Cycling City Infrastructure Capital Programme 2009/10 (Forward Plan Item 79/01 RH)

Approved Executive 1 paper

Cabinet approved this item on Wednesday 22 July 2009. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

1 That the programme of works identified in this report be approved and used as a framework for the delivery of the 2009/10 Cycling City capital programme. 2 That in relation to the schemes outlined within this report and where required the appropriate part of the footway be removed under section 66(4) of the Highways Act 1980 and a cycle track constructed under Section 65(1). 3 That where appropriate, new or existing off-highway cycle routes be designated as a bridleway as prescribed in the Countryside Act 1968. 4 That, in relation to the schemes outlined in this report and where necessary, approval be given to enter into detailed negotiations with third party landowners to gain permission to construct schemes on third party land, and designate such schemes as bridleways, as 3 above. 5 That, in relation to the schemes outlined in this report and where necessary, approval be given to enter into detailed negotiations with third party landowners to acquire land subject to achieving value for money and funding availability. 6 That, in relation to the schemes outlined in this report and where necessary, approval be given to seek planning permission, as required, to allow schemes to progress. 7 To approve delivery of specific schemes set out in Appendix A of this report, subject to consideration by the Portfolio Holders for Regeneration and Sports and Leisure following public consultation and consultation with Ward Councillors. 8 That, where necessary to deliver this programme, tenders are sought and awarded subject to availability of funding and achieving value for money.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 12 pages

Recommendations

1 That the programme of works identified in this report be approved and used as a framework for the delivery of the 2009/10 Cycling City capital programme.

2 That in relation to the schemes outlined within this report and where required the appropriate part of the footway be removed under section 66(4) of the Highways Act 1980 and a cycle track constructed under Section 65(1).

3 That where appropriate, new or existing off-highway cycle routes be designated as a bridleway as prescribed in the Countryside Act 1968.

4 That, in relation to the schemes outlined in this report and where necessary, approval be given to enter into detailed negotiations with third party landowners to gain permission to construct schemes on third party land, and designate such schemes as bridleways, as 3 above.

5 That, in relation to the schemes outlined in this report and where necessary, approval be given to enter into detailed negotiations with third party landowners to acquire land subject to achieving value for money and funding availability.

6 That, in relation to the schemes outlined in this report and where necessary, approval be given to seek planning permission, as required, to allow schemes to progress.

7 To approve delivery of specific schemes set out in Appendix A of this report, subject to consideration by the Portfolio Holders for Regeneration and Sports and Leisure following public consultation and consultation with Ward Councillors.

8 That, where necessary to deliver this programme, tenders are sought and awarded subject to availability of funding and achieving value for money.

Report Page 1 Report Summary:

1.1This report summarises the Cycling City outline capital programme of works for 2009/10, part of the three year Cycling City settlement (2008/09 to 2010/11) that was announced by Cycling England in June 2008.

1.2Those schemes that received approval for delivery during 2008/09 have been substantially completed and have been very well received by Cycling England.

1.3The proposed programme of Cycling City schemes will be implemented through the Highways minor works term contract.

1.4As part of the development of all schemes within the Cycling City programme, the portfolio holder, local ward councillors and neighbourhood areas will be consulted on progress and kept informed as the schemes progress. All schemes will undergo public consultation with those directly affected. Consultation with the Landscape Development Team will identify and mitigate any environmental impact, particularly in relation to the off-highway schemes.

1.5The Cycling City Capital Programme, summarised in Appendix A, has been developed in order to increase the number of people cycling within the city.

Supporting Information:

Key Issues

Background

2.1It is proposed to continue the implementation of cycling schemes across the city in support of the City’s Cycling Strategy. The City Council is committed to providing alternative and sustainable transport measures, as a long term aim to improving local accessibility, and providing an alternative means of transport to using the car. Such measures also contribute to improving air quality, increasing accessibility, improving the health of the city’s population and enhancing the opportunity for cycling as a leisure activity.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cycling City Infrastructure Capital Programme 2009/10 (Forward Plan Item 79/01 RH)Forward_plan 12 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Stoke-on-Trent

Search all
  1. Cycling City Infrastructure Capital Programme 2009/10 (Forward Plan Item 79/01 RH)This decision
  2. Adoption of City’s Local Cycling and Walking Infrastructure Plan (LCWIP) (Notice of Decisions Reference: 2337)Agreed
  3. Tender for the Collection and Marketing of Recyclables Materials arising at the City Council’s Household Waste Recycling CentresApproved
  4. Cycling City 2008/09 ProgrammeApproved

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies