CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Stoke-on-Trent City Council
(archived) Executive and Members Board, Tuesday 12 February 2008 at 5.30pm

Rough Sleepers - Review of Services and Report of Task and Finish Group (Forward Plan Item 64/05 RH)

Approved Executive 1 paper

(archived) Executive and Members Board approved this item on Tuesday 12 February 2008. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

(i) The Council and its partners take action to ensure that people sleeping rough and those at risk of sleeping rough have improved access to services and hostel accommodation (by approving actions 1 to 4 and 6 on page 4 of the task and finish group report) (ii) The Council and its partners take action to ensure that people at risk of rough sleeping have improved information about the associated dangers (by approving action 5 on page 4 of the task and finish group report) (iii) The Council and its partners take action to enforce legal requirements in relation to void and derelict properties and demonstrate this commitment through the early employment of a dedicated officer to lead the process(by approving action 3 on page 8 of the task and finish group report) (iv) The Council sets aside sufficient funds to cover the cost of enforcement actions up to and including prosecution of irresponsible property owners if necessary (by approving actions 4 and 5 on page 8 of the task and finish group report) The financial implications are set out against each of the actions listed above as recommended by the task and finish group, they are: Of which: YEAR TOTAL Supporting People General Fund 2007/08 £0 £0 £0* 2008/09 £435,000 £180,000 £255,000 2009/10 £250,000 £130,000 £120,000** 2010/11 £300,000 £130,000 £170,000*** * Appointment of dedicated officer this financial year to deal with void premises being used for rough sleeping. Taking account of the approval timeframe for this report it is most unlikely that an appointment can be made before the end of this financial year. However, to accelerate the programme the post could be advertised and recruited to begin in the new financial year. The cost of recruitment would be negligible and could be absorbed into current budgets. ** £120k is made up from the following elements: £40k for a dedicated officer £50k for legal action £25k for rent/service charge arrears payments for rough sleepers £5k for information (communication media across agencies to discourage rough sleeping/promote responsible landlord practice). *** £170k is made up as above plus a further £50k for legal costs (anticipating escalation of enforcement activity as new post embedded).
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to (archived) Executive and Members Board

Executive summary

This report outlines the recommendations of the officer led multi – agency task and finish group in relation to rough sleeping. At the request of the Executive, the group formed following the tragic deaths of two young people during a fire at derelict industrial premises on 3rd July 2007. The couple had been sleeping at the premises when the fire took hold and were unable to escape in time. The group was asked to bring forward recommendations on actions that the City Council and its partners could take to reduce the likelihood of a similar tragedy occurring in the future. Councillor Denver Tolley represented members on the task and finish group. To facilitate this work the group convened two sub-groups. One group considered how to improve services for people sleeping rough and so reduce the demand for derelict properties. A second group considered the issues in relation to derelict properties. The final report of the task and finish group is attached at appendix A and its recommendations are set out below for consideration and approval:

Implications Legal  Financial  Resources  (include HR, Property, IT, resource) Equality and diversity  Environment  Risk 

D:\moderngov\data\published\Intranet\C00000127\M00001709\AI00008665\EMBReportRoughSleepersAppendixAdoc10.doc page 1 Executive and Members’ Board Rough Sleepers – Review of Services and Report of Task and Finish Group

Recommendations: 1. The Council and its partners take action to ensure that people sleeping rough and those at risk of sleeping rough have improved access to services and hostel accommodation (by approving actions 1 to 4 and 6 on page 4 of the task and finish group report) 2. The Council and its partners take action to ensure that people at risk of rough sleeping have improved information about the associated dangers (by approving action 5 on page 4 of the task and finish group report) 3. The Council and its partners take action to enforce legal requirements in relation to void and derelict properties and demonstrate this commitment through the early employment of a dedicated officer to lead the process(by approving action 3 on page 8 of the task and finish group report) 4. The Council sets aside sufficient funds to cover the cost of enforcement actions up to and including prosecution of irresponsible property owners if necessary (by approving actions 4 and 5 on page 8 of the task and finish group report) The financial implications are set out against each of the actions listed above as recommended by the task and finish group, they are:

Of which: Supporting General YEAR TOTAL People Fund

2007/08 £0 £0 £0*

2008/09 £435,000 £180,000 £255,000

2009/10 £250,000 £130,000 £120,000**

2010/11 £300,000 £130,000 £170,000***

* Appointment of dedicated officer this financial year to deal with void premises being used for rough sleeping. Taking account of the approval timeframe for this report it is most unlikely that an appointment can be made before the end of this financial year. However, to accelerate the programme the post could be advertised and recruited to begin in the new financial year. The cost of recruitment would be negligible and could be absorbed into current budgets. ** £120k is made up from the following elements: £40k for a dedicated officer £50k for legal action £25k for rent/service charge arrears payments for rough sleepers £5k for information (communication media across agencies to discourage rough sleeping/promote responsible landlord practice).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Rough Sleepers: Review of Services and Report of Task and Finish Group (Forward Plan Item 64/05 RH)Forward_plan 275 KB DownloadRead as text

More from Stoke-on-Trent (archived) Executive and Members Board

All decisions
MeetingDecisionOutcome
27 May 2009 North Staffordshire Sub Regional Choice Based Lettings Scheme (Forward Plan Item 79/05 RH)To note and approve the inclusion of Stoke-on-Trent City Council with Newcastle Borough Council in the North Stafford... Approved Open
27 May 2009 City of CultureThat the Executive and Members Board approve in principle the recommendation that officers commence the work necessar... Approved Open
27 May 2009 Exclusion of the PublicResolved - That under Section 100(A )( 4) of the Local Government Act, 1972, the public be excluded from the meeting ... Decided Open
27 May 2009 Urgent Item of BusinessAgreed – That under Section 100(b )( 4) of the Local Government Act 1972, the following item of business be dealt wit... Agreed Open
27 May 2009 Transformation and Resources Overview and Scrutiny Committee - Recommendation in response to a Call-In - Proposal to re-phase and accelerate the transfer of services to the Strategic Partnership (Forward Plan Item 69/02 CR)That the Executive and Members Board re-affirm its original decision of 29 April 2009 that: Approval was given at the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies