Bridge Maintenance Contract 2008/09 (Forward Plan Item 64/03 RH)

Decided Executive 1 paper

(archived) Executive and Members Board decided this item on Tuesday 26 February 2008. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

(i) That the existing 2007/08 Bridge Maintenance Contract with Accord Operations Limited be extended for a further four months up to 31 July 2008. (ii) That the 2008/09 programme of highway bridge strengthening and structural maintenance works and minor routine maintenance works to highway structures be undertaken.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to (archived) Executive and Members Board

Ex e c u tive a n d Me m b e rs’ B o a rd Open

Portfolio: Regeneration Key decision Y

Forward Plan Ref: 64/03RH

Bridge Maintenance Contract 2008/09 Report date: 26 February 2008 Report of: Director of Regeneration Contact officer: Chris Mayer email: [email protected] telephone: 01782 231930 Wards Affected: All

Executive Summary The current Annual Contract for Bridge Maintenance Works expires on 31 March 2008. The works included in this Contract include bridge strengthening and structural maintenance works, together with smaller routine maintenance works to all types of highway structures. The Annual Contract is currently being carried out by Accord Operations, who have won this tender for the past five years. Extension of the existing tender for a further four months would enable the review and development of modern and alternative forms of Contract for future years.

Implications Legal Financial  Resources (include HR, Property, IT, resource) Equality and diversity Environment Risk  Implications indicated here must be explained in the body of the report at section 6

D:\moderngov\data\published\Intranet\C00000127\M00001143\AI00009028\Bridgemaintenance0.doc page 1 of 4 Executive and Members Board Bridge Maintenance Contract 2008/09

Recommendations: That the existing 2007/08 Bridge Maintenance Contract with Accord Operations Limited be extended for a further four months up to 31 July 2008.

That the 2008/09 programme of highway bridge strengthening and structural maintenance works and minor routine maintenance works to highway structures be undertaken.

D:\moderngov\data\published\Intranet\C00000127\M00001143\AI00009028\Bridgemaintenance0.doc page 2 of 4 Executive and Members Board Bridge Maintenance Contract 2008/09

1. Report Purpose 1.1 This report seeks to extend the existing Bridge Maintenance Contract for a further four months up to 31 July 2008.

2. Key Issues 2.1 The current Annual Bridge Maintenance Contract expires on 31 March 2008. The works included in this Contract include bridge strengthening and structural maintenance works, together with smaller routine maintenance works to all types of highway structures. These works are identified and prioritised following the undertaking of a formal structural assessment and inspection process. 2.2 For the last five years, the Contract has been won by Accord Operations Limited, operating from their local base in Leek. They have carried out the works during this period to a good standard and to both programme and budget. The costs of the new works will be derived by applying an appropriate index related increase to rates in the previous tender. 2.3 It is intended to undertake a review of the most appropriate forms of contract to more efficiently deliver these works in the future. More modern and alternative forms of contract can potentially offer measurable efficiency savings over the current form of procurement. However, it will take approximately four months to review and put a new form of contract into place. 2.4 Permission is sought to extend the existing Contract with Accord for a further four months up to 31 July 2008.

3. Benefits to Customers/Service Users 3.1 Extension of the existing Contract will enable the staff resources and fees which would have been used to re-tender, to instead be used for the review and development of a more modern form of contract.

4. Consultations 4.1 Consultations will be carried out with British Waterways, the Environment Agency, Network Rail and other affected stakeholders for individual sites as required, with the Ward Councillors and AIT Teams being kept informed as schemes are developed and progressed to completion.

5. Council policy 5.1 Extension of the existing Contract reflects the aims of best value and good management practice, through efficient and effective use of available finance.

6. Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bridge Maintenance Contract 2008/09 (Forward Plan Item 64/03 RH)Forward_plan 80 KB DownloadRead as text

More from Stoke-on-Trent (archived) Executive and Members Board

All decisions
MeetingDecisionOutcome
27 May 2009 North Staffordshire Sub Regional Choice Based Lettings Scheme (Forward Plan Item 79/05 RH)To note and approve the inclusion of Stoke-on-Trent City Council with Newcastle Borough Council in the North Stafford... Approved Open
27 May 2009 City of CultureThat the Executive and Members Board approve in principle the recommendation that officers commence the work necessar... Approved Open
27 May 2009 Exclusion of the PublicResolved - That under Section 100(A )( 4) of the Local Government Act, 1972, the public be excluded from the meeting ... Decided Open
27 May 2009 Urgent Item of BusinessAgreed – That under Section 100(b )( 4) of the Local Government Act 1972, the following item of business be dealt wit... Agreed Open
27 May 2009 Transformation and Resources Overview and Scrutiny Committee - Recommendation in response to a Call-In - Proposal to re-phase and accelerate the transfer of services to the Strategic Partnership (Forward Plan Item 69/02 CR)That the Executive and Members Board re-affirm its original decision of 29 April 2009 that: Approval was given at the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies