Stockton-on-Tees Borough Council
Cabinet, Thursday 23 April 2026 at 5.00pm

Strategic Asset Management Plan (SAMP) 2025-2030 - Implementation Update

Approved Executive 2 papers

AI summaryStockton-on-Tees Cabinet approves updated Strategic Asset Management Plan 2025-2030, with £430,000 in disposal receipts already received and a further £2,600,000 estimated from pending sales.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUpdated plan strengthens Corporate Landlord Model
Money£430,000 received; £2,600,000 estimatedFrom surplus asset disposals already and pending
What happens nextCall in by midnight 1 May 2026Or future updates delegated to Director
Who it affectsAll wardsCouncil-wide land and property estate

What was decided

Cabinet approved the updated Strategic Asset Management Plan 2025-2030 set out in Appendix 1 of the report. Report P2

Cabinet noted key updates including strengthened strategy, policy, asset categorisation and asset challenge arrangements, and progress on disposal of surplus assets. Report P2

Cabinet delegated authority to the Director of Regeneration and Inclusive Growth, in consultation with the Leader, to approve future updates to the SAMP, with significant changes continuing to be reported to Cabinet. Report P2

Why

The updated SAMP provides a more transparent, structured and accessible strategic framework for managing the council's land and property assets.

It formalises a more straightforward asset challenge process with defined stages, asset categorisation and decision pathways.

It ensures the asset base is aligned with the Stockton-on-Tees Plan, the Medium-Term Financial Plan, regeneration objectives, inclusive growth ambitions and sustainability commitments. Report P4

What happens next

Future updates to the SAMP will be approved by the Director of Regeneration and Inclusive Growth in consultation with the Leader, with significant changes reported back to Cabinet. Report P2

Further Cabinet Member briefings will inform members of significant actions and decisions following the SAMP's adoption. Report P32

Allocation of any future capital receipts will require a Council decision in line with the constitution. Report P37

The money

  • £430,000 Total received from disposal of Ideal House, Thornaby and 18-20 Yarm Lane, Stockton Report P20, P21
  • £2,600,000 Estimated total capital receipt from assets Sold Subject to Contract and On the Market Report P26
  • £1.428m Amount already allocated in the February 2026 budget report and Council, which includes the capital receipts already received Report P36

Options considered

  • Chosen: Approve the updated SAMP 2025-2030 as recommended. Provides strengthened strategic framework, clearer asset categorisation, and more transparent decision-making aligned with corporate priorities Report P2
  • Rejected: Alternative options. None considered

Implications

  • Financial: Capital receipts already received are accounted for within the £1.428m allocated in the February 2026 budget; future receipts require a Council decision. Report P36, P37
  • Legal: All asset-related decisions under the SAMP will comply with relevant legislation and the council's constitutional and governance arrangements. Report P39
  • Equalities: An EPIA has been completed covering the 12 protected characteristics under the Equality Act 2010; the impact is neutral, with subsequent asset decisions assessed individually. Report P29, P33
  • Risk: The updated SAMP reduces risk by strengthening governance, improving asset data and providing clearer decision pathways. Report P41
  • Other: Corporate Parenting implications: the SAMP will consider the needs of children and young people, particularly through assets that support services for children and families. Report P35
  • Climate: The SAMP aligns with the council's environmental responsibility commitments and the Powering Our Future Communities and Regeneration missions. Report P30

Who and where

  • All wards across Stockton-on-Tees Report P43
  • Council service areas, which will act as corporate tenants under the Corporate Landlord Model Report P4
  • Local communities, through assets identified as community, environmental and cultural facilities Report P10, P30

Timeline

  • December 2024: Previous version of SAMP approved by Cabinet
  • February 2026: Budget report presented to Cabinet and Council allocating £1.428m Report P36
  • 23 April 2026: Cabinet decision to approve updated SAMP 2025-2030
  • Midnight, 1 May 2026: Deadline for call in of the decision

Plain English for the jargon

  • SAMP: Strategic Asset Management Plan
  • Corporate Landlord Model: Approach where ownership and strategic management of all assets is held corporately, with service areas acting as corporate tenants
  • PULSES scoring: A framework used to assess assets, with score ranges linked to decision pathways such as retain, repurpose, dispose or acquire
  • STC: Sold Subject to Contract
  • EPIA: Equality and Poverty Impact Assessment
  • POF: Powering Our Future, the council's long-term vision programme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB/122/25

