Term Tenders for Carriageway Resurfacing, Minor Works and Thermoplastic Road Markings (Forward Plan Item 65/01 RH)
ApprovedExecutive1 paper
(archived) Executive and Members Board approved this item on Tuesday 11 March 2008. Below is the council's own wording, with the papers it was decided on.
That approval be given to invite and award the best value tender from approved contractors for (a) Term Contract for Carriageway Resurfacing 2008/2009 (b) Term Contract for Minor Works 2008/2009 (c) Term Contract for Thermoplastic Road Markings 2008/2009
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Term Tenders for Carriageway Resurfacing, Minor Works, and Thermoplastic Road Markings. Report date: 11th March 2008 Report of: Assistant Director (Highways) - Regeneration Contact officer: David Stubbs / David Stevens email: [email protected] telephone: 01782 232169 Wards Affected: City wide
Executive Summary It is necessary to invite and award three new highways contracts, namely, Term Contracts for Carriageway Resurfacing works, Minor Works, and Thermoplastic Road Markings, all of which are to commence during 2008/09 financial year.
The new Term Contracts will comprise of a detailed schedule of rates for the various individual elements which make up carriageway resurfacing works; minor construction or improvement works; or road markings respectively. These will generally be priced by those tendering on a rate per square metre or linear metre of work and not against specific projects. This ‘schedule of rates’ approach is appropriate for this type of work, gives a fair degree of certainty of cost but with greater flexibility on the timing of issuing works to the Contractor and also achieves efficiency savings by not having to prepare and submit tender documentation year on year.
The lowest acceptable tender will be determined by applying the submitted rates to a pre-determined typical range of actual schemes carried out in previous years. The value of works to be carried out under each of the individual Contracts are anticipated to be in the order of £1.5M per year for the Minor Works Contract; £1.5M per year for the Carriageway Resurfacing Contract; and £180,000 per year for the Thermoplastic Road Marking Contract.
It is proposed to award the Contracts for one year, extendable, depending on performance and agreement by both parties, for up to a further 2 years for the Minor Works, and the Carriageway Resurfacing Contracts; and for up to a further 3 years for the Thermoplastic Road Marking Contract. The rates for work in subsequent years will be adjusted in accordance with nationally agreed price adjustment indices specifically produced for term contracts as published by the Department of Trade and Industry.
These Contracts have also been used previously to undertake works for other City Council Departments for works not on the highway, thereby creating additional indirect staff time savings to the council through using this procurement route.
Implications Legal Financial Resources (include HR, Property, IT, resource) Equality and diversity Environment Risk D:\moderngov\data\published\Intranet\C00000127\M00001144\AI00009261\TendersforCarriagewayResurfacingMinorWorksandThermoplasticRoadMarkings0.doc page 1 of 4 Executive and Members Board Term Tenders for Carriageway Resurfacing, Minor Works, and Thermoplastic Road Markings
Recommendations: That approval be given to invite and award the best value tender from approved contractors for
(a) Term Contract for Carriageway Resurfacing 2008/2009
(b) Term Contract for Minor Works 2008/2009
(c) Term Contract for Thermoplastic Road Markings 2008/2009
D:\moderngov\data\published\Intranet\C00000127\M00001144\AI00009261\TendersforCarriagewayResurfacingMinorWorksandThermoplasticRoadMarkings0.doc page 2 of 4 Executive and Members Board Term Tenders for Carriageway Resurfacing, Minor Works, and Thermoplastic Road Markings
Report Purpose 1.1 To obtain approval to invite tenders for and award Term Contracts for Carriageway Resurfacing, Minor Works, and Thermoplastic Road Markings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow (archived) Executive and Members Board at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.