Place Select Committee, Monday 15 June 2026 at 4.00pm

Scrutiny Review of Governance of Capital Projects

Agreed Committee 2 papers

AI summaryPlace Select Committee approves action plan on governance of capital projects, covering financial delegations, member briefings, workforce capacity and a framework review, with a progress update due in January 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedFive recommendations on capital project governance
MoneyNot stated
What happens nextProgress update in January 2027Deadline for Concordat refresh to be circulated
Who it affectsCapital project officers and membersStockton-on-Tees capital programme

What was decided

The Committee approved the Action Plan arising from the scrutiny review of governance of capital projects. Report P2

Members asked for a deadline date to be circulated for refreshing the Concordat for Communication and Consultation with Councillors. Report P7

A progress update on the action plan will be provided in January 2027.

Why

The plan responds to recommendations from a scrutiny review of how the Council governs its capital projects, covering financial delegations, member information, workforce capacity and framework effectiveness. Report P2, P3, P4, P5, P7, P8

It aims to ensure that decision making on capital projects is proportionate to the scale, complexity and funding profile of the programme, and that members get consistent, structured information. Report P3, P4, P5, P7

What happens next

The Monitoring Officer and Section 151 Officer will review existing financial delegations on capital projects by October 2026, with any changes taken through Cabinet and Council. Report P3

The Director of Regeneration and Inclusive Growth and Director of Corporate Services will review Cabinet report guidance by December 2026, so reports cover option appraisal, engagement, benefits, risk, delegations and lessons learned. Report P4

The Programme Management Office will carry out a formal review of the capital governance framework and report back to Place Select Committee in January 2027. Report P8, P9, P10

Options considered

  • Chosen: Approve the Action Plan as presented. Committee agreed the plan responds to the scrutiny review and set a progress update for January 2027. Report P2
  • Chosen: Set a deadline for refreshing the Concordat for Communication and Consultation with Councillors. Members wanted a clear timetable for the Concordat refresh linked to member engagement on significant capital projects. Report P7

Implications

  • Governance: Any changes to financial delegations on capital projects will need Cabinet and Council approval under constitutional processes. Report P3
  • Governance: Revised Cabinet report guidance is expected to make information on option appraisal, risk, benefits, delegations and lessons learned more consistent across significant capital project reports. Report P4
  • Staffing: Workforce planning under the People Plan will be reviewed to make sure project management, commercial, procurement, engineering, design, finance and assurance skills are in place, with succession planning considered. Report P7
  • Risk: The Programme Management Office review will look at compliance, gateway arrangements, assurance, lessons learned and continuous improvement once enough projects have gone through the full lifecycle. Report P8, P10
  • Other: The Concordat for Communication and Consultation with Councillors will be refreshed to clarify expectations on information flow to members, especially Ward Members, on significant capital projects. Report P5, P7

Who and where

  • Monitoring Officer and Section 151 Officer, leading the review of financial delegations Report P3
  • Directors and Assistant Directors preparing Cabinet reports on significant capital projects Report P4
  • All councillors, particularly Ward Members, receiving information on capital projects in their areas Report P5, P7
  • Officers in the Programme Management Office, project leads and Democratic Services supporting member engagement on the capital programme Report P5, P8, P10
  • Place Select Committee, which will receive the framework review report in January 2027 Report P8, P9, P10

Timeline

  • October 2026: Target completion of the review of financial delegations on capital projects. Report P3
  • December 2026: Target date for revised Cabinet report guidance on significant capital projects to be issued. Report P4
  • January 2027: Progress update on the action plan to be provided to Place Select Committee.
  • January 2027: Target date for the Programme Management Office to report the formal review of the capital governance framework to Place Select Committee. Report P8, P9, P10
  • March 2027: Target date for the workforce review under the People Plan to complete and have actions incorporated into delivery arrangements. Report P7

Plain English for the jargon

  • Capital programme: The Council's planned spending on long term assets and infrastructure projects.
  • Concordat: An agreement, here the Council's Concordat for Communication and Consultation with Councillors on capital projects.
  • Section 151 Officer: The Council's designated chief finance officer, responsible for financial administration.
  • Programme Management Office: The team that oversees and supports delivery of the Council's capital projects.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPLA/17/26

Resolved

AGREED that: the Action Plan be approved a deadline date for refreshing the Concordat for Communication and Consultation with Councillors be circulated a progress update be provided in January 2027.
Word for word from the decision Stockton-on-Tees published for this meeting. Source: moderngov.stockton.gov.uk