Resolved

STOCKTON-ON-TEES BOROUGH COUNCIL CABINET DECISION PROFORMA Cabinet Meeting ........................................................................ 23 April 2026 1. Title of Item/Report Strategic Asset Management Plan SAMP 2025-2030 - Implementation Update 2. Record of the Decision Consideration was given to a report that presented an updated Strategic Asset Management Plan (SAMP) 2025–2030 and provided an update on its implementation. The updated Strategic Asset Management Plan (SAMP) 2025–2030 provided a strengthened strategic framework for managing the Council’s land and property estate. Building on the version previously approved by Cabinet in December 2024, this updated SAMP tightened the Council’s strategy and policy approach, strengthens the Corporate Landlord Model, enhances asset categorisation, and introduces a more structured and transparent process for asset challenges and decision-making. The updated SAMP provided greater clarity for Members, senior officers, and operational teams, ensuring that asset decisions are consistent, evidence-led, and aligned with the Council’s wider priorities, including financial sustainability, regeneration and inclusive growth, community outcomes, and environmental responsibility. RESOLVED that:- 1. The updated Strategic Asset Management Plan (SAMP) 2025–2030 as set out in Appendix 1 of the report be approved. 2. The key updates and improvements made to the SAMP since the previously approved version be noted, including strengthened strategy, policy, asset categorisation and asset challenge arrangements. 3. The progress made in implementing the SAMP be noted, particularly in relation to the disposal of surplus assets and improved asset performance through reviews. 4. Delegated authority be given to the Director of Regeneration and Inclusive Growth, in consultation with the Leader, to approve future updates to the SAMP to ensure it remains current, responsive and aligned with corporate priorities. Significant changes or departures from the agreed strategic direction will continue to be reported to Cabinet as appropriate 3. Reasons for the Decision 1. Strengthened Strategic Clarity To approve an updated SAMP that provides a more transparent, more structured and more accessible strategic framework for managing the Council’s land and property assets. 2. Improved Asset Challenge and Decision-Making To formalise a more straightforward asset challenge process, including defined stages, asset categorisation, and decision pathways, to support transparent and defensible asset decisions. 3. Alignment with Corporate Priorities To ensure the Council’s asset base is explicitly aligned with the Stockton-on-Tees Plan, the Medium-Term Financial Plan, regeneration objectives, inclusive growth ambitions and sustainability commitments. 4. Ongoing Flexibility and Responsiveness To delegate authority for future updates to the Director of Regeneration and Inclusive Growth, ensuring the SAMP remains a live and responsive strategic document. 5. Embedding the Corporate Landlord Model The transition to a Corporate Landlord approach, ensuring centralised strategic oversight, consistent standards across the estate, improved utilisation and performance and reduced duplication and inefficiency. 4. Alternative Options Considered and Rejected None 5. Declared (Cabinet Member) Conflicts of Interest None 6. Details of any Dispensations None 7. Date and Time by which Call In must be executed Midnight, 1 May 2026 Proper Officer
Word for word from the decision Stockton-on-Tees published for this meeting. Source: moderngov.stockton.gov.uk

Follow this further

Built from Stockton-on-Tees's papers

What the report saysPro

Report to Cabinet

Recommendations

It is recommended that Cabinet:

1. Approve the updated Strategic Asset Management Plan (SAMP) 2025–2030 as set out in Appendix 1. 2. Note the key updates and improvements made to the SAMP since the previously approved version, including strengthened strategy, policy, asset categorisation and asset challenge arrangements. 3. Note the progress made in implementing the SAMP, particularly in relation to the disposal of surplus assets and improved asset performance through reviews. 4. Delegate authority to the Director of Regeneration and Inclusive Growth, in consultation with the Leader, to approve future updates to the SAMP to ensure it remains current, responsive and aligned with corporate priorities. Significant changes or departures from the agreed strategic direction will continue to be reported to Cabinet as appropriate

Detail

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
April 2026: Strategic Asset Management Plan 2025-2030 Appendix.pdf /122/25Appendix 1.3 MB Download
PDF
Strategic Asset Management Plan (SAMP) 2025-2030: Implementation UpdateReport 190 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 24 attended
LE
Cllr Lisa EvansLeader, present
PB
Cllr Pauline BeallCabinet Member, present
CB
Cllr Clare BesfordCabinet Member, present
NC
Cllr Nigel CookeCabinet Member, present
RE
Cllr Richard EglingtonCabinet Member, present
PR
Cllr Paul RowlingCabinet Member, present
NS
Cllr Norma Stephenson OBECabinet Member, present
PB
Peter BellOfficer, in attendance
JA
Junita AgyapongSecretary, in attendance
MB
Cllr Marc BesfordGuest, in attendance
JB
Julie ButcherOfficer, in attendance
TC
Tracey CarterOfficer, in attendance

All 24 on the meeting page

On this subject at Stockton-on-Tees

Search all
  1. Strategic Asset Management Plan (SAMP) 2025-2030 - Implementation UpdateThis decision
  2. Strategic Asset Management PlanDecided

More from Stockton-on-Tees Cabinet

All decisions
MeetingDecisionOutcome
16 Nov 2026 Stockton-on-Tees Plan – Progress 2026STOCKTON-ON-TEES BOROUGH COUNCIL CABINET INFORMATION ITEM PROFORMA Cabinet Meeting ..................................... Agreed Open
16 Nov 2026 School Performance 2025 - 2026TOCKTON-ON-TEES BOROUGH COUNCIL CABINET INFORMATION ITEM PROFORMA Cabinet Meeting ...................................... Decided Open
16 Nov 2026 Local Account for Adults, Health and WellbeingTOCKTON-ON-TEES BOROUGH COUNCIL CABINET DECISION PROFORMA Cabinet Meeting .............................................. Decided Open
16 Nov 2026 Pride in Place Central Stockton & Portrack - update & 10-year planSTOCKTON-ON-TEES BOROUGH COUNCIL CABINET DECISION PROFORMA Cabinet Meeting ............................................. Noted Open
15 Oct 2026 Scrutiny Review of Community Participation Budget and Ward Transport Budget - Final Report of the Community Safety Select CommitteeSTOCKTON-ON-TEES BOROUGH COUNCIL CABINET DECISION PROFORMA Cabinet Meeting ............................................. Refused Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies