Executive Scrutiny Committee, Tuesday 19 May 2026 at 2.00pm

Scrutiny Review of Capital Projects

Agreed Executive 1 paper

AI summaryStockton Executive Scrutiny Committee noted the Place Select Committee's executive summary on its scrutiny review of capital projects, which recommends reviewing officer financial delegations and strengthening member engagement.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedOf Place Select Committee capital projects review
Money£245,234mAllocated to Capital Programme in November 2025
What happens nextJanuary 2027Governance effectiveness report to Select Committee
Who it affectsCapital programme governanceMembers, officers and project delivery

What was decided

The Committee agreed to note the Executive Summary of the Place Select Committee report on the scrutiny review of Capital Projects. Report P1

Why

The Place Select Committee had carried out a scrutiny review of how the Council plans, governs and delivers major capital projects, with the aim of examining processes including governance and decision-making structures. Report P1

The review found that a strong governance and oversight framework gives confidence that capital projects are value for money and deliver intended benefits, and that continued focus on governance, communication, risk management and workforce capability is needed. Report P1, P8

What happens next

Review the level of financial delegation given to officers for capital projects and take any changes through Cabinet and Council. Report P8

When making decisions, Cabinet should receive information on option appraisal, consultation and engagement, benefit identification, risk management, financial delegations, and lessons learned. Report P9

Strengthen member information and engagement through regular updates, capital programme training in Member Induction, and refreshing the Concordat for Communication and Consultation with Councillors. Report P10

Consider workforce capacity and skills for the capital programme within the People Plan, and bring a report on the effectiveness of the governance structure to the Select Committee in January 2027. Report P11, P12

The money

  • £245,234m Allocated to the Capital Programme within the Council's Medium-Term Financial Plan to 2027 Report P2
  • 64.9% Share of capital programme resources coming from grants and contributions Report P2
  • 59.52% Share of the capital budget held by Regeneration, the largest area Report P2

Implications

  • Governance: A five-stage project lifecycle framework (Foundation, Discovery, Design, Delivery, Review) with gateways has been in place since November 2024 but has not yet been tested across enough completed projects to fully evaluate its effectiveness. Report P5, P6, P7
  • Financial: Recommendation that the level of financial delegation given to officers in relation to capital projects is reviewed and any changes taken through Cabinet and Council. Report P8
  • Staffing: Recommendation that the People Plan address the need for sufficient workforce capacity and skills to support the capital programme. Report P11
  • Risk: Capital projects face unpredictable cost fluctuations from utility delays, market inflation, weather, site investigations and land acquisition, requiring flexibility in delivery and contingency allowances. Report P4, P6
  • Other: Some projects must also meet external governance such as Tees Valley Combined Authority assurance frameworks, Homes England validation, DLUHC and HM Treasury requirements, and Department of Education grant returns. Report P7

Who and where

  • Members, including Cabinet Members and Ward Members, who receive information on capital projects within their portfolios Report P7, P10
  • Council officers, including finance, legal, procurement and Assistant Directors, who sit on Project Groups, Programme Working Groups and the Placemaking Mission Board Report P6, P7
  • Residents, who stand to benefit from regeneration, infrastructure and place-based projects Report P2, P7

Timeline

  • November 2024: The current governance framework was introduced Report P7
  • November 2025: Capital Programme presented to the Committee: 17 programmes, 112 projects, £245,234m allocated to 2027 Report P2
  • February (annually): Capital Programme is agreed as part of the MTFP Budget report Report P4
  • 19 May 2026: Executive Scrutiny Committee noted the Executive Summary
  • January 2027: Officers to report on the effectiveness of the governance structure to the Select Committee Report P12

Plain English for the jargon

  • MTFP: Medium-Term Financial Plan, the Council's multi-year budget document
  • PID: Project Initiation Document, the detailed business case produced at the Design stage
  • PMB: Placemaking (Regeneration) Mission Board, which oversees the capital programme and approves stage progression
  • RAIDL: Risks, Actions, Issues, Decisions, and Lesson Learn Log maintained by Project Groups
  • CMT / PoF: Corporate Management Team and Powering our Futures Board, which authorise capital projects for progression to Cabinet and Council
  • Section 106 / Section 278: Developer funded schemes secured through planning applications to mitigate the effect of a development
  • DLUHC: Department of Levelling Up, Housing and Communities, a funder of schemes such as Town Deal
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemESC/10/26

Resolved

AGREED that the Executive Summary be noted.
Word for word from the decision Stockton-on-Tees published for this meeting. Source: moderngov.stockton.gov.uk

