Proposal to re-phase and accelerate the transfer of services to the Strategic Partnership
ApprovedExecutive1 paper
(archived) Executive and Members Board approved this item on Wednesday 29 April 2009. Below is the council's own wording, with the papers it was decided on.
Approval was given at the Executive and Members Board in July 2008 to progress the procurement of a Strategic Partner for Support Services. Following the evaluation of the Outline Solutions received from bidders in February 2009, approval is required to: 1. Re-phase the transfer of services to the Strategic Partnership i.e. move HR Shared Services, Payroll and Pensions, Creditor Payments and Performance Management (in part) from Phase 2 to Phase 1 of the project and, 2. Accelerate the transfer of services to the Strategic Partnership. Phase 2 service commencement would be brought forward from 1 April 2011 to at the latest 1 July 2010. Phase 1 service commencement would remain as planned at 1 April 2010.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Report to (archived) Executive and Members Board, 4 pages
Stoke-on-Trent City Council OPEN
Executive and Members Board
Proposal to re-phase and accelerate the transfer of services to the Strategic Partnership Date: 29th April 2009 Report of: Director of Central Services Contact officer(s): Peter Stone 01782 232736 [email protected] Portfolio Holder Resources - Councillor Kieran Clarke Wards Affected: No Ward Implications
Recommendations: Approval was given at the Executive and Members Board in July 2008 to progress the procurement of a Strategic Partner for Support Services.
Following the evaluation of the Outline Solutions received from bidders in February 2009, approval is required to:
Re-phase the transfer of services to the Strategic Partnership i.e. move HR Shared Services, Payroll and Pensions, Creditor Payments and Performance Management (in part) from Phase 2 to Phase 1 of the project and, Accelerate the transfer of services to the Strategic Partnership. Phase 2 service commencement would be brought forward from 1 April 2011 to at the latest 1 July 2010. Phase 1 service commencement would remain as planned at 1 April 2010.
Report Summary: Elected Members have been provided with regular presentations and updates as to how the project is progressing and these will continue throughout the procurement process. Reports will be presented to Elected Members later this year outlining the outcome of the evaluation process to identify a preferred bidder and make recommendations in relation to the award of the contract.
Supporting Information: Re-phase the transfer of services
The proposal is to bring forward the transfer of those transactional services that directly support the transferring services (i.e. FM, Property and ICT) to Phase 1 of the project. This proposal is detailed within the table below, with the re-phased services highlighted with an asterisk:
Report Page 1 Phase/Date Function Headcount Phase 1 ICT (including CCTV) 128 Facilities Management 226 Property 65 * HR Shared Services 30 * Payroll and Pensions/Creditor Payments 31 (including eMarketplace) * Performance & Transformation (in part, 18 including Records Management) Phase 1 Total 498 Phase 2 Contact Centre 120 Postal Service 8 Revenue and Benefits 167 Phase 2 Total 295
Accelerate the transfer of services to the Strategic Partnership
The proposed schedule for the programme would be as follows:
Phase 1 of the Strategic Partnership would be scheduled to commence on 1s April 2010, as originally planned.
Phase 2 of the Strategic Partnership would be scheduled to commence at the latest by 1st July 2010, i.e. an acceleration of at least nine months.
Bidders have suggested bringing services forward to support investment and job creation earlier in the contract
The three bids received at ISOS (Invitation to Submit Outline Solutions) stage all contain proposals for bringing forward Phase 2 services.
In relation to the Contact Centre there is a requirement to invest approximately £1m in a customer relationship management system. If approved, the investment will be funded by the strategic partner hence the council will not have to commit to this expenditure straight away. The investment will then be recovered throughout the period of the contract. An earlier transfer of the Contact Centre will enable the Strategic Partner to fast track the development of the service and support the council’s evolving customer access strategy. This will accelerate growth in this area which will help the council to meet its regeneration objectives, whilst creating employment opportunities. The bidders have expressed an interest in bringing forward the Revenues and Benefits service due to the current economic environment. This is an area of significant business growth and should provide job opportunities early in the contract.
Bringing services forward will provide greater certainty for the developer of the new Business District in Hanley
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow (archived) Executive and Members Board at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.