1 That the programme of works identified in this report be approved and used as a framework for the delivery of the 2009/10 Cycling City capital programme. 2 That in relation to the schemes outlined within this report and where required the appropriate part of the footway be removed under section 66(4) of the Highways Act 1980 and a cycle track constructed under Section 65(1). 3 That where appropriate, new or existing off-highway cycle routes be designated as a bridleway as prescribed in the Countryside Act 1968. 4 That, in relation to the schemes outlined in this report and where necessary, approval be given to enter into detailed negotiations with third party landowners to gain permission to construct schemes on third party land, and designate such schemes as bridleways, as 3 above. 5 That, in relation to the schemes outlined in this report and where necessary, approval be given to enter into detailed negotiations with third party landowners to acquire land subject to achieving value for money and funding availability. 6 That, in relation to the schemes outlined in this report and where necessary, approval be given to seek planning permission, as required, to allow schemes to progress. 7 To approve delivery of specific schemes set out in Appendix A of this report, subject to consideration by the Portfolio Holders for Regeneration and Sports and Leisure following public consultation and consultation with Ward Councillors. 8 That, where necessary to deliver this programme, tenders are sought and awarded subject to availability of funding and achieving value for money.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
1 That the programme of works identified in this report be approved and used as a framework for the delivery of the 2009/10 Cycling City capital programme.
2 That in relation to the schemes outlined within this report and where required the appropriate part of the footway be removed under section 66(4) of the Highways Act 1980 and a cycle track constructed under Section 65(1).
3 That where appropriate, new or existing off-highway cycle routes be designated as a bridleway as prescribed in the Countryside Act 1968.
4 That, in relation to the schemes outlined in this report and where necessary, approval be given to enter into detailed negotiations with third party landowners to gain permission to construct schemes on third party land, and designate such schemes as bridleways, as 3 above.
5 That, in relation to the schemes outlined in this report and where necessary, approval be given to enter into detailed negotiations with third party landowners to acquire land subject to achieving value for money and funding availability.
6 That, in relation to the schemes outlined in this report and where necessary, approval be given to seek planning permission, as required, to allow schemes to progress.
7 To approve delivery of specific schemes set out in Appendix A of this report, subject to consideration by the Portfolio Holders for Regeneration and Sports and Leisure following public consultation and consultation with Ward Councillors.
8 That, where necessary to deliver this programme, tenders are sought and awarded subject to availability of funding and achieving value for money.
Report Page 1 Report Summary:
1.1This report summarises the Cycling City outline capital programme of works for 2009/10, part of the three year Cycling City settlement (2008/09 to 2010/11) that was announced by Cycling England in June 2008.
1.2Those schemes that received approval for delivery during 2008/09 have been substantially completed and have been very well received by Cycling England.
1.3The proposed programme of Cycling City schemes will be implemented through the Highways minor works term contract.
1.4As part of the development of all schemes within the Cycling City programme, the portfolio holder, local ward councillors and neighbourhood areas will be consulted on progress and kept informed as the schemes progress. All schemes will undergo public consultation with those directly affected. Consultation with the Landscape Development Team will identify and mitigate any environmental impact, particularly in relation to the off-highway schemes.
1.5The Cycling City Capital Programme, summarised in Appendix A, has been developed in order to increase the number of people cycling within the city.
Supporting Information:
Key Issues
Background
2.1It is proposed to continue the implementation of cycling schemes across the city in support of the City’s Cycling Strategy. The City Council is committed to providing alternative and sustainable transport measures, as a long term aim to improving local accessibility, and providing an alternative means of transport to using the car. Such measures also contribute to improving air quality, increasing accessibility, improving the health of the city’s population and enhancing the opportunity for cycling as a leisure activity.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.