(archived) Executive and Members Board approved this item on Tuesday 29 January 2008. Below is the council's own wording, with the papers it was decided on.
(i) To approve the advertisement of appropriate notices. (ii) That approval is given to progress work to completion as outlined in this report, funded by an allocation of £268,000 in the City Council’s capital programme. (iii) To approve £13,000 per annum being included in the Responsive Maintenance budget for Streetscene from 2008/09 onwards. (iv) To approve £56,463 being included in the Street Lighting PFI budget for the maintenance and running costs of lighting in Swan Square until the end of the PFI (21 years)
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
The removal of the disused toilets and redevelopment of Swan Square is a recommendation of the Burslem Master Plan and Urban Design Action Plan (Atkins, 2004).
SRB6 funding has been used to provide 3 sketch designs and some of the materials needed for the scheme.
A final detailed design was determined following a public consultation and comments from relevant departments within the City Council. Planning permission for the final design was approved on 21 September 2007.
The demolition and resurfacing of the toilet block was completed in December 2007. Approval of the recommendations in this report will allow the proposed improvements, costing approximately £268,000 funded by the City Council, to be undertaken.
Implications Legal Financial Resources (include HR, Property, IT, resource) Equality and diversity Environment Risk Implications indicated here must be explained in the body of the report at section 6
page 1 of 4 Executive and Members’ Board Swan Square Improvements
Recommendations: 1. To approve the advertisement of appropriate notices.
2. That approval is given to progress work to completion as outlined in this report, funded by an allocation of £268,000 in the City Council’s capital programme.
3. To approve £13,000 per annum being included in the Responsive Maintenance budget for Streetscene from 2008/09 onwards.
4. To approve £56,463 being included in the Street Lighting PFI budget for the maintenance and running costs of lighting in Swan Square until the end of the PFI (21 years).
page 2 of 4 Executive and Members’ Board Swan Square Improvements
Report Purpose 1.1 To report the outcome of a public consultation exercise for the proposed improvements to Swan Square Burslem, and seek approval to: • Advertise any necessary notices • Undertake the proposed improvements costing approximately £268,000, funded by the City Council’s capital programme • Secure ongoing funding for maintenance of the completed project
2. Key Issues 2.1 62 people attended a public consultation held on 26 and 27 April 2007, 29 questionnaires were completed which provided comments on 3 designs for the Square. This identified that the majority of respondents were in favour of an option which incorporated the existing railings into the new design. 2.2 The questionnaire also identified some of the preferred features of the proposed designs, which included seating, trees and improved lighting. 2.3 Planning permission for the final design was approved 21 September 2007. 2.4 The main construction work is expected to begin in May 2008 and will take approximately 12 weeks. 2.5 Ongoing maintenance of the finished scheme will need additional funding included in the Street Lighting PFI and Streetscene budgets.
3. Benefits to Customers/Service Users 3.1 The improvements to Swan Square will enhance an area of Burslem town centre for visitors and residents, and provide an area suitable for outdoor events.
4. Consultations 4.1 Consultation has been undertaken with relevant departments within the City Council including the Access and Design and Conservation Teams. Urban Vision have also provided comments on the proposed designs. 4.2 A public consultation exercise identified a preferred option and features which should be included in the final design.
5. Council policy 5.1 The improvements to Swan Square will assist in the implementation of actions identified by the Burslem Master Plan (June 2004), which recommends the removal of the disused toilets (Action M7). 5.2 This project also contributes to the City Council’s corporate priority of Safer, Stronger, Cleaner and Greener Communities.
6. Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow (archived) Executive and Members Board at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.