Older Peoples Housing and Accommodation (Forward Plan Item 62/01 CM)
AgreedExecutive1 paper
(archived) Executive and Members Board agreed this item on Tuesday 18 December 2007. Below is the council's own wording, with the papers it was decided on.
(i) That a full report is brought back in respect of the PFI decision, next steps and financial implications, once the outcome is known, expected by the end of this calendar year. (ii) That the Project Board structure currently operating for Rowan Village becomes a Programme Board for future extra care developments, the next one being the Portmeirion site. (iii) That agreement in principle is given to the Council providing gap funding towards the Portmeirion extra care scheme, once all other funding options have been explored, with a full report brought back for gap funding approval at the appropriate time. (iv) That further work is undertaken with national developers for the early development of extra care housing without Housing Corporation grant support. (v) That a selection process is established for the approval of preferred development partners in respect of future older people’s housing developments. (vi) That the bid to the Housing Corporation for a 30-unit sheltered housing development, providing culturally sensitive accommodation for older people in the Normacot area is noted, alongside the ongoing development of new bungalow provision in the City. (vii) That the concluded Older People’s Supply and Demand mapping findings are noted. (viii) That the development of a draft Older People’s Housing and Accommodation Strategy is noted, with formal consultation and strategy implementation to progress via the Older People’s Housing and Accommodation Sub-Group of the Older People’s Partnership Board, involving the relevant Overview and Scrutiny Commission.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Report to (archived) Executive and Members Board, 7 pages
Ex e c u tive a n d Me m b e rs’ B o a rd Open
Portfolio: Community Services, Equality and Key decision Yes Cohesion Forward Plan Ref: 62/01 CM
Older People’s Housing & Accommodation - Future Developments Report date: 18 December 2007 Report of: Director of Regeneration Contact officers: Alan Slater / Joanna Stanaway email: [email protected] telephone: 01782 236349 Wards Affected: All wards
Executive Summary At a time of notable activity in older people’s housing and accommodation, with a decision in respect of the Extra Care Private Finance Initiative still awaited, this report seeks to update the Executive of ongoing and future developments in supported housing and requests key decisions be taken in respect of points outlined below.
Rowan Village, Meir, is due for completion in March 2008. Taking forward the experience realised through this project, it is proposed that the existing Project Board structure is continued into future extra care schemes, to become a Programme Board for Extra Care. Furthermore, acknowledging the progress on Rowan Village, development partners for that scheme have taken the opportunity to acquire land on the former Portmeirion Pottery site in Stoke, recognising its potential for extra care housing in another proposed area of major intervention. This scheme has been programmed into the Housing Corporation Forward Allocation Pool for 2008/10, but at the current time an estimated funding gap exists. Agreement in principle is sought to the Council funding the estimated capital gap, once alternative funding sources have been approached.
Other development approaches have been made through the Housing Enabling Team, and whilst still at tentative stage, agreement is sought to explore and bring forward such options for the early development of extra care housing without Housing Corporation grant support, with an acceptance that commitment may need to be given in the form of gap funding, primarily in the form of land support. In order to continue to actively engage with future developer approaches and expedite developments alongside programmed schemes such as the PFI, authority is sought to the establishment of a selection process to draw in Registered Social Landlord partners to work as preferred development partners for older people’s supported housing.
The Executive is also asked to note the wider context in relation to older people’s housing and accommodation, with a proposal that formal consultation on the draft strategy in this respect is led through the Older People’s Housing & Accommodation Sub-Group of the Older People’s Partnership Board, involving the appropriate Overview & Scrutiny Commission.
D:\moderngov\data\published\Intranet\C00000127\M00001139\AI00007901\OlderPeoplesHousingAccomodation0.doc page 1 of 7 Executive and Members’ Board OLDER PEOPLE’S HOUSING & ACCOMMODATION - FUTURE DEVELOPMENTS
Recommendations: 1. That a full report is brought back in respect of the PFI decision, next steps and financial implications, once the outcome is known, expected by the end of this calendar year.
2. That the Project Board structure currently operating for Rowan Village becomes a Programme Board for future extra care developments, the next one being the Portmeirion site.
3. That agreement in principle is given to the Council providing gap funding towards the Portmeirion extra care scheme, once all other funding options have been explored, with a full report brought back for gap funding approval at the appropriate time.
4. That further work is undertaken with national developers for the early development of extra care housing without Housing Corporation grant support.
5. That a selection process is established for the approval of preferred development partners in respect of future older people’s housing developments.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow (archived) Executive and Members Board at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.