RESOLVED that:- 1. The principle of reallocating of £3million LUF funds previously estimated to be required for Yarm High Street to support a broader range of interventions in Preston Park as set out in paragraph 29 of the report be agreed. 2. The challenges associated with delivering the original scope of cycle infrastructure be noted and the delivery of a single route, as set out in paragraph 26 of the report be approved. 3. The submission of a formal Project Adjustment Request into DLUHC reflecting the spend profile detailed in paragraphs 29-30 of the report be approved. 4. Delegate authority be given to agree final scheme details and any associated contracts or agreements to enable delivery of the LUF programme to the Director of Finance, Development and Regeneration in consultation with Cabinet Member for Regeneration and Housing ... view the full minutes text for item CAB/90/22
Word for word from the decision Stockton-on-Tees published for this meeting.Source: moderngov.stockton.gov.uk
This report provides an update on work undertaken since approval of Round 1 Levelling Up Funding (LUF) and seeks approval for submission of a formal request into Department for Levelling Up Homes and Communities (DLUHC) to reprofile and reallocate funding across the approved programme of interventions.
REASONS FOR RECOMMENDATION(S)/DECISION(S)
To enable the delivery of interventions under the Levelling Up Fund Round 1 umbrella to reflect public consultation and now that a greater level of detail across all approved interventions within the Round 1 programme has been developed and understood.
Recommendations
1. Cabinet agree to the principle of reallocating of £3million LUF funds previously estimated to be required for Yarm High Street to support a broader range of interventions in Preston Park as set out in paragraph 29
2. Cabinet note the challenges associated with delivering the original scope of cycle infrastructure and approve the delivery of a single route, as set out in paragraph 26
3. Cabinet approve the submission of a formal Project Adjustment Request into DLUHC reflecting the spend profile detailed in paragraphs 29-30
4. Cabinet delegate authority to agree final scheme details and any associated contracts or agreements to enable delivery of the LUF programme to the Director of Finance, Development and Regeneration in consultation with Cabinet Member for Regeneration and Housing and Director of Corporate Services
DETAIL
Levelling Up Fund Scope
1. Following the report to Cabinet in July 2022, work has been ongoing to develop a greater level of detail around the agreed interventions under the LUF Round 1 programme as well as further engagement with the public to help refine options for Yarm High Street. This document was classified as: OFFICIAL
2. The approved LUF programme at approval in 2021 saw £20million split across Preston Park, Museum and Grounds (£9m), Yarm High Street (£6.5m) and cycle infrastructure (£4.5m) supplemented by co funding from Council funds and Yarm Town Council.
Yarm High Street - Public Realm Improvement Scheme
3. An initial round of public consultation was undertaken in August 2022, which sought to gather feedback on local priorities and sensitivities relating to how people perceive, use and access Yarm High Street.
4. In-person consultation sessions were held in Yarm Library and an online consultation form was available on the Council’s website. Both consultation methods were promoted widely on social media, the Council’s website and were included in an invitation that was posted to all households in the Yarm ward. Upon completion of the consultation, feedback was analysed giving a total of 205 respondents, the majority of which were residents of Yarm.
5. The results, published in October 2022, demonstrated that the top five improvements people wanted to see are: improving footpaths, reducing street clutter, adding more planting, improving connections and accessibility to the River Tees and providing more seating and places to rest.
6. The findings from the initial public consultation were analysed and used to shape and develop a package of concept designs for Yarm High Street that were presented for a second round of consultation in December 2022.
7. The consultation provided the opportunity for members of the public to share their views on the concept designs which focussed on a number improvements on the High Street and surrounding areas reflecting the priorities identified from the first round of consultation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Stockton-on-Tees Plan – Progress 2026STOCKTON-ON-TEES BOROUGH COUNCIL CABINET INFORMATION ITEM PROFORMA Cabinet Meeting .....................................
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.