What was decided
Council approved a full update of the Stockton-on-Tees Local Plan under the Planning and Compulsory Purchase Act 2004 and the Town and Country Planning (Local Planning) (England) Regulations 2026. Report P1, P6
Authority was delegated to the Director of Regeneration and Inclusive Growth, in consultation with the Cabinet Member for Housing and Transport, to publish a Notice of intention to commence and to update the Local Plan Timetable monthly, and to commence a Design Guide Supplementary Plan. Report P1
Officers were authorised to explore a Joint Tees Valley Minerals and Waste Plan with neighbouring authorities and to set up a cross-party Members working group to support the process. Report P1, P4, P28
Why
A five-year review in January 2024 concluded that a full update of the Local Plan was needed, and the Government introduced a new 30-month plan-making framework through the Levelling-up and Regeneration Act 2023 and the 2026 Regulations. Report P6
The new system requires notice of intention to commence by 31 December 2026 and publication of a Gateway 1 self-assessment by 30 April 2027, so preparatory work must start now to meet statutory milestones. Report P6, P10
SPDs can no longer be adopted after 30 June 2026, so a Design Guide Supplementary Plan is being started to replace existing SPDs. Report P25
What happens next
Publish the Notice of intention to commence and an updated Local Plan Timetable, with the notice by September 2026 and the timetable to be kept up to date monthly. Report P1, P15
Run a scoping consultation from October to November 2026, then publish a Gateway 1 self-assessment in February or March 2027, ahead of the 30 April 2027 statutory deadline. Report P10, P44
Set up the cross-party Members working group of seven councillors, with quarterly meetings, to advise on the plan through to adoption targeted for September or October 2029. Report P4, P28, P29, P44
Options considered
- Chosen: Commence a full Local Plan update under the new plan-making system. Five-year review recommended a full update, and the new framework offers a streamlined 30-month process Report P6
- Rejected: Continue work under the previous plan-making system. Government backstop and new 2026 Regulations require progress under the new system Report P6, P10
- Chosen: Prepare a Design Guide Supplementary Plan. SPDs cannot be adopted after 30 June 2026, and a design guide is considered necessary Report P25
- Chosen: Explore a Joint Tees Valley Minerals and Waste Plan with neighbouring authorities. To progress through Gateway 1 and meet statutory requirements Report P1
Implications
- Legal: The plan-making process is the sole responsibility of full Council under the constitution and is subject to statutory procedure, including a 30-month timeframe and three gateways. Report P9, P37
- Legal: The Secretary of State can intervene if statutory milestones are not met or satisfactory progress is not made. Report P7, P31
- Financial: The new Local Plan and its evidence base will be met from existing budgets, with no additional costs at this stage; resources to be kept under review. Report P31, P36
- Risk: Development of the new Local Plan is categorised as low to medium risk, controlled through existing management systems. Report P38
- Equalities: An equality impact assessment will be undertaken, with due regard to Section 149 of the Equality Act as the plan progresses. Report P33
- Staffing: Plan-making will continue to be led by the current Planning Services team, with cross-service support as needed; future delegations to officers will be sought at later stages. Report P31, P36
- Other: The cross-party Members working group of seven councillors will be advisory only, with no decision-making powers; substantive decisions remain with Cabinet and Council. Report P4, P28, P50
Who and where
- All wards in the Borough of Stockton-on-Tees Report P39
- Residents, community groups, businesses and other interested parties Report P3
- Neighbouring Local Planning Authorities across the Tees Valley Report P1
- The Ministry of Housing, Communities and Local Government (MHCLG) Report P1
- The Planning Inspectorate Report P20, P21
- Planning Services team and other council officers Report P29, P31
Timeline
- June/July 2026: Indicative start of notice of intention to commence plan preparation Report P44
- October 2026: Start of the scoping consultation Report P44
- November 2026: End of the scoping consultation Report P44
- 31 December 2026: Statutory backstop for giving notice of intention to commence Report P6, P10
- February/March 2027: Publication of Gateway 1 self-assessment Report P44
- March 2027, February 2029: Plan preparation period Report P44
- 30 April 2027: Statutory deadline to publish Gateway 1 self-assessment Report P6, P10
- September 2027 to Mid October 2027: Consultation on proposed local plan content and evidence Report P44
- November 2027: Gateway 2 submission Report P44
- October 2028 to December 2028: Consultation on proposed local plan Report P44
- February 2029: Gateway 3 submission Report P44
- March 2029: Submit plan for examination Report P44
- September/October 2029: Adoption of the new Local Plan Report P44
Plain English for the jargon
- Local Plan: The statutory development plan that sets out planning policies and proposals for the Borough.
- Gateway 1: The first statutory checkpoint in the new plan-making system, requiring a published self-assessment before formal plan preparation begins.
- Supplementary Plan: A new type of plan introduced by the Levelling-up and Regeneration Act 2023 to replace Supplementary Planning Documents (SPDs), forming part of the statutory development plan.
- SPD (Supplementary Planning Document): An older type of planning document used to support Local Plan policies; new SPDs cannot be adopted after 30 June 2026.
- MHCLG: Ministry of Housing, Communities and Local Government, the government department receiving the Local Plan Timetable and notice of intention.