Follow this further

Built from Stockton-on-Tees's papers

What the report saysPro

Report to Executive Scrutiny Committee

Summary

1. This report outlines the findings and recommendations of the Place Select Committee’s scrutiny review of Capital Projects. Capital Projects are defined as those that are carried out via capital expenditure on the creation or improvement of assets such as purchasing land or buildings as well as creating or improving existing assets such as a roads/cycleways/drainage or undertaking works to Council property assets. 2. A strong governance and oversight framework for capital projects gives confidence to both Council members and residents that they are value for money and deliver the intended benefits. The review therefore aimed to examine the processes, including the governance and decision-making structures, in delivering major capital projects.

The Capital Programme 3. The Capital Programme reflects the Council’s long-term ambition to support regeneration, manage assets, and deliver infrastructure that meets the needs of residents. Investment is targeted to meet the five strategic priorities. There is no definitive definition of what constitutes a major capital project, and while there is monetary value to consider there are also community economic and environmental impacts which may make a capital project a major project. 4. A programme is a group of linked projects that deliver a long-term objective (e.g. regeneration of an area) whereas a project is a specific action to achieve an outcome (e.g. one scheme within an area). 5. When presented to the Committee in November 2025, there were 17 programmes and 112 projects delivering place or theme-based outputs and benefits. Community, Environment, Culture, and Leisure had the biggest number of programmes (8) followed by Regeneration (4), however within those programmes Transportation had the biggest number of projects (46) followed by Community Environment and Culture & Leisure (24). 6. Funding determines what can be achieved within the capital programme, with projects unable to progress without the funding that they need. Work may commence to scope the outcomes, resource and finance requirements ahead of an allocation of capital. In November 2025 there was £245,234m allocated to the Capital Programme within the Council’s Medium-Term Financial Plan (MTFP) to 2027. Regeneration had the largest budget for capital projects (59.52%) 7. The majority of resources come from grants and contributions (64.9%) therefore many projects are dependent on successful bidding opportunities or complex negotiations with developers, and require alignment with external criteria. This document was classified as: OFFICIAL

8. Due to the breadth of the Capital Programme, there is a challenge to ensure the knowledge and skills are in place to support and deliver the programme. Staff development is important and there is investment in trainees, graduate trainees and apprenticeships. In areas where specific knowledge is required, external support from other organisations is sought.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Scrutiny Review of Capital ProjectsReport 176 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 18 attended
SW
Cllr Sylvia WalmsleyChair, present
KF
Cllr Kevin FaulksVice-Chair, present
JB
Cllr Jim BeallCommittee Member, present
MB
Cllr Marc BesfordCommittee Member, present
CC
Cllr Carol ClarkCommittee Member, apologies
SD
Cllr Stephen DoddsCommittee Member, present
LH
Cllr Lynn HallCommittee Member, present
SH
Cllr Shakeel HussainCommittee Member, present
NI
Cllr Niall InnesCommittee Member, present
MA
Cllr Mrs Ann McCoyCommittee Member, present
SM
Cllr Sufi MubeenCommittee Member, present
TR
Cllr Tony RiordanCommittee Member, present

All 18 on the meeting page

On this subject at Stockton-on-Tees

Search all
  1. Scrutiny Review of Capital ProjectsThis decision
  2. Progress Update - Scrutiny Review of Disabled Facilities GrantsAgreed
  3. Scrutiny Review of Community Participation Budget and Ward Transport Budget - Final Report of the Community Safety Select CommitteeRefused
  4. Scrutiny Review of Community Participation Budget and Ward Transport BudgetAgreed
  5. People Select Committee Scrutiny Review of Post 16 ProvisionRefused
  6. Children and Young People Select Committee Scrutiny Review of Additionally Resourced SEND ProvisionNoted

More from Stockton-on-Tees Executive Scrutiny Committee

All decisions
MeetingDecisionOutcome
21 Jul 2026 Medium Term Financial Plan (MTFP) Outturn March 2026AGREED that the report be noted. Agreed Open
21 Jul 2026 Scrutiny Review of Post 16 EducationAGREED that the Executive Summary be noted. Agreed Open
21 Jul 2026 Scrutiny Review of Additionally Resourced SEND ProvisionAGREED that the Executive Summary be noted. Agreed Open
21 Jul 2026 Forward PlanAGREED that the be noted. Agreed Open
21 Jul 2026 Chairs' UpdatesAGREED that the Chairs’ Updates be noted. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies