Cabinet approve the release £3million Renew funding identified in the 2008-2011 HMR allocation for the Canal Quarter Scheme to enable the site assembly, remediation and advanced infrastructure works to progress. This will be match funded (£3million) by the Homes and Communities Agency; Cabinet authorise the Director of Regeneration to negotiate and agree a funding agreement with the Homes and Communities Agency to give effect to the Heads of Terms as outlined in the report submitted to Cabinet. The Director of Regeneration is then authorised to accept the offer of match funding from the Homes and Communities Agency and enter into the funding agreement in the City Councils interest; and Cabinet authorise the Director of Regeneration in consultation with the Head of Procurement and the Homes and Communities Agency to seek tenders for the remediation and infrastructure works and to award contract(s) to the contractor(s) which offer the most economically advantageous solution to the City Council and the Homes and Communities Agency, provided they are set within the limits outlined in the report submitted to Cabinet.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Stoke on Trent City Council: c/o Civic Centre, Stoke on Trent
2. Purpose of the agreement
To bring forward the provision of infrastructure and serviced development plots specifically on the site known as The Canal Quarter. The scheme will contribute to the joint efforts of both parties in bringing forward the City Waterside scheme.
It is recognised that in bringing forward this scheme, that Renew have already invested in acquisitions and demolitions, and that this amount, together with any additional funding will be considered in any arrangement for sharing of land receipts. Specifically this will include the following:
i) expenditure on CPO acquisitions, costs and compensation payments for displaced occupiers (including that incurred by Stoke on Trent and Renew) ii) acquisition of the Bridgwater Pottery site iii) Renew investment in the installation of the new Bridge (excl. any ERDF funding) iv) Expenditure on the acquisition of that part of the Imperial Pottery site which is to be included in this site boundary v) Expenditure in relation to the remediation and provision of infrastructure of the site
3. The development
i) Remediation of the site for areas owned by SoTCC (defined in the attached plan excluding the existing and operational parts of the pottery site); ii) Provision of site infrastructure, including provision of the pedestrian north-south spine road; iii) Preparation of serviced development plots
4. Role of each party
HCA – Funding partner (£3.0m)
Renew – Funding partner [(£3.0m)], and development manager Stoke on Trent City Council – accountable body for Renew
5. Responsibilities of Development Manager (i.e. Renew)
i) To procure the design and implementation of a site remediation contract
ii) To procure the design and implementation of the on-site infrastructure, to adoptable standards under the Highways Act
iii) To obtain all permissions necessary in respect of the above.
iv) To monitor the progress on the above, and report progress/outputs to the HCA on an agreed basis. Full risk analysis must be included as part of the updates
v) To seek to procure a developer for the [first phase] of housing units to be delivered [(min 60 units)],
vi) Mechanisms for procurement of developer to be agreed with the HCA [e.g. competitive tender /public land initiative].
vii) Minimum design and quality standards to be agreed for inclusion in any briefs for the procurement of developer. Renew to monitor the performance of the selected developer to ensure the delivery of minimum quality standards for housing units.
6. Responsibilities of HCA
To provide the agreed contribution [£3.0m] to the works. The initial 60% to be transferred to Renew as project manager prior to 31/03/2010.
To seek to provide NAHP funding [currently estimated at £2.862m] from the 2011/12 bidding round [subject to availability] to support the first phase of housing delivery.
7. Land receipts
Any receipts obtained from disposal of the land under Section 5 (v) above will be split proportional to the investment made. On the basis of current/planned investment, this will be [X%] Renew, and X%[] to HCA
Any land receipt will become payable upon receipt from developer.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
117Canal Quarter /Bridgewater Potteries Masterplan - Release of Approved HMR Funding for Advanced Infrastructure Works (Forward Plan Item 058)This decision
Canal Quarter /Bridgewater Potteries Masterplan - Release of Approved HMR Funding for Advanced Infrastructure Works (Forward Plan Item 058)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.