus lane: A lane reserved for buses, often during specific hours, to speed up bus journeys.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item23
Resolved
RESOLVED – That the Cabinet Member for Parks, Highways and Transport Services be recommended to give approval to the legal advertising for the Traffic Regulation Order and Moving Traffic Regulation Order set out in Appendix A of the report and, subject to the receipt of no objections within 21 days of the advertisement date, the subsequent making of the orders subject to further discussions with Heatons South ward councillors in relation to that element of the scheme on Didsbury Road to Park Road.
Word for word from the decision Stockport published for this meeting.Source: democracy.stockport.gov.uk
Report to Heatons & Reddish Area Committee, 20 pages
Area Committee Report Summary Sheet
Report title: Bus Lane / Gates (Signing & Lining Improvements - Proposed Traffic Regulation Orders Report to: Heatons & Reddish Monday, 15 June 2026 Stepping Hill Tuesday, 16 June 2026 Central Stockport Thursday, 18 June 2026
Cabinet Member for Parks, Highways & Transport Services
Report of Director of Place Management
1. Summary & Purpose of Report:
1 To inform the Area Committee that the Council have entered into a Delivery Agreement with Transport for Greater Manchester to pursue the Signing and Lining schemes associated with a review of several bus lanes across the Borough.
1.1To seek approval for the introduction of Moving Traffic Regulation Orders (MTROs) and Static Traffic Regulation Orders (TROs) at these sites.
2. Summary of recommendations:
2.1The Director for Place Management requests that members of the Area Committee consider and comment on this report and recommend that the Cabinet Member for Parks, Highways & Transport Services approves the legal advertising for the following Traffic Regulation Order (TRO) and Moving Traffic Regulation Order (MTRO) set out in Appendix A, and subject to no objections being received within 21 days from the advertisement date, the order can be made.
3. Alternative options considered and rejected
3.1No other alternatives were considered 4. Is any part of the report confidential, - if so, confirm below that it has been agreed and signed off by the Monitoring Officer (Vicki Bates):
4.1Not Applicable
5. Urgent Decision:
5.1Not applicable for the report
6. One Stockport One Future – which priorities of One Stockport One Future does the report support:-
☐ Good jobs and homes ☐ The Best Place to Grow Up ☐ Best Health and Care ☐ Thriving Neighbourhoods / Live Well √ ☐ Clean Green Transport √ ☐ Fair & Inclusive ☐ Climate and Nature √
7. Supporting documents
(a) Background Papers
(i) ‘There are ‘None’
(b) List of Appendices to the report
(i) Appendix A – List of Drawings (ii) Appendix B – TRO Schedules
Contact Officer Craig Peet (Traffic Engineer) at [email protected] Report title: Bus Lane / Gates (Signing & Lining Improvements) - Proposed Traffic Regulation Orders
1. Summary and purpose of the Report:
1.1To inform the Area Committee that the Council have entered into a Delivery Agreement with Transport for Greater Manchester to pursue the Signing and Lining schemes associated with a review of several bus lanes across the Borough.
1.2To seek approval for the introduction of Moving Traffic Regulation Orders (MTROs) and Static Traffic Regulation Orders (TROs) at these sites.
2. Background to the Report:
2.1In 2024, Transport for Greater Manchester (TfGM) advised officers of additional funding being made available to Stockport Council to deliver further improvements and enhancements to bus stops and road markings in the borough to compliment the Bus Pinch Point Programme. Officers obtained delegated approval to pursue these additional works and entered into a funding agreement with TfGM to develop the proposals and progress a Business Case through TfGM’s governance processes.
2.2TfGM undertook their own audits on different types of bus stops (e.g. pole only, sheltered etc.) with the ambition that these be improved via separate schemes.
2.3A review of the bus lanes across the borough commenced; and was undertaken to ensure that these sites are enforceable and compliant (e.g. correct signage and road marking etc.). Implementation of the scheme will be subject to Full Business Case approval by TfGM.
It was also noted that the bus gates and bus lanes located in close proximity to Stockport Interchange should also be reviewed once all nearby associated works are complete. Therefore, the Council have now pursued the following schemes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ward Flexibility Funding - AutiskRESOLVED – That consideration of this application for Ward Flexibility Funding be deferred to a future meeting of thi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.