Burslem Historic Quadrant (Forward Plan Item 064)

Decided Executive 1 paper

Cabinet decided this item on Wednesday 24 February 2010. Below is the council's own wording, with the papers it was decided on.

Item175

Resolved

That Cabinet supported the Burslem Historic Quadrant and in the first instance enable expressions of interest to be sought, as part of a soft market test, to ascertain interest from design and development partners or consortium, prior to entering into a formal European Journal Procurement Process.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet

Recommendations

1. For the Cabinet to support the Burslem Historic Quadrant and in the first instance enable expressions of interest to be sought, as part of a soft market test, to ascertain interest from design and development partners or consortium, prior to entering into a formal European Journal Procurement Process.

Report Summary:

1.1The Burslem Historic Quadrant is the most significant project contained within the Burslem Regeneration Company Delivery and Business Plans. The concept for this project was first considered by the Burslem Development Trust, was included as part of the 2004 Atkins Masterplan for Burslem as the Clayhanger Yard Development Site and further refined by the Masterplan Review conducted by Hypostyle in 2008.

1.2The project seeks to regenerate the urban block defined by Market Place to Queen Street and Swan Square to St.Johns Square including Brick House Street and Clayhanger Yard. The project will also address the usage and regeneration of key assets including the Victorian Market, Wedgwood Institute, and other publicly owned buildings within the vicinity.

1.3North Staffordshire Regeneration Partnership (NSRP) wish to take the opportunity to find a realistic deliverable option for this site with the aim of reviving the economy of Burslem Town Centre by bringing it to life and creating a thriving commercial core.

1.4The preferred development route is to launch a design and developer competition to select the most innovative and sustainable proposal for the Burslem Historic Quadrant. It has been recommended by both Stoke-on-Trent City Council Legal and Procurement that this is brought forward following a formal European Journal process. However, In the first instance to test development potential expressions of interest should be sought prior to entering into a formal procurement route.

Report Page 1 Supporting Information:

2.1Strategic Intent

Burslem Town Centre is one of the three town centres identified in the programme of ‘Enabling Town Centre Transformation’ identified as a Strategic Objective in the NSRP Business Plan, through the ‘Communities’ (Urban Centres) theme.

This programme supports the other key themes of ‘Image and Place Making’ and ‘Business and Knowledge’ and is crucial to the successful delivery of ‘Building on the Urban Core’ by ensuring the complementary regeneration of key town centres.

As a consequence the Burslem Regeneration Company Team has been established to lead the transformation of the town. The team currently support the Burslem Regeneration Company Board and reports to the NSRP.

The Burslem Regeneration Company vision is:-

“To deliver economic and social transformation of Burslem by creating a unique commercial core by promoting the town’s internationally renowned heritage”.

2.2Masterplan(s)

Stoke-on-Trent City Council and Burslem Regeneration Company jointly commissioned WS Atkins to prepare a comprehensive masterplan for Burslem and the surrounding area in 2004. This masterplan was subsequently adopted as Supplementary Planning Guidance and published in June 2004.

The masterplan sets out:- • Overall Vision and Strategic Aims • A Strategic Framework for Burslem • Urban Design Guiding Principles for key development sites • Transport and movement strategy • A Public Realm Strategy The WS Atkins Masterplan for Burslem was reviewed by Hypostyle in 2008, whereupon the original masterplan was determined to be inherently sound. In review of the Atkins Masterplan, Hypostyle Architects made recommendations and also recognised that:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Burslem Historic Quadrant (Forward Plan Item 064)Forward_plan 51 KB DownloadRead as text

At this meeting

Whole meeting

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies