24/1351/FUL Land to The West of Thornaby Pavilion, Thornaby, TS17 9EW Erection of a leisure centre incorporating a gym and swimming pool, along with a link bridge to provide a connection to the existing Thornaby Pavilion, with associated access, parking and infrastructure.
ApprovedPlanning6 papers
Planning Committee approved this item on Wednesday 4 December 2024. Below is the council's own wording, with the papers it was decided on.
RESOLVED that planning application 24/1351/FUL be approved subject to the following conditions and informatives; 01 Time Limit The development hereby permitted shall be begun before the expiration of three years from the date of this permission. 02 Approved Plans The development hereby approved shall be in accordance with the following approved plan(s); Plan Reference Number Date Received THP-RYD-00-00-DDR-A-3000-S2-P12 31 July 2024 THP-RYD-00-01-DDR-A-3001-S2-P12 31 July 2024 THP-RYD-00-ZZ-DDR-A-3002-S2-P7 31 July 2024 THP-RYD-00-ZZ-DDR-A-3600-S2-P7 31 July 2024 THP-RYD-00-ZZ-DDR-A-3800-S2-P2 31 July 2024 THP-RYD-00-ZZ-DDR-A-3850-S2-P2 31 July 2024 THP-RYD-XX-XX-LSH-A-0002-S2-P01 31 July 2024 THP-BGP-02-00-DDR-C-2137_P01 31 ... view the full minutes text for item P/46/24
Word for word from the decision Stockton-on-Tees published for this meeting.Source: moderngov.stockton.gov.uk
Planning permission is sought for the erection of a leisure centre, which will incorporate a gym and swimming pool, along with a link bridge at first floor to connect to the existing Thornaby Pavilion leisure facilities, together with associated access, parking and infrastructure.
The application is within the centre of Thornaby, in the designated district centre, on a parcel of previously developed, brownfield land. The redevelopment of the site for leisure purposes, would be commensurate with the surrounding land uses, therefore the principle of development in this location is considered acceptable.
The application has not generated any letters of objection following neighbour consultations and no objections have been raised by statutory consultees. The application has been called to Planning Committee for determination as the application has been made by Stockton Borough Council and falls outside of Officers scheme of delegation.
The application has been considered in full and it is considered that the development would not result in any significant conflict with the policies of the Local Plan or relevant chapters of the NPPF and there are no technical reasons why the proposed scheme would be deemed unacceptable in planning terms in which to justify a refusal of the application.
Recommendation
That planning application 24/1351/FUL be approved subject to the following conditions and informatives;
Time Limit 01 The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: By virtue of the provision of Section 91 of the Town and Country Planning Act 1990 (as amended). This document was classified as: OFFICIAL
Approved Plans 02 The development hereby approved shall be in accordance with the following approved plan(s);
Plan Reference Number Date Received THP-RYD-00-00-DDR-A-3000- 31 July 2024 S2-P12 THP-RYD-00-01-DDR-A-3001- 31 July 2024 S2-P12 THP-RYD-00-ZZ-DDR-A-3002- 31 July 2024 S2-P7 THP-RYD-00-ZZ-DDR-A-3600- 31 July 2024 S2-P7 THP-RYD-00-ZZ-DDR-A-3800- 31 July 2024 S2-P2 THP-RYD-00-ZZ-DDR-A-3850- 31 July 2024 S2-P2 THP-RYD-XX-XX-LSH-A-0002- 31 July 2024 S2-P01 THP-BGP-02-00-DDR-C- 31 July 2024 2137_P01 THP-BGP-02-00-DDR-C- 31 July 2024 2138_P01 THP-BGP-02-00-DDR-C- 31 July 2024 2139_P01 THP-RYD-XX-XX-DR-L-2001-S2- 31 July 2024 P1 THP-RYD-XX-XX-DR-L-2100-S2- 31 July 2024 P3 THP-RYD-XX-XX-DR-L-2110-S2- 31 July 2024 P1 THP-RYD-XX-XX-DR-L-2120-S2- 31 July 2024 P1 THP-RYD-XX-XX-DR-L-2701-S2- 31 July 2024 P1 THP-RYD-XX-XX-DR-L-7000-S2- 31 July 2024 P1 THP-RYD-ZZ-ZZ-DDR-A-0100- 31 July 2024 S2-P3 THP-BGP-02-00-DDR-C- 23 October 2024 2131_P04 THP-BGP-02-00-DDR-C- 23 October 2024 2132_P04 THP-BGP-02-00-DDR-C- 23 October 2024 2133_P02 THP-BGP-02-00-DDR-C- 23 October 2024 2139_P02 THP-BGP-02-XX-TRP-C- 23 October 2024 2023_REV002 This document was classified as: OFFICIAL
Reason: To define the consent.
External Materials 03 The development shall be carried out in accordance with the external materials as detailed in the submitted or otherwise approved ‘Planning Exterior Elevation Building Material Schedule’, reference ‘THP-RYD-XX-XX-LSH-A-0002-S2-P01’, submitted 31.07.24
Reason: In the interest of visual amenity and in accordance with Policy SD8 of the Stockton on Tees Local Plan and Chapter 12 of the National Planning Policy Framework.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
24/1351/FUL Land to The West of Thornaby Pavilion, Thornaby, TS17 9EW Erection of a leisure centre incorporating a gym and swimming pool, along with a link bridge to provide a connection to the existing Thornaby Pavilion, with associated access, parking and infrastructure.Report
P/46/2424/1351/FUL Land to The West of Thornaby Pavilion, Thornaby, TS17 9EW Erection of a leisure centre incorporating a gym and swimming pool, along with a link bridge to provide a connection to the existing Thornaby Pavilion, with associated access, parking and infrastructure.This decision
24/1351/FUL Land to The West of Thornaby Pavilion, Thornaby, TS17 9EW Erection of a leisure centre incorporating a gym and swimming pool, along with a link bridge to provide a connection to the existing Thornaby Pavilion, with associated access, parking and infrastructure.This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.