Resolved
That the ICT infrastructure works are approved to Birches Head High School to provide ICT availability throughout the whole school.
(archived) Executive and Members Board approved this item on Tuesday 23 October 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
That the ICT infrastructure works are approved to Birches Head High School to provide ICT availability throughout the whole school.
1. ICT is an integral part of the Building Schools for the Future government programme and initiative. As part of the overall funding package agreed by the DCSC (Department of Children, Schools and Families) the reconstruction of a school building and ICT are integral.
2. On 30th July it was agreed that an interim contract was put in place to deliver the ICT for the first two High Schools Birches Head and Sandon.
3. New construction work for Birches Head has been carried out in two phases. Phase I completed in 2005 and Phase II completing November 2007 with earlier sub phases this year.
4. There is a proportion of the school remaining with no refurbishment work but essential to delivering the ICT across the whole school, whether new or existing, the ICT infrastructure needs to be installed throughout.
5. This report is to ratify the approval for the ICT infrastructure throughout all the school.
Implications Legal Financial Resources (include HR, Property, IT, resource) Equality and diversity Environment Risk
D:\moderngov\data\published\Intranet\C00000127\M00001135\AI00006846\ICTInfrastructureatBirchesHead0.doc page 1 of 5 EXECUTIVE AND MEMBERS’ ICT INFRASTRUCTURE WORKS TO BOARD THE EXISTING SCHOOL AT BIRCHES HEAD
Recommendation: That the ICT infrastructure works are approved to Birches Head High School to provide ICT availability throughout the whole school.
D:\moderngov\data\published\Intranet\C00000127\M00001135\AI00006846\ICTInfrastructureatBirchesHead0.doc page 2 of 5 EXECUTIVE AND MEMBERS’ ICT INFRASTRUCTURE WORKS TO BOARD THE EXISTING SCHOOL AT BIRCHES HEAD
1.0Report Purpose
1.1This reports seeks ratification for the installation of data infrastructure and associated electrical work.
2.0Key Issues
2.1‘Building Schools for the Future’ is a major Government initiative to rebuild/refurbish the secondary school estate across England and Wales to make secondary schools a fit place for learning and centres of community use for the 21st century. Stoke-on-Trent has been included in wave 1 of this programme (one of only 10 LAs out of 150), which means speedy delivery. 2.2 The appointment of an ICT Managed Service Provider for the delivery of the service across the Secondary School Estate was approved at the 22nd August 2006 Executive Meeting. This enabled detailed negotiations to commence (the procurement procedure was an ITN) and this neared conclusion in January 2007.
2.3The consolidation of two school sites at Birches Head into the one lower site meant that the new construction work was required to the existing school building to accommodation the additional pupils. Phase 1 construction was carried out in 2004 and 2005.
2.3The Phase II construction which consists of Art & Music block, classrooms and the central street enclosure has been under construction from June 2006 and will conclude in October 2007.
2.4The remaining existing school was due to be refurbished and remodelled as a later part of the BSF proposals. The secondary school re-organisation plans vary from the original concept for the Phase lll works. Until these proposals can be confirmed after the public consultation it is not appropriate to proceed with those works. This will delay the refurbishment. We are currently working through those options to finalise the plans and proceed to formal public consultation.
2.5The potential options were discussed at the BSF Board in May 2007. It was agreed not to proceed with any building proposals but to ensure that the ICT infrastructure is installed in Phase II and in the existing school to ensure ICT throughout.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ICT Infrastructure works to the existing school at Birches Head (Forward Plan Item 60/01 CS)Forward_plan | 5 pages | DownloadRead as text |
Follow (archived) Executive and Members Board at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 May 2009 | North Staffordshire Sub Regional Choice Based Lettings Scheme (Forward Plan Item 79/05 RH)To note and approve the inclusion of Stoke-on-Trent City Council with Newcastle Borough Council in the North Stafford... | Approved | Open |
| 27 May 2009 | City of CultureThat the Executive and Members Board approve in principle the recommendation that officers commence the work necessar... | Approved | Open |
| 27 May 2009 | Exclusion of the PublicResolved - That under Section 100(A )( 4) of the Local Government Act, 1972, the public be excluded from the meeting ... | Decided | Open |
| 27 May 2009 | Urgent Item of BusinessAgreed – That under Section 100(b )( 4) of the Local Government Act 1972, the following item of business be dealt wit... | Agreed | Open |
| 27 May 2009 | Transformation and Resources Overview and Scrutiny Committee - Recommendation in response to a Call-In - Proposal to re-phase and accelerate the transfer of services to the Strategic Partnership (Forward Plan Item 69/02 CR)That the Executive and Members Board re-affirm its original decision of 29 April 2009 that: Approval was given at the... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.