Follow this further

Built from Stockton-on-Tees's papers

What the report saysPro

Report to Place Select Committee

This document was classified as: OFFICIAL

ACTION PLAN: Review of Governance of Capital Projects

No. Recommendation Proposed Actions / Progress Success Measures Responsibility Date 1 The level of financial delegation given to A review will be undertaken of the Completion of the review and Monitoring Officer October 2026 officers in relation to capital projects is operation of the Council’s existing financial implementation of any and Section 151 reviewed and any potential changes be delegations in relation to capital projects. approved constitutional Officer. taken through Cabinet and Council. This will include consideration of approval amendments. thresholds, consultation requirements, escalation arrangements and decision making responsibilities to ensure that the current framework remains proportionate and appropriate having regard to the scale, complexity and funding profile of the Council’s capital programme. Any proposed amendments arising from the review will be reported through the Council’s constitutional governance processes for consideration by Cabinet and Council.

2 When making a decision Cabinet Existing Cabinet report guidance and Revised guidance issued and Director of December receive information that addresses the report templates will be reviewed to ensure evidence of consistent Regeneration and 2026 following: that reports relating to significant capital consideration of these Inclusive Growth • option appraisal projects provide members with matters within future Cabinet and Director of • public and stakeholder proportionate and relevant information reports relating to significant Corporate consultation and engagement regarding option appraisal, stakeholder capital projects. Services. • benefit identification engagement, intended project outcomes • risk management and benefits, key project risks, governance • financial delegations arrangements, proposed onward decision • lessons learned making arrangements and, where from previous projects where appropriate, lessons learned from appropriate comparable projects. The revised guidance will be reinforced through officer briefing and existing report quality assurance arrangements.

3 Member information for and A more structured approach to member Regular member briefing Directors, Assistant Ongoing engagement of the capital programme is engagement in relation to the capital arrangements established, Directors, Project strengthened by: programme will be developed. This will capital programme Leads, Democratic include periodic programme updates for governance incorporated into Services and the This document was classified as: OFFICIAL

ACTION PLAN: Review of Governance of Capital Projects

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Action Plan: Governance of Capital Projects /17/26Report 118 KB DownloadRead as text
PDF
Scrutiny Review of Governance of Capital ProjectsReport 146 KB Download

At this meeting

Whole meeting

Who was there

8 of 15 attended
JB
Cllr Jim BeallChair, present
SN
Cllr Steve NelsonVice-Chair, present
SD
Cllr Stephen DoddsCommittee Member, present
SM
Cllr Sufi MubeenCommittee Member, present
DR
Cllr David ReynardCommittee Member, present
TR
Cllr Tony RiordanCommittee Member, present
TS
Cllr Ted StrikeCommittee Member, apologies
MS
Cllr Marilyn SurteesCommittee Member, present
SW
Cllr Sylvia WalmsleyCommittee Member, present
NB
Neil BrammaOfficer, in attendance
SD
Stephen DonaghyOfficer, in attendance
JA
Junita AgyapongSecretary, in attendance

All 15 on the meeting page

On this subject at Stockton-on-Tees

Search all
  1. Scrutiny Review of Governance of Capital ProjectsThis decision
  2. Progress Update - Scrutiny Review of Disabled Facilities GrantsAgreed
  3. Scrutiny Review of Community Participation Budget and Ward Transport Budget - Final Report of the Community Safety Select CommitteeRefused
  4. Scrutiny Review of Community Participation Budget and Ward Transport BudgetAgreed
  5. People Select Committee Scrutiny Review of Post 16 ProvisionRefused
  6. Children and Young People Select Committee Scrutiny Review of Additionally Resourced SEND ProvisionNoted

More from Stockton-on-Tees Place Select Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Chair's Update and Select Committee Work ProgrammeAGREED the work programme be noted. <TRAILER_SECTION> Agreed Open
14 Sep 2026 Chair's Update and Select Committee Work ProgrammeAGREED the work programme be noted. <TRAILER_SECTION> Agreed Open
13 Jul 2026 Chair's Update and Select Committee Work ProgrammeAGREED that site visits would be arranged and the work programme be noted. Agreed Open
15 Jun 2026 Chairs Update and Work Programme 2026-2027AGREED the work programme be noted and site visits arranged. Agreed Open
18 May 2026 Progress Update of Previously Agreed Recommendations - Affordable HousingAGREED that the progress update be noted and the assessment of progress be confirmed and a further update presented i... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies