(archived) Executive and Members Board agreed this item on Wednesday 3 December 2008. Below is the council's own wording, with the papers it was decided on.
The City Council supports the RSS Phase 2 Revisions Preferred Option, subject to adequate infrastructural investment being brought forward to secure delivery of agreed regeneration programmes. That the City Council’s comments regarding the Nathaniel Lichfield and Partners technical evidence as set out in paragraph 3.4 of this report form the basis of the City Council’s response to consultation and evidence at the forthcoming public inquiry.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Report to (archived) Executive and Members Board, 9 pages
Recommendation
1. The City Council supports the RSS Phase 2 Revisions Preferred Option, subject to adequate infrastructural investment being brought forward to secure delivery of agreed regeneration programmes.
2. That the City Council’s comments regarding the Nathaniel Lichfield and Partners technical evidence as set out in paragraph 3.4 of this report form the basis of the City Council’s response to consultation and evidence at the forthcoming public inquiry.
Summary
1. The design and delivery of sustainable regeneration in the period to 2026 depends upon our ability to transform the quality of life and prosperity within the City of Stoke- on-Trent and the competition available for finite development within the local market area.
2. Regional Spatial Strategy, a Government policy document, provides constraints and challenges, threats and opportunities and is the template against which local planning policies and regeneration programmes must generally conform. It is part of the development plan and provides relevant policies for making development control decisions.
3. Regional Spatial Strategy (RSS) is currently subject to a Phase 2 Revision revisiting strategic planning policy in respect of homes; jobs; town centres; waste and transportation. These are all interlinked but the distribution of housing development, set within the Government policy to increase housing supply, is both a key driver and determinant of infrastructural implications.
4. The RSS planning process involves three broad stages: publication of the Preferred Option, produced as advice by the West Midlands Regional Assembly; Public Examination of Issues arising (scheduled for April 2009) and publication and ultimately
D:\moderngov\data\published\Intranet\C00000127\M00002070\AI00013359\031208WestMidlandsRSSPhase2RevisionsREPORT0.doc page 1 of 9 adoption of the Secretary of States’ policy. The RSS Preferred Option has been published and this has underpinned production of the City and Borough Council’s joint Core Spatial Strategy.
5. However, Government was unhappy with what they perceived as an inadequate, projected housing supply in the West Midlands and commissioned consultants, Nathaniel Lichfield and Partners, to explore the options for additional housing supply. The consultants published their evidence in October 2008 and this will be considered at the forthcoming RSS Examination in Public. The City Council has been invited to comment on the additional evidence.
6. The consultant’s work solely addressed the issue of additional potential housing supply. Its outputs are controversial, particularly in areas being targeted for additional growth. Locally it suggests potential for an additional 33% housing in Stoke and Newcastle over and above that set out in the Preferred Option and joint Core Spatial Strategy. The timing and distribution will be a matter for local determination as part of the review of the joint Core Spatial Strategy. No change is proposed to strategic housing targets in Staffordshire Moorlands. Stafford and East Staffordshire Borough could be asked to accommodate between 4,000–8,000 dwellings which could adversely impact upon the regeneration prospects of the North Staffordshire Major Urban Area.
7. The consultant’s work is evidence and not policy and Government Office have reserved their position until they have had the opportunity to fully study its contents. It is anticipated that RSS Phase 2 strategic development targets will be approved in 2010/11 and may be subject to legal challenge.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow (archived) Executive and Members Board at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.