Resolved
Agreed – That the report be noted and the proposed budget carry forwards of £27.1m be endorsed.
Cabinet agreed this item on Thursday 29 July 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed – That the report be noted and the proposed budget carry forwards of £27.1m be endorsed.
Stoke-on-Trent City Council OPEN
CABINET
Capital Outturn 2009/10 Date: 29th July 2010 Report of: Director of Central Services Contact officer(s): Peter Bates – Director of Resources (23) 5671 [email protected] Sarah Bourne – Financial Strategy Manager (23) 7825 [email protected] Cabinet Member Councillor Kieran Clarke (Resources) Wards Affected: All Wards
Recommendations: • That the contents of this report are noted. • That the proposed budget carry forwards of £27.1m are endorsed. 1.0 Summary
1.1This report presents the year end capital outturn for the City Council’s capital programme. The City Council’s capital programme includes both investments funded directly by the City Council, and those funded from other sources but for which the income and expenditure activity flows through ‘the books’ of the City Council.
1.2The capital programmes and projects have been prioritised to ensure that the City Council investment delivers the maximum impact against the transformational aspirations for the area. Where appropriate the City Council has maximised its use of external funding before utilising City Council resources. This ensures that the City Council is getting the best use from its resources whilst maintaining flexibility for the projects to invest when the timing and local conditions are right.
1.3A revised capital budget for 2009/10 of £143.5m was endorsed as part of the Medium Term Financial Strategy 2010/11 – 2012/13. Against this revised budget a total of £119.1m was invested by the end of the financial year.
1.4The table below summarises the capital investment by corporate priority, and this is expanded on in Sections 2 to 4. Budget Actual Variance Variance Revised spend Corporate Priority Section £'000s £'000s £'000s %
Physical Regeneration and Economic Development Section 2 73,174 64,156 (9,018) (12%) Improving the lives of vulnerable people Section 3 58,684 44,913 (13,771) (23%) Better services and value for money Section 4 11,653 10,034 (1,619) (14%) TOTAL 143,511 119,103 (24,408) (17%)
1.5The impact of this investment is enhanced through further initiatives being delivered by our
Report Page 1 partners into the sub-region. By the end of 2009/10 circa £165m of direct public and private investment had been made into the sub-region through the regeneration directorate. This investment includes capital, revenue and private sector spend invested into priorities by our regeneration partners, and not all of the monies flow through the books of the City Council.
1.6It is proposed that £27.1m of budget be carried forward into 2010/11. This is for capital projects where the timing has been rephased and the level of resources utilised by the end of the year is below the levels that were set aside in the 2009/10 budget. (section 5)
1.7A full re-forecast of the capital programme, funding streams and impact on prudential borrowing will be carried out at quarter one. This will include an update on the impact of announced cuts to capital grants and will set the foundations for a policy review on the City Council’s capital programme in light of the financial challenges facing the authority. Due to the pressures that the authority will face going forward, the mechanisms around stewardship and governance arrangements in respect of capital programmes are being reviewed and a report will be brought to Corporate Directors’ Board with proposals in due course.
2.0Physical Regeneration and Economic Development
2.1Year End Outturn
The outturn for Physical Regeneration and Economic Development was £64.2m against a revised budget of £73.2m.
Budget Actual Variance Variance Revised spend
£'000s £'000s £'000s %
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(4).xlsAppendix A | 2 pages | Download |
PDF |
Capital Outturn 2009/10Report | 6 pages | DownloadRead as text |
Follow Cabinet at Stoke-on-Trent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... | Agreed | Open |
| 3 Nov 2026 | Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... | Agreed | Open |
| 3 Nov 2026 | Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... | Agreed | Open |
| 3 Nov 2026 | Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... | Agreed | Open |
| 3 Nov 2026 | Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.